ORD 2007-18 Capital Facilities Plan 121207 CC City of Bainbridge Island CITY COUNCIL AGENDA BILL PROCESS INFORMATION Subject: Ord. 2007-18: 2008 Capital Facilities Plan Update Date: 12/12/2007 Agenda Item: 2nd Reading Bill No.: AB 07-0089 Contact Person: Peter Namtvedt Best, Elray Konkel, Randy Witt Referral(s): Reading: 1st 2nd 3rd BUDGET INFORMATION Department or Fund: n/a Total Expenditure Required (tax included): n/a Budgeted? yes no Is a budget amendment required? yes no POLICY INFORMATION Comprehensive Plan: Capital Facilities Element; CF 1.5 Municipal Code: 18.117.050 (Comprehensive Plan amendment decision criteria) DESCRIPTION/SUMMARY Ord. 2007-18 is a Comprehensive Plan amendment adopting the 2008 Capital Facilities Plan (CFP) update for the City and, by reference, the CFP’s for the Special Districts that serve Bainbridge Island. This public hearing draft reflects the results of the staff review process and Council action. Appendix A shows the proposed projects that are no longer included in the 6- year (2008-2013) CIP list. The Planning Commission completed their Comprehensive Plan consistency review on July 19, 2007. City Council conducted a 2nd Reading on August 29, 2007 and continued 2nd Reading to September 12, 2007. Due to substantial changes since September, another 2nd Reading will be held on December 12, 2007. RECOMMENDED ACTION Waive 3rd reading and adopt Ordinance 2007-18 (2008 Capital Facilities Plan Update). Ordinance 2007-18: 2008 Capital Facilities Plan Update DRAFT Page 1 of 3 CC 2nd Reading 12/12/2007 DRAFT ORDINANCE NO. 2007-18 AN ORDINANCE of the City of Bainbridge Island, Washington, adopting the 2008 update of the six-year Capital Facilities Plan; amending the Capital Facilities Element of the Bainbridge Island Comprehensive Plan. WHEREAS, in accordance with the Growth Management Act, the City of Bainbridge Island adopted a Comprehensive Plan on September 1, 1994 and revised it on December 8, 2004, which Plan contains a Capital Facilities Element that establishes goals and policies for the provision and financing of capital facilities for the citizens of Bainbridge Island; and WHEREAS, the Growth Management Act requires that the six-year Capital Facilities Plan be updated at least biennially and adopted as an amendment to the Comprehensive Plan and Comprehensive Plan Policies CF 1.3, 1.4, and 1.5 requires an annual update; and WHEREAS, the 2008 update of the six-year Capital Facilities Plan addresses all of the goals and requirements set forth in the Growth Management Act and the Bainbridge Island Comprehensive Plan; and WHEREAS, the 2008 update of the six-year Capital Facilities Plan is in accordance with the decision criteria for amendments of the Comprehensive Plan as set forth in BIMC 18.117; and WHEREAS, the Planning Commission and the City Council have received, discussed, and considered testimony, written comments, and materials from the public; now, therefore, Ordinance 2007-18: 2008 Capital Facilities Plan Update DRAFT Page 2 of 3 CC 2nd Reading 12/12/2007 THE CITY COUNCIL OF THE CITY OF BAINBRIDGE ISLAND, WASHINGTON, DO ORDAIN AS FOLLOWS: Section 1. The 2008 update of the six-year Capital Facilities Plan of the Capital Facilities Element of the Bainbridge Island Comprehensive Plan, attached as Exhibit A, is adopted as of December 12, 2007. Section 2. In the event that there are instances where the dollar amounts or timing of capital projects included in this update differ from those in other sections of the Comprehensive Plan, the amounts and timing in this update shall prevail. Section 3. This ordinance authorizes the reformatting of the information in this update of the Capital Facilities Plan and the transmission of this information to the State of Washington as the City’s annual State Transportation Improvement Program (STIP). Section 4. The six-year Capital Facilities Plan of the Bainbridge Island School District No. 303 adopted on June 21, 2007 is adopted by reference. Section 5. The six-year Capital Facilities Plan of the Bainbridge Island Metropolitan Park & Recreation District adopted by resolution 2007-18 on November 8, 2007 is adopted by reference. Section 6. The six-year Capital Facilities Plan of the Bainbridge Island Fire Department adopted by Resolution No. 44-2006 on December 20, 2006 and amended by Resolution No. 08-2007 on March 14, 2007 is adopted by reference. Section 7. The six-year Capital Facilities Plan of the Kitsap County Sewer District No. 7 for the years 2006-2011 and the 2007-2012 update is adopted by reference. Section 8. The six-year Capital Facilities Plan of the Kitsap County Public Utilities District No. 1 adopted by resolution 06-11-14D on November 14, 2006 is adopted by reference. Section 9. Severability. If any section, sentence, clause or phrase of this ordinance shall be held to be invalid or unconstitutional by a court of competent jurisdiction, such invalidity or unconstitutionality shall not affect the