Ordinance No. 2021-28 Adopting the 2022 Update of the2021-2026 Six-Year CIP - Approved 101221Page 1 of 2 ORDINANCE NO. 2021-28 AN ORDINANCE of the City of Bainbridge Island, Washington, adopting the 2022 update of the 2021-2026 six-year Capital Improvement Plan. WHEREAS, in accordance with the Growth Management Act, the City of Bainbridge Island adopted a Comprehensive Plan on September 1, 1994, revised it on December 8, 2004, and completed an update on February 28, 2017; and WHEREAS, the Comprehensive Plan contains a Capital Facilities Element that establishes goals and policies for the provision and financing of capital facilities for the residents of Bainbridge Island; and WHEREAS, the Capital Facilities Element is implemented through the City’s Capital Improvement Plan, which is a six-year plan that is updated annually; and WHEREAS, the 2021-2026 update of the six-year Capital Improvement Plan addresses the goals and requirements set forth in the Growth Management Act and the Bainbridge Island Comprehensive Plan; and WHEREAS, the 2021-2026 update of the six-year Capital Improvement Plan is consistent with the Comprehensive Plan, functional plans, and adopted capital and operating budgets as stated in Policy CF 1.1 of the Comprehensive Plan; and WHEREAS, the City Council conducted public hearings on the 2021-2022 Biennial Budget on October 27, 2020 and November 10, 2020, and the 2021-2026 update of the six-year Capital Improvement Plan is a component of that budget, such that the 2021 and 2022 capital improvements identified in the Capital Improvement Plan are incorporated into the 2021-2022 Biennial Budget; and WHEREAS, the City Council is considering modifications to the 2022 Adopted Budget, including updates to the six-year Capital Improvement Plan, as attached. NOW THEREFORE, THE CITY COUNCIL OF THE CITY OF BAINBRIDGE ISLAND, WASHINGTON, DOES ORDAIN, AS FOLLOWS: Section 1. The 2022 update of the 2021-2026 six-year Capital Improvement Plan, attached as Exhibit A, is adopted as of the effective date of this ordinance. Section 2. In the event that there are instances in which the dollar amounts or timing of capital projects included in this update differ from those in other sections of the Comprehensive Plan, the amounts and timing in this update shall prevail. Page 2 of 2 Section 3. This ordinance authorizes the City Manager to reformat Exhibit A into a final edition for publication and to reformat and transmit Exhibit A to the State of Washington as the City’s annual State Transportation Improvement Program (“STIP”), as applicable. Section 4. If any section, sentence, clause, or phrase of this ordinance is held to be invalid or unconstitutional by a court of competent jurisdiction, such invalidity or unconstitutionality shall not affect the validity or constitutionality of any other section, sentence, clause, or phrase of this ordinance. Section 5. This ordinance shall take effect and be in force five (5) days from and after its passage and publication as required by law. PASSED by the City Council this 12th day of October, 2021. APPROVED by the Mayor this 12th day of October, 2021. Rasham Nassar, Mayor ATTEST/AUTHENTICATE: FILED WITH THE CITY CLERK: October 8, 2021 PASSED BY THE CITY COUNCIL: October 12, 2021 PUBLISHED: October 15, 2021 EFFECTIVE DATE: October 20, 2021 ORDINANCE NUMBER: 2021-28 Exhibit A: 2022 Update of the 2021-2026 CIP City of Bainbridge Island Total CIP (2021 - 2026) 2022 Modifications Pr i o r Y e a r s 2021 2022 2023 2024 2025 2026 2027 - 2040 Total in (1000s) Transportation Projects 5,310 1,045 50 800 - 625 1,110 - 8,941 Transportation Grants 3,072 79 - - - - - - 3,151 Non Motorized Projects 1,561 721 1,809 15 1,498 235 - - 5,838 Non Motorized Grants 925 210 1,200 - 735 220 - - 3,290 Fleet and Equipment - 1,659 270 909 486 633 684 - 4,641 Facility Projects 20,000 396 393 111 - - - - 20,900 Facility Grants - - - - - - - - - Water Projects 2,016 1,260 811 10,700 1,735 60 228 - 16,810 Water Grants - - - - - - - - - Sewer Projects 1,660 1,566 1,374 4,169 1,490 1,330 490 - 12,079 Sewer Grants - - - - - - - - - SSWM Projects 501 226 20 1,955 765 1,270 - - 4,736 SSWM Grants - 85 - 1,000 - - - - 1,085 Utility Funding 4,177 2,967 2,205 15,824 3,990 2,660 718 - 32,540 General Govt Funding 22,874 1,873 1,053 926 763 640 1,110 - 29,238 Total Project Cost Less Grants 27,051 6,498 3,528 17,659 5,239 3,933 2,512 - 66,420 Grant Totals 3,997 374 1,200 1,000 735 220 - - 7,526 TOTAL PROJECT COST . . . . . . . . . . 31,048 6,872 4,728 18,659 5,974 4,153 2,512 - 73,946 Amounts in thousands City of Bainbridge Island Transportation CIP (2021 - 2026) 2022 Modifications Project / Location Gr a n t E l i g i b l e Gr a n t A w a r d e d Gr a n t F u n d s Ge n e r a l C o m p St r t s C o m p o n e n t Wt r C o m p o n e n t Sw r C o m p o n e n t SS W M C o m p Pr i o r Y e a r s 2021 2022 2023 2024 2025 2026 2027 - 2040 Total TRANSPORTATION PROJECTS - 6-YEAR CIP Wyatt Way Reconstruction Phase 1 X X 2,516 Y Y 4,153 22 - - - - - - 4,175 Madison - Lovell Sportsman Club/New Brooklyn X X 635 Y 1,096 128 3 - - - - - 1,228 Intersection Imprv. Finch Road Improvements X - Y - 105 47 - - - - - 152 Wyatt to Sportsman Club Country Club Bulkhead Spot Repairs - 400 - - - - - - 400 at Seawall Country Club Bulkhead Reconstruction - 15 - 525 - - - - 540 at Seawall Country Club Rd Reconstruction - Y 61 325 - - - - - - 386 Past Toe Jam to Seawall Manitou Beach Rd & Bulkhead Repair - Y - - - 225 - 485 500 - 1,210 Manitou Beach Rd Winslow Way West Y - - - - - 140 610 - 750 Parfitt to Grow Ave Springbrook Fish Passage - 50 - 50 - - - - 100 Fletcher Bay Road West of New Brooklyn - City Funding 2,238 966 50 800 - 625 1,110 - 5,790 Grant Totals 3,072 79 - - - - - - 3,151 TOTALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5,310 1,045 50 800 - 625 1,110 - 8,941 Amounts in thousands Project: Wyatt Way Reconstruction Phase 1 Number:00708 Location: Madison to Lovell Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $1,279 $22 $0 $0 $0 $0 $0 $0 $1,301 Water Fund $343 $167 $0 $0 $0 $0 $0 $0 $510 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Trans. Impact Fees $358 $0 $0 $0 $0 $0 $0 $0 $358 State Grant $2,516 $0 $0 $0 $0 $0 $0 $0 $2,516 Sub-total $4,496 $189 $0 $0 $0 $0 $0 $0 $4,685 FUNDING USES (1000's) Project Management $144 $79 $223 Design/permitting $770 $770 Construction $3,582 $110 $3,692 Sub-total $4,496 $189 $0 $0 $0 $0 $0 $0 $4,685 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Capacity (level of service) improvements to the intersection of Madison Avenue and Wyatt Way, including a roundabout. Complete sidewalk and bicycle facilities on both sides of Wyatt from Madison to Lovell. Reconstruct roadway surfacing and drainage. Replace several hundred feet of aging and undersized water mains prior to road repairs. Benefit: Relieve current and future intersection congestion and ensure mobility by implementing improvements prior to development. Address