RES 81-03 SSDP FOR EAGLE HARBOURRESOLUTION NO. 81_ 03
. .
A RESOLUTION EXTENDING FOR ONE YEAR THE SHORELINE
SUBSTANTIAL DEVELOPMENT PERMIT FOR THE EAGLE HARBOUR
CONDONIMIUM
WHEREAS, Winslow Ordinance 77-1 Section 7 (1) provides for
extension of the duration of a Shorelines Substantial Development
Permit beyond the initial 5 year period upon showing of cause;
WHEREAS, Eagle Harbour Partnership, Ltd. applied by letter for
a 1 year extension;
WHEREAS, a public hearing was held on December 1 during which
testimony was heard from the developer as well as members of
the public regarding the requested extension;
NOW THEREFORE BE IT RESOLVED BY TIlE CITY COUNCIL OF THE CITY
OF WINSLOW AS FOLLOWS:
Substantial Development Permit is hereby extended with
conditions for 1 year beyond the original expiration date of
October 26, 1981 to October 26, 1982. The following conditions
are part of the 1 year extension:
1. Eagle Harbour Partnership, Ltd. shall make a good faith
effort to insure the execution of an Easement Agreement
between the Eagle Harbour Partnership, Ltd., Russell J.
Trask, the Washington Toll Bridge Authority and other
parties as may be required to April 1, 1981. This
Agreement shall include relocation of the private road
easement, maintenance of the private road, location of
a City water line easement near the north and northeast
property lines of the Eagle Harbour and Trask pmperties
and the location of a 10' public trail easement near the
north and northeast property lines of the Eagle Harbour
and Trask properties.
2. The landscaped pedestrian and bicycle walkway for the
public north and northeast property lines of the Eagle
Harbour and Trask properties to the mid span of the
bridge over the Hall Brothers slough shall be completed
by September 1, 1981, provided that events beyond the
control of Eagle Harbour Partnership, Ltd. (not including
problems in obtaining financing ) do not operate to
prevent the completion of the walkway by September
1, 1981. Plans for the bridge will be supplied by the
City of Winslow. Construction of bridge and walkway
must be as per City approved plans. All costs of the
walkway and the midspan bridge are to be borne by the
Eagle ttarbour Partnership, Ltd.,
3. A bond, in an amount sufficient to cover the completion
of the trail and water line (amount to be determined
by the City Engineer) line must be secured by Eagle
Harbour Partnership by March 1, 1981.
If any of the above conditions are not complied with by the
dates specified, the 1 year extension will become null and
void and the original expiration date of October 26, 1981 will
apply.