validity or constitutionality of any other section, sentence, clause or phrase of this ordinance. Section 10. This ordinance shall take effect and be in force five days from and after its passage, approval and publication as required by law. Ordinance 2007-18: 2008 Capital Facilities Plan Update DRAFT Page 3 of 3 CC 2nd Reading 12/12/2007 PASSED by the City Council this day of 2007. APPROVED by the Mayor this day of 2007. Darlene Kordonowy, Mayor ATTEST/AUTHENTICATE: Rosalind Lassoff, City Clerk FILED WITH THE CITY CLERK: PASSED BY THE CITY COUNCIL: PUBLISHED: EFFECTIVE DATE: ORDINANCE NUMBER: 2007-18 CITY OF BAINBRIDGE ISLAND 2008 CAPITAL FACILITIES PLAN UPDATE December 12, 2007 2nd Reading Draft Ord. 2007-18: Exhibit A TABLE OF CONTENTS I. INTRODUCTION....................................................................................................................................................3 RELATIONSHIP OF CAPITAL FACILITIES PLAN TO THE BUDGET...................................................................................4 WHAT IS A CAPITAL FACILITY?..................................................................................................................................4 HOW ARE CAPITAL FACILITY PROJECTS IDENTIFIED?.................................................................................................5 Levels of Service (LOS)........................................................................................................................................5 PRIORITIZING CAPITAL PROJECTS ...............................................................................................................................5 II. CAPITAL FACILITIES INVENTORY & PLANNING ....................................................................................6 CITY OFFICES, FACILITIES, & UNDEVELOPED LAND ..................................................................................................6 PARKS & TRAILS ........................................................................................................................................................8 TRANSPORTATION FACILITIES (ROADS, BIKE LANES, SIDEWALKS, TRAILS)............................................................10 WATER .....................................................................................................................................................................11 Winslow Water System.......................................................................................................................................12 SANITARY SEWAGE DISPOSAL ..................................................................................................................................13 SURFACE & STORM WATER MANAGEMENT .............................................................................................................14 III. SIX-YEAR CAPITAL IMPROVEMENT PLAN ............................................................................................15 IV. FINANCIAL CAPACITY ANALYSIS.............................................................................................................59 APPENDICES: A. City project not included in 2008-2013 CIP B. Bainbridge Island School District CFP C. Bainbridge Island Metropolitan Park And Recreation District CIP D. Bainbridge Island Fire District CFP E. Kitsap County Sewer District No. 7 CFP F. Kitsap County Public Utilities District No. 7 CFP LIST OF TABLES TABLE 1: CITY LAND AND OFFICE FACILITY INVENTORY ..............................................................................................6 TABLE 2: CITY PUBLIC WORKS FACILITIES INVENTORY (2005/2006)............................................................................7 TABLE 3: CITY UNDEVELOPED LAND INVENTORY (2005/2006).....................................................................................7 TABLE 4: PARK FACILITY LEVELS OF SERVICE...............................................................................................................8 TABLE 5: PARKS & TRAILS INVENTORY (2005/2006).....................................................................................................8 TABLE 6: TRANSPORTATION FACILITIES INVENTORY (2005/2006)...............................................................................11 TABLE 7: WATER SYSTEM LEVELS OF SERVICE ...........................................................................................................11 TABLE 8: GROUP A & B WATER SYSTEMS (2005/2006) ..............................................................................................12 TABLE 9: WATERS SYSTEMS WITH OVER 100 CONNECTIONS (2005/2006)...................................................................12 TABLE 10: WINSLOW WATER SYSTEM WELL INVENTORY (2005/2006).......................................................................12 TABLE 11: WINSLOW SEWER FACILITY INVENTORY (2005/2006)................................................................................14 