a gap in non-motorized facilities to improve mobility and safety. Support businesses and employment in the downtown area. Schedule: YR1/2: design, ROW, and permitting, YR3: construction. Project: Sportsman Club Road and New Brooklyn Road Number:00715 Location: Intersection Improvements Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $540 $49 $3 $0 $0 $0 $0 $0 $593 Trans. Impact Fees $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $556 $79 $0 $0 $0 $0 $0 $0 $635 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $1,096 $128 $3 $0 $0 $0 $0 $0 $1,228 FUNDING USES (1000's) Project Management $56 $49 $3 $109 Design/permitting $208 $208 Construction $832 $79 $911 Sub-total $1,096 $128 $3 $0 $0 $0 $0 $0 $1,228 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Non-motorized and safety improvements such as sidewalks and improved crosswalks are planned for the intersection to better facilitate walking and biking to school. Benefit: Improved non-motorized safety at the intersection. Schedule: 2020: Design; 2021: Construction Project: Finch Road Improvements Number:01087 Location: Intersection Improvement Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $105 $47 $0 $0 $0 $0 $0 $152 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $105 $47 $0 $0 $0 $0 $0 $152 FUNDING USES (1000's) Project Management $5 $47 $52 Design/permitting $100 $100 Construction $0 Sub-total $0 $105 $47 $0 $0 $0 $0 $0 $152 Estimated Impact on Future Operating Budget Prior Yrs 2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Vehicular and non-motorized and safety improvements at the intersection of Finch Road and Wyatt Way, as well as non-motorized improvements along the Finch corridor from Wyatt Way to Sportsman Club Road. Benefit: Improved vehicular and non-motorized safety. Schedule: YR1: Design; Y2: Construction Project: Country Club Bulkhead Spot Repairs Number:01116 Location: Seawall on Country Club Road Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $400 $0 $0 $0 $0 $0 $0 $400 REET $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $400 $0 $0 $0 $0 $0 $0 $400 FUNDING USES (1000's) Project Management $34 $34 Design/permitting $0 Construction $366 $366 Sub-total $0 $400 $0 $0 $0 $0 $0 $0 $400 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The project consists of short-term (3-5 yr) spot repairs to the existing Country Club Road bulkhead to prevent further deterioration and erosion of the embankment until a longer-term solution is implemented. Benefit: Repairing the bulkhead will prevent further failure of the roadway. Schedule: 2020: Design and permitting; 2021: Construction Project: Country Club Bulkhead Reconstruction Number:00781 Location: Seawall on Country Club Road Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 REET $0 $15 $0 $525 $0 $0 $0 $0 $540 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $15 $0 $525 $0 $0 $0 $0 $540 FUNDING USES (1000's) Project Management $0 $37 $37 Design/permitting $15 $95 $110 Construction $0 $393 $393 Sub-total $0 $15 $0 $525 $0 $0 $0 $0 $540 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The project consists of long-term (10-15-yr) repair and replacement of the Country Club bulkhead, including the replacement of drainage facilities and repair of the adjacent roadway. Benefit: Repairing the bulkhead will prevent further failure of the roadway. Schedule: 2020: Design and permitting; 2021: Construction Project: Country Club Road Reconstruction Number:00712 Location: Toe Jam Road to the Seawall Project Description Capital Funding (1000's) Prior Yrs 2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $61 $0 $0 $0 $0 $0 $0 $0 $61 REET $0 $325 $0 $0 $0 $0 $0 $0 $325 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $61 $325 $0 $0 $0 $0 $0 $0 $386 FUNDING USES (1000's) Project Management $61 $4 $65 Design/permitting $55 $55 Construction $266 $266 Sub-total $61 $325 $0 $0 $0 $0 $0 $0 $386 Estimated Impact on Future Operating Budget Prior Yrs 2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project will repair failing roadway pavement and improve drainage conditions east of Toe Jam Road to the existing bulkhead. Benefit: Roadway preservation. Schedule: YR1: Design; YR2: Construction Project: Springbrook Fish Passage Number: Location: Fletcher Bay Road west of New Brooklyn Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $50 $0 $50 $0 $0 $0 $0 $100 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $50 $0 $50 $0 $0 $0 $0 $100 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $85 $0 $1,000 $0 $0 $0 $0 $1,085 Sub-total 0 185 0 1100 0 0 0 0 1285 FUNDING USES (1000's) Project Management $4 $50 $54 Design/permitting $181 $50 $231 Construction $1,000 $1,000 Sub-total 0 185 0 1100 0 0 0 0 1285 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The Springbrook Fish Weir/Passage project proposes to replace the existing culvert at Springbrook Creek with an open box/bridge structure and streambed restoration. Schedule: YR 1: Design City of Bainbridge Island Non-Motorized Transportation CIP (2021- 2026) 2022 Modifications Project Gr a n t E l i g i b l e Gr a n t A w a r d e d Gr a n t F u n d s Ge n e r a l C o m p St r t s C o m p Wt r C o m p Sw r C o m p SS W M C o m p Pr i o r Y e a r s 2021 2022 2023 2024 2025 2026 2027 - 2040 Total NON-MOTORIZED PROJECTS - 6-YEAR CIP High School Road Safety Improvements X X 225 248 196 - - - - - - 444 SR305 to Grow Eagle Harbor Phase II X X 700 1,020 57 2 - - - - - 1,079 Eagle Harbor Dr STO Trail Sakai Pond Connector 141 128 - - - - - - 269 SR305 at HS Rd Madison Avenue Sidewalk Improvements X X 1,410 Y - 309 1,801 - - - - - 2,110 Wyatt to High School C40 Eagle Harbor Dr Phase I X X 735 Y 95 30 7 5 755 - - - 892 Wyatt to past Bucklin Hill Lost Valley Trail X 220 - - - 10 45 235 - - 290 HOB to Fletcher Bay Rd C40 - Bucklin Ph 2 X - Y 57 - - - 698 - - - 755 Blakely - Fletcher Bay City Project Funding 636 511 609 15 763 15 - - 2,548 Grant Totals 925 210 1,200 0 735 220 - - 3,290 TOTALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,561 721 1,809 15 1,498 235 0 - 5,838 Amounts in thousands Project: High School Road Safety Improvements Number:00966 Location: SR305 to Grow Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $23 $16 $0 $0 $0 $0 $0 $0 $39 REET Fund $0 $180 $0 $0 $0 $0 $0 $0 $180 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $225 $0 $0 $0 $0 $0 $0 $0 $225 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $248 $196 $0 $0 $0 $0 $0 $0 $444 FUNDING USES (1000's) Project Management $20 $16 $36 Design/permitting $26 $26 Construction $202 $180 $382 Sub-total $248 $196 $0 $0 $0 $0 $0 $0 $444 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: Improve pedestrian safety by reconfiguring an existing mid-block crossing, adding signage and flashing beacons, and adding/moving radar feedback signs. Benefit: Increase pedestrian and other non-motorized safety. Schedule: 2020: Design; 2021 Construction Project: C40 Eagle Harbor Drive Phase 2 