City of Bainbridge Island 2008 Capital Facilities Plan Update 2 of 186 I. INTRODUCTION Capital Facilities Plans (CFPs) are required under State law to identify capital facility deficiencies needed to serve our existing population, plan for capital facility improvements to meet the needs of our future population, and ensure that local governments have the fiscal capacity to afford to construct and maintain those capital facilities. Capital Facilities Planning is required to consider a 6-year time frame into the future. Therefore the 2008 CFP update includes the years 2008-2013. The Capital Facilities Plan includes summary details of the major capital projects of the City and a financial capacity analysis. As the general purpose government on Bainbridge Island, the City is required to analyze and integrate the capital facilities plans from special purpose districts (Schools, Parks, Fire, etc) into its Capital Facilities Plan. The City and the special purpose districts continue to work together to integrate their capital planning efforts to provide a more even tax impact and to prioritize their projects while still providing quality facilities and services for the citizens they serve. This is consistent with Goal 6 of the Framework of the Comprehensive Plan: All government entities strive to cooperate and serve their constituents in a fiscally sound manner; and Policy CF1.10 of the Capital Facilities Element: The City shall coordinate with other public entities which provide public services within the City to ensure that the Capital Facilities Plans of each of these entities are consistent with the City's Comprehensive Plan. This CFP update has been developed in accordance with the RCW 36.70A, the Growth Management Act (GMA), and WAC 365-195, the Procedural Criteria. It begins with a short review of some of the concepts behind the Capital Facilities Plan. This Capital Facilities Plan is the product of many separate but coordinated planning documents and planning bodies. Each of the special districts (Schools, Parks, Fire, etc) has its own capital facilities plans, which are attached as appendices to this document. The City’s Comprehensive Plan has various elements that relate land use and population growth management to water resources and transportation, which in turn have various adopted plans, including a Non- Motorized Transportation Plan, Water System Plan, a Sewer System Plan, a Storm and Surface Water Management Plan, and a Pavement Management System Plan – each providing an inventory of existing facilities, an analysis of deficiencies and future demand, and recommendation for capital improvements. Most facilities must be planned for years in advance and planning means determining not only when a facility will be needed but how it will be financed. For facilities that are projected for four to six years in the future, capital costs are more estimates than actual. As the time for construction nears, actual costs are narrowed as design and engineering are completed. It is important to remember that capital facilities planning is not a once a year or once every two years effort, but an ongoing process requiring continual review as new information becomes available, conditions change, and priorities evolve. The GMA requires that the Capital Facilities Element contain a financing plan that identifies the type and location of expanded or new capital facilities and the sources of funding that will used to pay for them. There are two questions that must be satisfactorily answered: City of Bainbridge Island 2008 Capital Facilities Plan Update 3 of 186 1) What is the quantity of the public facilities that will be required during the six years? (identified in the inventory and needs analysis); 2) Is it financially feasible to provide the quantity of facilities that are required? (do we now, or will we, have the money to pay for them?) Dependable revenue sources must be identified that equal or exceed the anticipated costs. If the costs exceed the revenue, the local government must reduce its level of service, reduce its costs (or increase revenue), or modify the land use element of its Comprehensive Plan to bring future development into balance with available or affordable facilities and services. This plan will examine each type of facility separately. The costs of all the facilities will then be added together in order to determine the financial feasibility of the plan. The Capital Facilities Plan is intended to be a planning document. It, therefore, does not contain the level of detail that the annual budget must contain. Some costs in the plan are estimated in order to give citizens a general idea of how much certain types of projects or facilities may cost. Relationship of Capital Facilities Plan to the Budget The Capital Facilities Plan and the City's budget serve different but related purposes. Both are prepared annually. The budget authorizes the amount to be spent during the coming year; whereas the Capital Facilities Plan identifies needed capital facilities over a six year period. A requirement of the Capital Facilities Plan is that it show how the needed facilities will be paid for during at least a six-year period. Because State law requires that no money can be spent on capital projects which are not shown in the Capital Facilities Plan, it is important that the budget not authorize spending on capital facilities not in the Plan. What is a Capital Facility? Capital facilities are those public facilities, including utilities, which are necessary for a government to carry out its functions to provide services to its citizens. Examples are roads, public buildings, schools, parks, water and sewer systems, fire protection and police protection facilities, and libraries. Often the entire collection of these facilities is referred to as infrastructure. Studies or plans (e.g. transportation studies) are not capital facilities and are not included in the Capital Facilities Plan. There are several categories of capital projects and a key distinction is whether new or expanded facilities will serve existing residents or future population growth. Projects may also be proposed to maintain or repair existing capital facilities (cure deficiencies). The categories are as follows and will be used to identify specific projects proposed in the Plan: (M) Major maintenance, repair, renovation, or replacement of an existing facility that do not add additional capacity. (E) New facilities or improvements to existing facilities that provide added capacity to serve the existing population. (N) New facilities or improvements to existing facilities that are built primarily to provide added capacity to serve future population or employment growth. City of Bainbridge Island 2008 Capital Facilities Plan Update 4 of 186 How are Capital Facility Projects Identified? Capital facility projects are generally identified from a planning process for a particular type of facility (e.g. roads, sewer, water, schools, parks, etc) that includes an inventory of existing facilities, an analysis of existing and future demand for service, an analysis of existing or anticipated deficiencies in service (often based on adopted levels of service), and maintenance needs. This planning process is typically incorporated into a local government’s Comprehensive Plan or a specific system plan which is then adopted as part of a Comprehensive Plan. Levels of Service (LOS) Levels of Service (LOS) are usually quantifiable measures of the amount and/or quality of public facilities or services that are provided to the community and are usually expressed as a ratio of amount of service to a selected demand unit. For example, sewer LOS is expressed as 100 gallon per capita per day, public school LOS may be expressed as the number of square feet available per student or as the number of students per classroom. Police or Fire protection may be expressed as the average response time for emergency calls. Parks LOS is often expressed as the number of acres of park per 1,000 population. Once the level of service is decided upon it can then be determined what capital improvements are necessary to 1) cure any existing deficiencies, and 2) maintain that level as the community grows. Prioritizing Capital Projects Since it is unlikely that there is adequate money and resources to implement every capital project in a one-year period, the City goes through a process to prioritize capital projects. The City uses a combination of criteria to prioritize and rank projects that are proposed in a Six-Year Capital Improvement Project (CIP) list, including consistency with the City’s Comprehensive Plan, level-of-service deficiency, financial capacity, budgetary policies, and community need. A recommended Capital Facilities Plan is presented to the City Council for consideration and adoption. Public outreach and participation is integrated throughout this process. City of Bainbridge Island 2008 Capital Facilities Plan Update 5 of 186 II. CAPITAL FACILITIES INVENTORY & PLANNING The following is the City's capital facilities inventory. The inventory is organized by category and includes a current inventory of facilities, a narrative providing a general background of the planning activities and some discussion of future plans, and a discussion of level of service (LOS), if applicable. City Offices, Facilities, & Undeveloped Land City offices are located at several sites due to space constraints at City Hall. Additional City buildings and facilities provide a variety of functions, including public works operations and house cultural and social services. In recent years, the City has also lead an extensive effort to purchase open space and agricultural lands throughout the Island with revenue generated from an $8 million bond approved by voters in 2001. Table 1: City Land and Office Facility Inventory