Number:01077 Location: Eagle Harbor shoreline to McDonald Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) REET $70 $57 $2 $0 $0 $0 $0 $0 $129 TIF $250 $0 $0 $0 $0 $0 $0 $0 $250 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $700 $0 $0 $0 $0 $0 $0 $0 $700 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $1,020 $57 $2 $0 $0 $0 $0 $0 $1,079 FUNDING USES (1000's) Project Management $40 $57 $2 $99 Design/permitting $0 Construction $980 $980 Sub-total $1,020 $57 $2 $0 $0 $0 $0 $0 $1,079 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Benefit: Safety and non-motorized transportation connectivity. Schedule: YR1: design/permitting YR2: construction. Description: Provide a 5’-wide separated shoulder from the shoreline to McDonald Ave. Project: STO Trail Sakai Pond Connector Number:00841 Location: Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $20 $0 $0 $0 $0 $0 $0 $0 $20 REET $0 $128 $0 $0 $0 $0 $0 $0 $128 Developer Donation $121 $0 $0 $0 $0 $0 $0 $0 $121 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $141 $128 $0 $0 $0 $0 $0 $0 $269 FUNDING USES (1000's) Project Management $20 $34 $54 Design/permitting $0 Construction $121 $94 $215 Sub-total $141 $129 $0 $0 $0 $0 $0 $0 $269 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2022 2023 2024 2025 2026- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project is a continuation of the paved, multi-use Sound to Olympics Trail (STO) from the Northwest corner of SR305 and High School Road to the southwest side of the Sakai Pond. The end of the paved, multi-use trail will connect with the Sakai trail on Bainbridge Island Parks property. Approximately $121,000 of the project cost was provided through the Visconsi development agreement. Benefit: Extension of the STO multi-use trail for non-motorized users. Schedule: 2020: Design; 2021: Construction Project: Madison Avenue Sidewalk Improvements Number:01088 Location: Wyatt to High School Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $74 $0 $0 $0 $0 $0 $0 $74 REET $0 $0 $601 $0 $0 $0 $0 $0 $601 TBD $0 $25 $0 $0 $0 $0 $0 $0 $25 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $210 $1,200 $0 $0 $0 $0 $0 $1,410 Sub-total $0 $309 $1,801 $0 $0 $0 $0 $0 $2,110 FUNDING USES (1000's) Project Management $24 $51 $75 Design/permitting $285 $285 Construction $1,750 $1,750 Sub-total $0 $309 $1,801 $0 $0 $0 $0 $0 $2,110 Estimated Impact on Future Operating Budget Prior Yr 2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project will widen the existing east-side sidewalk to 5-feet or greater, and include sections of landscape buffer. Driveways and ramps on the both sides will be upgraded to meet current standards. This project wil be closed and combined with the sewer project Village Basin Improvements in 2022. Benefit: The goal of the project is to better accommodate pedestrians of all ages and abilities along this heavily used corridor that currently has barriers for many users. Schedule: YR1: Design; YR2 Construction Project: C40 Eagle Harbor Drive Phase 1 Number:00968 Location: Wyatt to past Bucklin Hill Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) REET $95 $30 $7 $5 $20 $0 $0 $0 $157 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $735 $0 $0 $0 $735 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $95 $30 $7 $5 $755 $0 $0 $0 $892 FUNDING USES (1000's) Project Management $10 $30 $7 $5 $20 $72 Design/permitting $85 $85 Construction $735 $735 Sub-total $95 $30 $7 $5 $755 $0 $0 $0 $892 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Shoulder widening on both sides from the Head of the Bay and along the shoreline segment of the road. This project includes the replacement of a culvert with a fish passage culvert – see SSWM project list. Benefit: Safety and Non Motorized Transportation Connectivity. Schedule: 2023: Design; 2024: Construction Project: C40 Bucklin Hill Road Phase 2 Number:00723 Location: Blakely to Fletcher Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $57 $0 $0 $0 $698 $0 $0 $0 $755 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $57 $0 $0 $0 $698 $0 $0 $0 $755 FUNDING USES (1000's) Project Management $10 $95 $105 Design/permitting $47 $47 Construction $603 $603 Sub-total $57 $0 $0 $0 $698 $0 $0 $0 $755 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2022 2023 2024 2025 2026- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Provide shoulder widening on both sides of Bucklin Hill Road and Lynwood Center Road from Blakely Avenue to Fletcher Bay Road. There is a potential for separated paths along portions of this segment on both sides of the road. Benefit: Safety and non-motorized transportation connectivity. Schedule: YR1: Construction (in-house design) City of Bainbridge Island FLEET and EQUIPMENT CIP (2021 - 2026) 2022 Modifications Project Ge n e r a l C o m p St r t s Co m p o n e n t Wt r C o m p o n e n t Sw r C o m p o n e n t SS W M C o m p 2021 2022 2023 2024 2025 2026 Total FLEET & EQUIPMENT - 6-YEAR CIP (1000s) Police Vehicles (2)100%187 195 202 211 219 228 1,242 2020 Police Vehicles 100%80 - - - - - 80 2020 Dump Truck 50%50%276 - - - - - 276 2020 Man Lift 100%325 - - - - 325 2020 Utilities Pickup (F150)20%80%70 - - - - - 70 2020 Medium Duty Pickup 80%20%74 - - - - - 74 2020 Utilities Van 80%20%61 - - - - - 61 - Track Excavator 100%160 - - - - - 160 Medium Duty Pickup 100%66 - - - - - 66 Heavy Duty Pickup with Crane 50%50%120 - - - - - 120 Heavy Duty Pickup 80%20%115 115 Light Duty Pick Up 100%60 - - - - - 60 Light Duty Pick Up 20%20%20%20%20%65 - - - - - 65 Police Boat Trailer 100%- 34 - - - - 34 Police Motorcycle 100%- 41 - - - - 41 Vactor Truck 50%50%- - 462 - - - 462 Electric SUV 20%20%20%20%20%- - 70 - - - 70 Medium Duty Pickup 20%20%20%20%20%- - 110 - - - 110 Electric SUV 20%20%20%20%20%- - 65 - - - 65 Electric SUV 20%20%20%20%20%- - - 70 - - 70 City Hall Vehicle 100%- - - 70 - - 70 Electric SUV 100%- - - 65 - - 65 Salt Brine System 100%- - - 70 - - 70 - - - - - - - Police Boat Motor 100%- - - - 15 - 15 Heavy Duty Pickup 20%80%- - - - 119 - 119 Truck Cab and Chassis 50%50%- - - - 280 - 280 Forklift 20%20%20%20%20%- - - - - 45 45 Street Sweeper 20%80%- - - - - 325 325 Pup Trailer 50%50%- - - - - 86 86 TOTALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,659 270 909 486 633 684 4,641 Amounts in thousands City of Bainbridge Island Facilities CIP (2021 - 2026) 2022 Modifications Project Gr a n t E l i g i b l e Gr a n t A w a r d e d Gr a n t F u n d s Ge n e r a l C o m p St r t s C o m p o n e n t Wt r C o m p o n e n t Sw r C o m p o n e n t SS W M C o m p Prior Years 2021 2022 2023 2024 2025 2026 2027 - 2040 Total FACILITIES PROJECTS - 6-YEAR CIP Police and Municipal Court Building Y 20,000 - - - - - - - 20,000 City Hall Parking Lot Retrofit X Y - - - 111 - - - - 111 City Hall Security Y - 153 7 - - - - - 160 Dry Fire Sprinkler - 60 - - - - - - 60 Salt Storage Facility Y - 71 - - - - - - 71 B.I. Senior Center Renovations Y - 112 386 - - - - - 498 City Total 20,000 