Building and Location Land Area Building Area Owned or Leased Office Uses City Hall Administration, Finance, Planning, & Engineering - 280 Madison Ave. N 1.92 Ac 24,107 SqFt Owned Police Station Police - 625 Winslow Way E 0.82 Ac 7,000 SqFt Owned Municipal Court Municipal Court - 10255 NE Valley Rd. n/a 2,289 SqFt Leased Subtotal Staff Office Space 2.74 Ac 33,396 SqFt Bainbridge Island Commons Social Services & Public Meetings - 223 Bjune Ave. 0.38 Ac 4,975 SqFt Owned Bainbridge Performing Arts (land only) Land leased to BPA for $1/yr through May, 2081 - 200 Madison Ave. N 2.45 Ac n/a Owned Helpline House No-cost lease to Helpline House - 282 Knechtel Way 1.07 Ac 4,400 SqFt Owned Public Works Facility O&M Offices, Shop, and - 7305 NE Hidden Cove Road 12.62 Ac 22,712 SqFt Owned Covered Equipment Storage Public Works Facility Covered Storage - 7305 NE Hidden Cove Road Included 1,524 SqFt Owned Public Works Facility Fueling Facility - 7305 NE Hidden Cove Road Included n/a Owned Land with City-owned utilities 15.42 Ac n/a Owned Wells, pump stations, etc. Total 34.68 Ac 67,007 SqFt City of Bainbridge Island 2008 Capital Facilities Plan Update 6 of 186 Table 2: City Public Works Facilities Inventory Facility Floor Area Function Portable office trailers (4) 2,520 SqFt * Storage, safety & future parks buildings Steel shop building 2,400 SqFt Storage - holds telemetry PW Facility - Wood Building 100 SqFt Well house PW Facility - Shop 7,776 SqFt * Mechanics Shop / Equipment Maintenance PW Facility - Covered Equipment Storage 11,520 SqFt * Covered Equipment Storage PW Facility - Office Trailer 1,792 SqFt * O & M Office Fueling Facility Vehicle Fueling inside covered equipment storage building Total 26,108 SqFt *These facilities are also counted in the main office inventory above. Table 3: City Undeveloped Land Inventory (2005/2006) Location / Description Land Area Owned or Leased Uses High School Rd. near Madison 1.42 Ac Owned No use specified Head of the Bay 30.77 Ac Owned Wellhead protection Off Madison near Wyatt 0.43 Ac Owned Future pocket park Lumpkin Property 11.00 Ac Owned Open space / park Suzuki Property 15.00 Ac Owned Future Police/Court Facility Salter Property 5.00 Ac Owned Open space Johnson Farm 14.51 Ac Owned Open space Suyematsu Farm 15.00 Ac Owned Agricultural Land County Gravel Pit ("Lovgren Pit") 17.00 Ac Owned No use specified Council Site ("Road Shed") 2.00 Ac Owned No use specified Council Site ("Myers Pit") 6.00 Ac Owned No use specified Vincent Road Landfill 40.00 Ac Owned Solid Waste Transfer Station Manitou Beach ("Kane") 1.36 Ac Owned Open space / Habitat restoration M & E Tree Farm 13.00 Ac Owned Open space Morales Property 4.74 Ac Owned Open space Crawford Property 2.30 Ac Owned Open space Near Gazzam Lake ("Close Prop") 64.26 Ac Owned Open space Near Schel-Chelb ("Cool Property") 0.74 Ac Owned Open space Ft. Ward Estates - 5 lots 1.61 Ac Owned Future Park Ft. Ward Parade Ground - 2 lots 0.28 Ac Owned Future Park Lost Valley Trail 8.06 Ac + Owned Open space Yama Property 7.50 Ac Owned Open space Blossom - Pt White Drive 0.88 Ac Owned Open space Blossom - Sullivan Road 3.32 Ac Owned Open space Unocal Site 1.03 Ac Owned Future Park Strawberry Plant 4.20 Ac Owned Future Park City of Bainbridge Island 2008 Capital Facilities Plan Update 7 of 186 Bentryn Property 11.50 Ac Owned Agricultural Land Pritchard Park Phase II - South * 4.02 Ac Owned Future Park Misc. unimproved land 2.24 Ac Owned No use specified Total 289.17 Ac Open Space & Future Park Land Included in Above: 176.16 Ac * The City is presently in the process of acquiring the 23.08 ac. of Pritchard Park Phase II - North. Parks & Trails Most of the parks and trails on Bainbridge Island are owned and managed by the Bainbridge Island Metropolitan Park and Recreation District. The City has a few parks which are generally maintained (with the exception of Waterfront Park) by the Park District under contract to the City. During the past several years, the City has acquired or helped the Park District acquire a large amount of open space and park lands. Plans for this land have generally not yet been developed and the City is in the process of transferring title to several parcels to the Park District. The City has adopted the Bainbridge Island Park and Recreation District Comprehensive Plan, which establishes levels of service for park and recreation facilities for the Island as summarized below. A summary inventory of existing park and recreation facilities is also provided below. Table 4: Park Facility Levels of Service Park Type Definition of Park / Facility Level of Service Neighborhood Park ¼ to ½ mile service area & minimum size 5 acres .9 acres / 1000 Community Park ½ to 3 mile service area & minimum size 20 acres 2.1 acres / 1000 Island-Wide Park within ½ mile drive and minimum size 100 acres 5.3 acres / 1000 Parks - All Categories All parks except State parks 46 acres / 1000 Tennis / Multi-use Asphalt or concrete courts with nets 1 court / 2000 Ball Fields - 200' + Areas designed for softball and baseball 1 field / 2000 Ball Fields - 300' + Areas designed for adult baseball 1 field / 8000 Soccer Fields Areas designed for soccer including goals & nets 1 field /2000 Swimming Pools Covered pool suitable for year-round use 1 pool / 10000 Volleyball Courts Outdoor court with net and sand / soil mixture 1 court / 5000 Mini-Parks/Tot Lots Not Defined Not Specified Spec Use Facilities Public art, parkways, historic sites, etc. Not Determined Linear Parks / Trails Elongated area with lengthwise road or trail Not Determined Equestrian Facilities Areas primarily used by equestrians Not Determined Table 5: Parks & Trails Inventory (2005/2006) City of Bainbridge Island 2008 Capital Facilities Plan Update 8 of 186 Park Site Owner Facilities Size (Acres) Resource Conservancy : Meigs Park Park District None as yet 67.0 W. Port Madison Preserve Park District Trails, picnic shelters, beach access 13.8 Manzanita Park Park District Horse & pedestrian trails 120.0 The Grand Forest Park District Horse & pedestrian trails 240.0 Gazzam Lake Preserve Park District Horse & pedestrian trails 294.0 Battle Point Park, North Park District Fishing pond, trails, picnicking 45.3 Rockaway Beach Parcels Park District None as yet - undesignated 0.5 Hall Property (Eagle Harbor) Park District None as yet - undesignated 11.7 Near Gazzam Lake ("Peters") Park District None as yet - undesignated 53.4 Athletic Parks/Playgrounds : Battle Point Park, South Park District Sport courts, fields, play area, trails, horse arena, maintenance facility 45.0 Strawberry Hill Park Park District Sport courts, field sports, classrooms, skate park , picnicking, administrative offices 17.8 Aaron Tot Park City Park Children's play structure 0.3 Eagledale Park Park District Sport courts, play structure, covered picnic shelter, art center 6.7 Gideon Park Park District Trail and playground 2.5 Hidden Cove Park Park District Ballfields and trails 7.8 Rotary Park Park District Ballfields & children's' play structure 9.8 Gazzam Park Park District Future ballfields, sport courts, trails 24.0 Sands Road Park School District Ballfields 10.0 Resource Activity Parks : Camp Yeomalt Park District Multi-use bldg, trail, picnicking 3.0 Waterfront Park City Park Boat launch, picnicking, tennis courts, playground 8.1 Fay Bainbridge Park State Park Picnicking, camping, boat launch, volleyball, sandy beach 16.8 Fort Ward Park State Park Boat launch, picnicking, trails, beach access 137.0 Spargur Property Park District Shoreline and boat access - to be designed 6.0 Pritchard Park Park District & City Shoreline access, WWII Japanese - American Memorial 21.9 Blakely Harbor Park Park District Picnicking, hand-carry boat access, shoreline 57.0 Recreation Centers : Island Center Park Park District Community hall, picnicking 2.5 City of Bainbridge Island 2008 Capital Facilities Plan Update 9 of 186 Linear Park / Trail : Fairy Dell Trail Park Park District Trail and beach access 2.5 South End Trails Park District Trails, easements, trail implementation 4 linear miles Battle Point Trail Connection Park District Trails, easements, trail implementation 10.7 Special Use Facility : B. I. Aquatic Center Park District (leased) Aquatic Center 1.5 Point White Dock Park District Dock, fishing, clamming 0.3 Other : City Open Space City None - Designated for Open Space / Ag 176.2 Total 1,413.0 Transportation Facilities (Roads, Bike Lanes, Sidewalks, Trails) Of the many types of capital facilities that are constructed, operated and maintained by the City, the most costly and most familiar to citizens are the transportation facilities. Where there are facility needs that involve SR305 or the ferries, the Washington State Department of Transportation assumes the costs. Kitsap Transit pays for facilities that support transit service. The transportation system outside of historic Winslow has suffered from "deferred maintenance". The Pavement Management System (PMS) study conducted for the City in 1992/1995 indicated the wearing surface of many of the roads to be at or near failure, especially the smaller suburban roads. Since many of the Island's roads were initially only scraped and then a thin layer of asphalt applied, the maintenance performed by the City is usually more extensive, and costly, than normal maintenance of "paved" roads. Many roads, having no substantial base before placing asphalt, need considerable base preparation. The PMS study indicated a need for $600,000 per year for 10-12 years in the annual roads maintenance and repaving program to maintain the roads at the then current status; but that study assumed a normal road base. The City has attempted to "reconstruct" some of the roads, rather than just "maintain" their wearing surface, and while it is more time consuming and more costly (initially), the life-cycle costs will be less, and the citizens will have better roads to