396 393 111 - - - - 20,900 Grant Totals - - - - - - - - - TOTALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20,000 396 393 111 - - - - 20,900 Amounts in thousands Project: Police and Municipal Court Facility Number:00724 Location: 8804 Madison Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $10,281 $0 $0 $0 $0 $0 $0 $0 $10,281 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 REET $1,719 $0 $0 $0 $0 $0 $0 $0 $1,719 Long-Term Debt $8,000 $0 $0 $0 $0 $0 $0 $0 $8,000 Sub-total $20,000 $0 $0 $0 $0 $0 $0 $0 $20,000 FUNDING USES (1000's) Project Management $200 $0 $0 $0 $0 $0 $0 $0 $200 Predesign $450 $0 $0 $0 $0 $0 $0 $0 $450 Acquisition $8,975 $0 $0 $0 $0 $0 $0 $0 $8,975 Design $672 $0 $0 $0 $0 $0 $0 $0 $672 Construction $9,703 $0 $0 $0 $0 $0 $0 $0 $9,703 Sub-total $20,000 $0 $0 $0 $0 $0 $0 $0 $20,000 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating $100 $100 $100 $100 $100 $100 $1,400 $2,000 Debt Service $482 $510 $508 $510 $511 $507 $507 $6,620 $10,155 Sub-total $482 $610 $608 $610 $611 $607 $607 $8,020 $12,155 Description: This project provides for the replacement of the Police Station and relocation of the Municipal Court. Benefit: Replacement Police facility will provide adequate space for current and future departmental needs, while correcting numerous space, structural, and security deficiencies in the current facility. New Court facility will replace existing leased space, which marginally meets current requirements and will create operational efficiencies by being co-located with the Police Station. Schedule: Construction in 2022. Project: City Hall Parking Lot Retrofit Number: Location: City Hall Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 REET Fund $0 $0 $0 $111 $0 $0 $0 $0 $111 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $0 $0 $111 $0 $0 $0 $0 $111 FUNDING USES (1000's) Project Management $0 $0 $0 $11 $0 $0 $0 $0 $11 Design/permitting $0 $0 $0 $0 $0 $0 $0 $0 $0 Construction $0 $0 $0 $100 $0 $0 $0 $0 $100 Sub-total $0 $0 $0 $111 $0 $0 $0 $0 $111 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total Description: Improve the stormwater drainage system and add water quality facilities at the City Hall lower parking lot in accordance with the City’s stormwater permit. The project would seek to eliminate the use of asphalt paving as part of the suite of improvements. Benefit: The improvements would improve drainage and water quality from the site, and potentially enhance the visual aesthetics of the parking lot. Schedule: YR 1: Design and construction Project: City Hall Security Number:01092 Location: City Hall Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $153 $7 $0 $0 $0 $0 $0 $160 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $153 $7 $0 $0 $0 $0 $0 $160 FUNDING USES (1000's) Project Management $0 $3 $7 $0 $0 $0 $0 $0 $10 Design/permitting $0 $0 $0 $0 $0 $0 $0 $0 $0 Construction $0 $150 $0 $0 $0 $0 $0 $0 $150 Sub-total $0 $153 $7 $0 $0 $0 $0 $0 $160 Estimated Impact on Future Operating Budget (1000's) Prior Yrs 2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total Description: Replace the obsolete existing security system at City Hall to match coordinate with the new system to be installed at the new Police/Court Facility. Benefit: Improved security at City Hall, and coordinated systems across the organization for ease of maintenance and operability. Schedule: YR 1: Design and construction; YR 2: Construction Project: Dry Fire Sprinkler Number:01163 Location: Hidden Cove Maintenance Facility Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $60 $0 $0 $0 $0 $0 $0 $60 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $60 $0 $0 $0 $0 $0 $0 $60 FUNDING USES (1000's) Project Management $0 $2 $0 $0 $0 $0 $0 $0 $2 Design/permitting $0 $0 $0 $0 $0 $0 $0 $0 $0 Construction $0 $58 $0 $0 $0 $0 $0 $0 $58 Sub-total $0 $60 $0 $0 $0 $0 $0 $0 $60 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total Description: The City of Bainbridge Island’s Operations and Maintenance facility has a lower storage yard that houses various materials and equipment. The main steel canopy ( 60’ x 270’) that covers and protects public works equipment is outfitted with a fire protection system so that equipment, property and life will be protected in the event of a fire. This particular system is known as a “Dry Fire System”. A dry fire system is a sprinkler system where the sprinkler pipes are filled with compressed air instead of water. Because the sprinkler pipes are exposed to the external environment (freezing temperatures) this type of system is used to prevent the lines from bursting. If fire is detected the system will open and water will rush through the system. During the city’s annual fire sprinkler inspection it was determined that dry fire system underneath the metal canopy had reached its operational lifespan. This project will replace the existing dry fire system and bring the facility up to current standards. Project: Salt Storage Facility Number:01093 Location: Hidden Cove Maintenance Facility Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $71 $0 $0 $0 $0 $0 $0 $71 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $71 $0 $0 $0 $0 $0 $0 $71 FUNDING USES (1000's) Project Management $0 $11 $0 $0 $0 $0 $0 $0 $11 Design/permitting $0 $0 $0 $0 $0 $0 $0 $0 $0 Construction $0 $60 $0 $0 $0 $0 $0 $0 $60 Sub-total $0 $71 $0 $0 $0 $0 $0 $0 $71 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total Description: The salt storage facility will enable road maintenance crews to store and more easily distribute salt brine as part of the City’s snow and ice response efforts. Salt brine has previously been purchased from the County, and this new approach will reduce the budget and labor associated with this work over the long term. Stockpiled salt needs to be sheltered from the elements. Benefit: Improved snow and ice response, and reduced costs. Schedule: YR1: Design and construction Project: Bainbridge Island Senior Center Renovations Number:01050 Location: BISCC Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $62 $0 $0 $0 $0 $0 $0 $62 REET $0 $0 $276 $0 $0 $0 $0 $0 $276 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Donated $0 $50 $110 $0 $0 $0 $0 $0 $160 Sub-total $0 $112 $386 $0 $0 $0 $0 $0 $498 FUNDING USES (1000's) Project Management $0 $12 $46 $0 $0 $0 $0 $0 $58 Design/permitting $0 $100 $0 $0 $0 $0 $0 $0 $100 Construction $0 $0 $340 $0 $0 $0 $0 $0 $340 Sub-total $0 $112 $386 $0 $0 $0 $0 $0 $498 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total Description: The Bainbridge Island Senior Community Center Renovations project includes a suite of repair and maintenance upgrades (heat pump and roof replacement, security and electrical upgrades, etc.), and renovations to improve efficiency and the use of space for community programs. The work will include retrofitting the east-wing for more a more communal layout, reconfiguring the entryway, and expanding the thrift store. Benefit: Improved asset and more efficient use of existing space. Schedule: YR1: Design; YR2: Construction City of Bainbridge Island Water CIP (2021 - 2026) 2022 Modifications Project Location Gr a n t E l i g i b l e Ge n e r a l C o m p St r t s C o m p Wt r C o m p Sw r C o m p SS W M C o m p Prior Years 2021 2022 2023 2024 2025 2026 2027 - 2040 Total WATER PROJECTS - 6-YEAR CIP (1000s) Wyatt Way Reconstruction Wyatt Way Y 343 167 - - - - - - 510 SCADA Upgrades Various Y 208 74 - - - - - - 282 Chlorine Generator Upgrades Various Y 460 271 - - - - - - 731 Winslow Water Tank Replacement New Brooklyn x Y 1,005 535 39 10,040 - - - - 11,619 Fire Flow Improvements Winslow Y - 91 275 - - - - - 366 Well Development/Rehab Pritchard Park Y - 56 164 - - - - - 220 Pipeline Improvements Shephard Way Y - 66 333 - - - - - 399 Emergency Generator Head of the Bay Y - - - 60 135 - - - 195 Water Treatment Improvements Head of the Bay Y - - - 600 1,600 - - - 2,200 Winslow Way West - - - - - 60 228 - 288 City Project Funding 2,016 1,260 811 10,700 1,735 60 228 - 16,810 Grant Totals - - - - - - - - - TOTALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2,016 1,260 811 10,700 1,735 60 228 - 16,810 Amounts in thousands Project: Wyatt Way Reconstruction Phase 1 Number:00708 Location: Madison to Lovell Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $1,637 $22 $0 $0 $0 $0 $0 $0 $1,659 Water Fund $343 $167 $0 $0 $0 $0 $0 $0 $510 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $2,516 $0 $0 $0 $0 $0 $0 $0 $2,516 Sub-total $4,496 $189 $0 $0 $0 $0 $0 $0 $4,685 FUNDING USES (1000's) Project Management $144 $79 $223 Design/permitting $770 $770 Construction $3,582 $110 $3,692 Sub-total $4,496 $189 $0 $0 $0 $0 $0 $0 $4,685 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Capacity (level of service) improvements to the intersection of Madison Avenue and Wyatt Way, including a roundabout. Complete sidewalk and bicycle facilities on both sides of Wyatt from Madison to Lovell. Reconstruct roadway surfacing and drainage. Replace several hundred feet of aging and undersized water mains prior to road repairs. Benefit: Relieve current and future intersection congestion and ensure mobility by implementing improvements prior to development. Address a gap in non-motorized facilities to improve mobility and safety. Support businesses and employment in the downtown area. Schedule: 2020: Construction Project: SCADA Upgrades Number:00818 Location: Various Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $208 $74 $0 $0 $0 $0 $0 $0 $282 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $208 $74 $0 $0 $0 $0 $0 $0 $282 FUNDING USES (1000's) Project Management $3 $17 $20 Design/permitting $57 $57 Construction $205 $205 Sub-total $208 $74 $0 $0 $0 $0 $0 $0 $282 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: The City’s water systems are monitored and controlled remotely by a Supervisory Control and Data Acquisition (SCADA) system that was design and installed in 1995. This project will upgrade and replace this critical system to meet current hardware and software standards. Benefit: Provide reliable monitoring and control of the water system. Schedule: YR1: construction. Project: Chlorine Generator Upgrades Number:00987 Location: Various Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $460 $271 $0 $0 $0 $0 $0 $0 $731 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $460 $271 $0 $0 $0 $0 $0 $0 $731 FUNDING USES (1000's) Project Management $11 $11 Design/permitting Construction $460 $260 $720 Sub-total $460 $271 $0 $0 $0 $0 $0 $0 $731 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: The City's chlorine generators at the Sands, Fletcher Bay, and Head of the Bay Well Site are between 9 and 15 years old. These three 36 pounds per day (ppd) units need to be replaced. Benefit: Improve water quality for the system. Schedule: 2021: Construction Project: Winslow Water Tank Replacement Number:00988 Location: New Brooklyn Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $1,005 $535 $39 $10,040 $0 $0 $0 $0 $11,619 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $1,005 $535 $39 $10,040 $0 $0 $0 $0 $11,619 FUNDING USES (1000's) Project Management $5 $35 $39 $40 $119 Design/permitting $1,000 $500 $1,500 Construction $10,000 $10,000 Sub-total $1,005 $535 $39 $10,040 $0 $0 $0 $0 $11,619 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service TBD Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: Construct a new 2 million-gallon reservoir to replace both of the existing tanks that are located on an easement near the High School. Benefit: A new tank built at a sufficient elevation, and to the most recent design standards, will correct several deficiencies associated with existing tanks including: significant dead storage, pressure zone deficiencies, water quality issues, and seismic deficiencies. Schedule: 2021: Design; 2023: Construction Project: Fire Flow Improvements Number:01095 Location: Winslow Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $91 $275 $0 $0 $0 $0 $0 $366 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $91 $275 $0 $0 $0 $0 $0 $366 FUNDING USES (1000's) Project Management $16 $35 $51 Design/permitting $0 Construction $75 $240 $315 Sub-total $0 $91 $275 $0 $0 $0 $0 $0 $366 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: As recommended by the City’s 2017 Water System Plan, two pipeline upgrades have been identified that will allow the Winslow Water System to provide the required fire flow requirements for commercial and multi-family buildings. Benefit: Sufficient fire flow to provide life safety and property protections. Schedule: YR1: design, YR2: construction. Project: Well Development Number:01096 Location: Pritchard Park Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $56 $164 $0 $0 $0 $0 $0 $220 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $56 $164 $0 $0 $0 $0 $0 $220 FUNDING USES (1000's) Proj. Management $6 $14 $20 Design/permitting $50 $50 Construction $150 $150 Sub-total $0 $56 $164 $0 $0 $0 $0 $0 $220 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: Pritchard well, which serves the City’s Rockaway Beach Water System, has declined 40% since the City took ownership of the system in 1996. Rehabilitation of the well may be possible, but a new well location may also need to be planned in another nearby location. Benefit: Provide sufficient water supply for the Rockaway service area. Schedule: YR1: Planning; YR2: Construction Project: Pipeline Improvements Number:01097 Location: Shepard Way Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $66 $333 $0 $0 $0 $0 $0 $399 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $66 $333 $0 $0 $0 $0 $0 $399 FUNDING USES (1000's) Proj. Management $16 $33 $49 Design/permitting $0 Construction $50 $300 $350 Sub-total $0 $66 $333 $0 $0 $0 $0 $0 $399 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: This project proposes to increase the size of the water main on