travel over. The $600,000 amount has proven inadequate to cover the more extensive "reconstruction" as well as normal repaving. In 1998 the City Council increased the annual amount for repaving to about $1,000,000; but that amount has often not been available. Also, in 1998 the City began a program using a "chip-seal" which has allowed many more lane miles to be recovered for the same cost as asphalt overlays. Chip- sealing the roads to halt their deterioration is intended to buy the City time to accomplish the needed reconstruction before the failure of more of the Island's roads. A complete inventory of the Island's transportation facilities is contained in the Island-wide Transportation System Study and a complete inventory of the Island’s non-motorized transportation facilities is contained in the Non-Motorized Transportation Plan. A summary of those facilities follows: City of Bainbridge Island 2008 Capital Facilities Plan Update 10 of 186 Table 6: Transportation Facilities Inventory (2005/2006) Type of Facility Description Example Length FRC 1 * State Highway SR305 6.8 miles FRC 2 * Secondary Arterial Miller Road 35.2 miles FRC 3 * Collectors Oddfellows Road 42.3 miles FRC 4 * Residential Urban Wood Avenue 21.7 miles FRC 5 * Residential Suburban Spargur Loop Road 38.3 miles FRC 6 * Unimproved City Roads (gravel) Walden Lane 10.2 miles Subtotal 154.4 miles Without SR305 & gravel roads 137.5 miles Bike lanes** Shared roadway on paved shoulders High School Road 23.5 miles Sidewalks Paved walkway Madison Ave. 7.6 miles Trails pedestrian, bike, equestrian, etc. The Grand Forest 6.9 miles *FRC = Functional Road Classification; Source: Public Works Department, Pavement Management Program (Klohn Leonoff) ** With the exception of SR305, bike lanes on Bainbridge Island are three to five foot paved shoulders. Bike lanes are reported in lane miles. SR305 is included here. Water Domestic drinking water is supplied by the City of Bainbridge Island, Kitsap County P.U.D. No. 1, South Bainbridge Water Company, numerous smaller public water systems (2 or more hookups), and over 1,000 private single-dwelling wells. The levels of service in the Water Element for water systems on Bainbridge Island are the minimum design standards and performance specifications provided in the 1992 Kitsap County Coordinated Water System Plan. Fire flow requirements were adopted by Ordinance 98-30 and Resolution 98-34 and are tiered based on zoning and type of construction. Residences can satisfy deficiencies by installing individual sprinkler systems. Levels of service are as follows: Table 7: Water System Levels of Service Pressure 30 psi residual Pipe sizing 8" diameter min. (where fire system is required) Storage "Sizing Guidelines for Public Water Systems" Quality Federal and State minimum standards Fire Flow Residential Zone R.04 & R.1 = 500 gpm or sprinkler Fire Flow Residential Other Zones = 1,000 gpm or sprinkler Fire Flow Commercial & LM = 1,000 gpm or don't build The Bremerton-Kitsap County Health District records indicate approximately 170 water systems on the Island that have 2 or more households connected. The number of Group A & B systems are listed below and following is a summary of systems with more than 100 connections. City of Bainbridge Island 2008 Capital Facilities Plan Update 11 of 186 Table 8: Group A & B Water Systems (2005/2006) Group A systems (15 or more connections) 44 Group B systems (under 15 connections) 124 Table 9: Waters Systems with over 100 Connections (2005/2006) Capacity Storage System # Connections (ERU) (MGD) Volumes (gal.) Island Utility 140 455 0.43 400,000 PUD #1 1,688 2,028 0.36 860,000 Meadowmeer (MWSA) 279 283 .45 200,000 South Bainbridge 1,395 1,415 0.90 562,000 Winslow (City) 2,184 4,727 1.00 2,800,000 Total 3,791 6,540 2.43 3,597,000 Most existing water systems were established under state and local guidelines and generally provide high quality water at an adequate pressure and flow rate for residential use. However, because of the number of systems on the Island, it must be concluded that there are systems that may not be in compliance with Department of Health water quality requirements and may not meet minimum requirements of pressure and reliability. It is also concluded that most of the smaller systems have poor or nonexistent fire protection designed into their systems due to the cost of providing large diameter pipes and storage tanks. Winslow Water System The Winslow Water System is owned and operated by the City of Bainbridge Island under the direction and control of the Department of Public Works. It serves an area similar to the historic Winslow city limits plus Fletcher Bay and Rockaway Beach. The system gets all of its water from the eleven wells owned by the City as noted below. Water is pumped into the distribution system both directly from the well pumps and by booster pump stations. A detailed inventory is provided in the Winslow Water System Plan, which