Shepard Way which was identified by the City’s Water System Plan as undersized to meet current needs. Benefit: Sufficient fire flow to protect life and property. Schedule: YR1: design, YR2: construction. Project: Water Treatment Improvements Number:00816 Location: Winslow Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $600 $1,600 $0 $0 $0 $2,200 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $0 $0 $600 $1,600 $0 $0 $0 $2,200 FUNDING USES (1000's) Project Management $100 $100 Design/permitting $500 Construction $1,500 Sub-total $0 $0 $0 $600 $1,600 $0 $0 $0 $2,200 Estimated Impact on Future Operating Budget Prior Yrs 2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project implements water treatment improvements to prevent iron, manganese, and sulfide levels from exceeding the maximum contaminant levels (MCLs). Benefit: Improve water quality for the system. Schedule: YR1: design. YR2: construction. City of Bainbridge Island Sewer CIP (2021 - 2026) 2022 Modifications Project Location and/or Phase Gr a n t E l i g i b l e Gr a n t A w a r d e d Gr a n t F u n d s Ge n e r a l C o m p St r t s C o m p o n e n t Wt r C o m p o n e n t Sw r C o m p o n e n t SS W M C o m p Prior Years 2021 2022 2023 2024 2025 2026 2027 - 2040 Total SEWER PROJECTS - 6-YEAR CIP (1000s) Rehabilitate Pumps Sunday Cove - Y 151 45 466 - - - - - 662 Lift Station SCADA Upgrades Various - Y 281 106 - - - - - - 387 Pump Station & Force Main Wood Ave - Y 753 17 21 2,800 - - - - 3,591 Rehabilitate Pump Station (Lower Lovell) Lower Lovell Y 173 12 475 440 - - - - 1,100 Rehabilitate Pump Station (Wing Point) Wing Point - Y 102 15 17 - 525 - - - 659 Village Basin Improvements NW Winslow Y - 791 1 - - - - - 792 WWTP Airgap Replacement Wing Point Y - 188 - - - - - - 188 Hawley Pump Lower Hawley Y - - 124 - 490 - - - 614 Hawley/Irene Grinder Pumps Wing Point Y - 363 27 - - - - - 390 North Town Woods Pump NW Winslow Y - - 115 474 - - - - 589 Woodward Pump NW Winslow Y - 14 119 - - 380 - - 513 Rehabilitate Pump Station (Island Island Terrace - Y - - - 180 475 - - - 655 Install Gravity Sewers Sunday Cove - Y 200 15 10 - - - 490 - 715 Extend WWTP Outfall Wing Point - Y - - - 275 - 950 - - 1,225 City Total 1,660 1,566 1,374 4,169 1,490 1,330 490 - 12,079 Grant Total - - - - - - - - - TOTALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,660 1,566 1,374 4,169 1,490 1,330 490 - 12,079 Amounts in thousands Project: Rehabilitate Pumps Number:00989 Location: Sunday Cove Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $151 $45 $466 $0 $0 $0 $0 $0 $662 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $151 $45 $466 $0 $0 $0 $0 $0 $662 FUNDING USES (1000's) Project Management $1 $15 $46 $62 Design/permitting $150 $30 $180 Construction $420 $420 Sub-total $151 $45 $466 $0 $0 $0 $0 $0 $662 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: Some components of the Sunday Cove pump station will reach the end of their useful life, which is assumed to be approximately 30 years, over the next few years. In addition to replacement of the pumps and motors, this project will include the replacement of the station’s emergency generator. Benefit: Replacement of a deteriorated system with a reliable sewer collection system that can be maintained in the future. Schedule: YR1: Design and construction. Project: Lift Station SCADA Upgrades Number:00821 Location: Various Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $281 $106 $0 $0 $0 $0 $0 $0 $387 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $281 $106 $0 $0 $0 $0 $0 $0 $387 FUNDING USES (1000's) Project Management $1 $21 $22 Design/permitting $85 $85 Construction $280 $280 Sub-total $281 $106 $0 $0 $0 $0 $0 $0 $387 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The City’s sewer system is monitored and controlled remotely by a Supervisory Control and Data Acquisition (SCADA) system that was designed and installed in 1995. This project will upgrade and replace this critical system to meet current hardware and software standards. Benefit: Replacement of a deteriorated system with a reliable sewer collection system that can be maintained in the future. Schedule: 2020: Design; 2021: Construction Project: Pump Station and Force Main Number:00990 Location: Wood Ave Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $753 $17 $21 $2,800 $0 $0 $0 $0 $3,591 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $753 $17 $21 $2,800 $0 $0 $0 $0 $3,591 FUNDING USES (1000's) Project Management $3 $17 $21 $50 $91 Design/permitting $750 $750 Construction $2,750 $2,750 Sub-total $753 $17 $21 $2,800 $0 $0 $0 $0 $3,591 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: This project is part of a suite of projects (Lovell Pump Station; Sunday Cove Pump Station; and Sunday Cove Gravity Sewers) that are planned to facilitate the abandonment of the north and south sewer beach main, which is an aging facility that has reached the end of its useful life. Abandonment of the beach mains was determined to be the best replacement approach due to environmental, maintenance and cost-benefit concerns. Benefit: Replacement of a deteriorated system with a reliable sewer collection system that can be maintained in the future. Schedule: YR1: design/permitting, YR3: construction. Project: Rehabilitate Pump Station and Re-connect Side Sewers Number:01086 Location: Lower Lovell Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $173 $12 $475 $440 $0 $0 $0 $0 $1,100 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $173 $12 $475 $440 $0 $0 $0 $0 $1,100 FUNDING USES (1000's) Project Management $3 $12 $45 $40 $100 Design/permitting $170 $170 Construction $430 $400 $830 Sub-total $173 $12 $475 $440 $0 $0 $0 $0 $1,100 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The pump station is reaching the end of its useful life, and needs to be upgraded with replacement pumps. This project is part of a suite of projects (Lovell Pump Station; Sunday Cove Pump Station; and Sunday Cove Gravity Sewers) that are planned to facilitate the abandonment of the north and south sewer beach main, which is an aging facility that has reached the end of its useful life. Side sewers associated with several properties along Lovell Avenue will be reconnected to the upland sewer main as part of this project. Benefit: Replacement of a deteriorated system with a reliable sewer collection system that can be maintained in the future. Schedule: YR1: design. YR2: construction. Project: Rehabilitate Pump Station Number:00820 Location: Wing Point Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $102 $15 $17 $0 $525 $0 $0 $0 $659 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $102 $15 $17 $0 $525 $0 $0 $0 $659 FUNDING USES (1000's) Project Management $2 $15 $17 $25 $59 Design/permitting $100 $100 Construction $500 $500 Sub-total $102 $15 $17 $0 $525 $0 $0 $0 $659 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: The Wing Point Pump Station has not been upgraded since its construction in 1979, and has reached the end of its useful life. In addition to required upgrades, the pump station access hatch will need to be re-designed to accommodate impacts from sea-level rise. Benefit: Improves reliability of current sewer collection system. Schedule: 2020: Design; 2024: Construction Project: Village Basin Improvements Number:01100 Location: Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $791 $1 $0 $0 $0 $0 $0 $792 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $791 $1 $0 $0 $0 $0 $0 $792 FUNDING USES (1000's) Project Management $41 $1 $42 Design/permitting $30 $30 Construction $720 $720 Sub-total $0 $791 $1 $0 $0 $0 $0 $0 $792 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project is a placeholder for prioritized sewer improvements that will be identified by the City’s sewer basin analysis, which is anticipated to be completed in Fall 2020. The amount is reflective of the approximate cost of what may be the basin’s priority project, replacement of a force main in New Brooklyn and Madison Avenue. This project wil be closed and combined with Madison Avenue Sidewalk Improvements in 2022. Benefit: Improves reliability of sewer collection system. Schedule: YR1: Design and Construction Project: WWTP Air Gap Replacement Number:01073 Location: Wing Point Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $188 $0 $0 $0 $0 $0 $0 $188 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $188 $0 $0 $0 $0 $0 $0 $188 FUNDING USES (1000's) Project Management $8 $8 Design/permitting $0 Construction $180 $180 Sub-total $0 $188 $0 $0 $0 $0 $0 $0 $188 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Replace backflow protection for the potable water connection within the wastewater treatment plant. An in plant air gap system will be installed to isolate the solids processing building from the potable water connection, Winslow Water System and will meet Washington State Department of Health current regulations. Schedule: YR1: design, YR2: construction Project: Rehabilitate Pump Station Number:01102 Location: Lower Hawley Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $124 $0 $490 $0 $0 $0 $614 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $0 $124 $0 $490 $0 $0 $0 $614 FUNDING USES (1000's) Project Management $24 $40 $64 Design/permitting $100 $100 Construction $450 $450 Sub-total $0 $0 $124 $0 $490 $0 $0 $0 $614 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The station was constructed as part of a major sewer system upgrade in 1979. Telemetry is limited to monitoring and is provided by a tone RTU installed in 1995. A generator set installed in 1996. The electrical systems are in fair condition, the telemetry is beyond its useful life, and the wet well controls do not meet current safety standards. Because of their age, the pumps, motors, valves, controls, and telemetry should be replaced. The station has exceeded the estimated useful life and requires rehabilitation. Benefit: Replacement of a deteriorated system with a reliable sewer collection system that can be maintained in the future. Schedule: YR1: design. YR2: construction. Project: Hawley/Irene Grinder Pumps Number:01103 Location: Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $363 $27 $0 $0 $0 $0 $0 $390 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $363 $27 $0 $0 $0 $0 $0 $390 FUNDING USES (1000's) Project Management $13 $27 $40 Design/permitting $0 Construction $350 $350 Sub-total $0 $363 $27 $0 $0 $0 $0 $0 $390 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project proposes to replace an aging and failing gravity sewer main with a new force main and grinders pumps for several residences along Hawley Way and Irene Place. Benefit: Replacement of a deteriorated system with a reliable improvement that can be maintained in the future. Schedule: YR1: Design and Construction Project: North Town Woods Pump Number:01104 Location: Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $115 $474 $0 $0 $0 $0 $589 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $0 $115 $474 $0 $0 $0 $0 $589 FUNDING USES (1000's) Project Management $14 $24 $39 Design/permitting $100 $100 Construction $450 $450 Sub-total $0 $0 $114 $474 $0 $0 $0 $0 $589 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project proposes to upgrade the North Town Woods pump station to meet current standards, as identified in the City’s General Sewer Plan. Benefit: Upgrading the sewer system with a reliable improvement that can be maintained in the future. Schedule: YR1: design. YR2: construction. Project: Woodward Pump Number:01125 Location: Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $14 $119 $0 $0 $380 $0 $0 $513 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $14 $119 $0 $0 $380 $0 $0 $513 FUNDING USES (1000's) Project Management $14 $19 $30 $63 Design/permitting $100 $100 Construction $350 $350 Sub-total $0 $14 $119 $0 $0 $380 $0 $0 $513 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project proposes to upgrade the Woodward pump station to meet current standards, as identified in the City’s General Sewer Plan. Benefit: Upgrading the sewer system with a reliable improvement that can be maintained in the future. Schedule: YR1: Design; YR4: Construction Project: Rehabilitate Pump Station Number: Location: Island Terrace Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027-2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $180 $475 $0 $0 $0 $655 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $0 $0 $180 $475 $0 $0 $0 $655 FUNDING USES (1000's) Project Management $30 $25 $55 Design/permitting $150 $150 Construction $450 $450 Sub-total $0 $0 $0 $180 $475 $0 $0 $0 $655 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027-2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The Island Terrace pump station will reach the end of its useful life, which is assumed to be approximately 30 years, over the next few years. Additionally the concrete drywell and wet well at the pump station requires painting. As the upgrade project takes place, wet well controls should be replaced to meet current safety standards. Benefit:Replacement of a deteriorated system with a reliable sewer collection system that can be maintained in the future. Schedule: YR1: design. YR2: construction. Project: Install Gravity Sewers Number:01085 Location: Sunday Cove Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $200 $15 $10 $0 $0 $0 $490 $0 $715 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $200 $15 $10 $0 $0 $0 $490 $0 $715 FUNDING USES (1000's) Project Management $15 $10 $40 $65 Design/permitting $200 $200 Construction $450 $450 Sub-total $200 $15 $10 $0 $0 $0 $490 $0 $715 Estimated Impact on Future Operating Budget Prior 2021 2022 2023 2024 2025 2026 2027-Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: This project is part of a suite of projects (Lovell Pump Station; Sunday Cove Pump Station; and Sunday Cove Gravity Sewers) that are planned to facilitate the abandonment of the north and south sewer beach main, which is an aging facility that has reached the end of its useful life. Abandonment of the beach mains was determined to be the best replacement approach due to environmental, maintenance and cost- benefit concerns. Benefit: Replacement of a deteriorated system with a reliable sewer collection system that can be maintained Schedule: 2020: Design; 2026: Construction Project: Extend WWTP Outfall Number:01106 Location: Wing Point Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $275 $0 $950 $0 $0 $1,225 SSWM Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $0 $0 $0 $275 $0 $950 $0 $0 $1,225 FUNDING USES (1000's) Project Management $75 $50 $125 Design/permitting $0 Construction $0 $200 $900 $1,100 Sub-total $0 $0 $0 $275 $0 $950 $0 $0 $1,225 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The outfall from the City WWTP operates under an aquatic lease with WDFW. The outfall terminates in a geoduck bed, which is closed for harvesting due to this outfall. Recent shellfish surveys have documented the loss of potential harvest, and WDFW has notified the City that natural resource fines will likely be implemented in the near future. This project will extend the outfall as described in the Cosmopolitan Engineering report of 2008. Benefit: Protect natural resources and ensure the future operation of the WWTP. Schedule: YR1: design, YR2: construction City of Bainbridge Island Stormwater CIP (2021- 2026) 2022 Modifications Project Gr a n t E l i g i b l e Gr a n t A w a r d e d Gr a n t F u n d s Ge n e r a l C o m p St r t s C o m p o n e n t Wt r C o m p o n e n t Sw r C o m p o n e n t SS W M C o m p Pr i o r Y e a r s 2021 2022 2023 2024 2025 2026 2027 - 2040 Total STORMWATER PROJECTS - 6-YEAR CIP (1000s) Eagle Hrbr. Dr. @ McDonald Creek Culvert - Y 210 56 9 - - - - - 276 Pritchard Park Outfall Y 125 24 - - - - - - 149 Yeomalt Area Drainage Improvements - Y 61 - - 625 - - - - 686 Blakely Ave. Drainage Improvements - Y - - - 280 - - - - 280 Springbrook Creek Restoration and Culvert Complex Replacement x - Y - - - - 240 1,270 - - 1,510 Springbrook Fish Passage x 1,085 X Y - 135 - 1,050 - - - - 1,185 Eagle Harbor Drive Cooper Creek Fish Passage x - X Y 105 10 11 - 525 - - - 651 City Funding 501 141 20 955 765 1,270 - - 3,651 Grant Totals - 85 - 1,000 - - - - 1,085 TOTALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 501 226 20 1,955 765 1,270 - - 4,736 Amounts in thousands Project: Eagle Harbor Drive at McDonald Creek Number:00823 Location: 5530 Eagle Harbor Drive Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $210 $56 $9 $0 $0 $0 $0 $0 $276 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $210 $56 $9 $0 $0 $0 $0 $0 $276 FUNDING USES (1000's) Project Management $10 $6 $9 $26 Design/permitting $200 $50 $250 Construction $0 Sub-total $210 $56 $9 $0 $0 $0 $0 $0 $276 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Replacement of an existing deep concrete culvert that shows signs of failure. Benefit: Preservation of roadway and drainage system. Schedule: 2020: Design and permitting; Construction deferred until permits are in place. Project: Pritchard Park Outfall Number:1120 Location: Pritchard Park Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $125 $24 $0 $0 $0 $0 $0 $0 $149 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $125 $24 $0 $0 $0 $0 $0 $0 $149 FUNDING USES (1000's) Project Management $24 $24 Design/permitting $0 Construction $125 $125 Sub-total $125 $24 $0 $0 $0 $0 $0 $0 $149 Estimated Impact on Future Operating Budget (1000's) Prior Yrs 2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 INSERT PICTURES HERE Description: Relocate stormwater outfall for Nikkei Memorial Park as agreed in legal settlement with adjacent property owner. Benefit: Achieve compliance with legal settlement and coordinate on-site construction with planned improvements to the memorial. Schedule: Design complete; 2021: Construction Project: Yeomalt Area Drainage Improvements Number:00663 Location: Area bordered by Cherry, Yeomalt, Madrona and Wing Point Way Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $61 $0 $0 $625 $0 $0 $0 $0 $686 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $61 $0 $0 $625 $0 $0 $0 $0 $686 FUNDING USES (1000's) Project Management $1 $35 $36 Design/permitting $60 $60 Construction $590 $590 Sub-total $61 $0 $0 $625 $0 $0 $0 $0 $686 Estimated Impact on Future Operating Budget (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2026- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Provides for storm drainage improvements in the Yeomalt area. The City completed design in 2014 with funds received from a DOE grant for water quality Benefit: Much of the Wing Point area above Yeomalt Point was developed before regulations required conveyance systems. Currently there are drainage problems in many areas and/or existing conveyances are lacking or inadequate. Schedule: 2021: Design; 2022: Construction Project: Springbrook Fish Passage Number: Location: Fletcher Bay Road west of New Brooklyn Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $50 $0 $50 $0 $0 $0 $0 $100 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $0 $50 $0 $50 $0 $0 $0 $0 $100 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $85 $0 $1,000 $0 $0 $0 $0 $1,085 Sub-total 0 185 0 1100 0 0 0 0 1285 FUNDING USES (1000's) Project Management $4 $50 $54 Design/permitting $181 $50 $231 Construction $1,000 $1,000 Sub-total 0 185 0 1100 0 0 0 0 1285 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: The Springbrook Fish Weir/Passage project proposes to replace the existing culvert at Springbrook Creek with an open box/bridge structure and streambed restoration. Benefit: Schedule: YR 1: Design Project: Eagle Harbor Drive Cooper Creek Fish Passage Number:1107 Location: Head of the Bay North of Green Light Automotive Project Description Capital Funding (1000's) Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total FUNDING SOURCES (1000's) General Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Water Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 Sewer Fund $0 $0 $0 $0 $0 $0 $0 $0 $0 SSWM Fund $105 $10 $11 $0 $525 $0 $0 $0 $651 Federal Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 State Grant $0 $0 $0 $0 $0 $0 $0 $0 $0 Sub-total $105 $10 $11 $0 $525 $0 $0 $0 $651 FUNDING USES (1000's) Proj. Management $10 $10 $11 $31 Design/permitting $95 $95 Construction $525 $0 $0 $525 Sub-total $105 $10 $11 $0 $525 $0 $0 $0 $651 Estimated Impact on Future Operating Budget Prior Yrs.2021 2022 2023 2024 2025 2026 2027- 2040 Total Operating Debt Service Sub-total $0 $0 $0 $0 $0 $0 $0 $0 $0 Description: Replace existing undersized culvert with a fish passage box culvert wide enough to accomodate non-motorized improvements on Eagle Harbor Drive. Benefit: Addresses flooding, provides for fish passage, and accommodates future non-motorized improvements. Schedule: 2021: Design; 2024 Construction