is currently being updated and is expected to be adopted in 2007. Table 10: Winslow Water System Well Inventory (2005/2006) Name Capacity Depth Present Yield Head of Bay #1 50 gpm 135 ft. 32 gpm Head of Bay #1A 150 gpm 145 ft. 135 gpm Head of Bay #2 215 gpm 50 ft. 184 gpm Head of Bay #3 100 gpm 50 ft. 270 gpm Head of Bay #4 138 gpm 150 ft. 115 gpm Head of Bay #5 96 gpm 160 ft. 111 gpm Head of Bay #6 110 gpm 70 ft. 91 gpm Lower Weaver * 80 gpm 135 ft. 47 gpm Fletcher Bay 688 gpm 1,050 ft. 500 gpm City of Bainbridge Island 2008 Capital Facilities Plan Update 12 of 186 Sands Ave. #1 288 gpm 1,055 ft. 365 gpm Sands Ave. #2 600 gpm 1,055 ft. 400 gpm Commodore Well 100 gpm 190 ft. 47 gpm Taylor Avenue 80 gpm 600 ft. 56 gpm Total 2,615 gpm 2,297 gpm *Not a potable source - used for construction Under Washington law, water purveyors, including the City, need water rights in order to be assured that it can continue to provide water. The City has "primary" water rights for 2,054 acre- feet per years and "allocated instantaneous capacity" for 3,037 gpm (about 60% over the City's present capacity). According to the existing Winslow Water System plan, the system’s capacity is adequate to serve the needs of the potential build-out population under existing zoning and build-out to the highest density possible (to R-28) in the Land Use Element. The available sources are adequate to serve a potential population of approximately 7,900 or approximately 4,000 units. The system currently serves a population of 3,500 and approximately 3,500 residential equivalent units. There are, however, upgrades necessary to provide adequate fire flow in areas, more efficiently use existing storage capacity, rehabilitate existing wells, and improve system reliability. Sanitary Sewage Disposal The City of Bainbridge Island provides for the collection, treatment, and disposal of effluent in the Winslow service area. The Kitsap County Sewer District #7 treatment plant north of Fort Ward Park serving customers within the District's service area in Fort Ward and the City’s sewer service areas in the Emerald Heights, Point White, North Pleasant Beach, and Rockaway Beach neighborhoods and Blakely School. All other residents not within the service areas of the above districts rely upon on-site septic systems that require approval from the Bremerton-Kitsap County Health District. Levels of service for wastewater treatment systems are typically expressed as the number of gallons of flow per capita per day and the level of treatment provided by the treatment plant. The current and proposed level of service for the Winslow service area follow the Department of Ecology guidelines of 100 gallons per capita per day (flow) and secondary treatment. In areas not served by treatment plants, on-site septic systems must be built to Bremerton-Kitsap County Health District standards that consider combinations of lot size, soil type, infiltration capacity, depth to hardpan, and proximity to surface water among others. The Winslow sanitary sewer system consists of two separate parts: the collection system, and the treatment plant. City of Bainbridge Island 2008 Capital Facilities Plan Update 13 of 186 Table 11: Winslow Sewer Facility Inventory (2005/2006) 5.12 miles gravity sewer with pipes 8" to 16" in diameter 2.69 miles of force main with pipes 4" to 12" in diameter Collection system 11 pumping stations with 100-2,300 gpm pumping capacity Treatment plant Secondary treatment facility located on Donald Place NE The existing collection system capacity has been judged to be adequate through the year 2010 with periodic upgrades in pumping facilities, although the City like other sewage utility providers experiences seasonal inflow and infiltration problems, which the City works to reduce through on going efforts. The existing treatment plant was designed to accommodate an effective population of 10,000 and now serves a population equivalent to 5,500 (with conversion of multifamily and commercial customers to single-family residential equivalents). An upgrade was completed in January, 1996, at a cost of $2.5 million. A number of additional improvements costing some $6 million have been identified by H R Esvelt Engineering. Those improvements are to be completed over the next two years. The City regularly adds emergency generators and telemetry to the system to significantly curtail demands. Where possible, pump stations have been taken out of service to further reduce system costs. Esvelt's study found that the system had adequate capacity for the projected growth for Winslow well past 2012; however the system lacked redundancy. Additional capital projects may be indicated following an inflow/infiltration analysis being done at the request of the Department of Ecology. Surface & Storm Water Management In the Winslow urban area and a few smaller areas, stormwater is managed by a combination of piped collectors, roadside ditches and natural stream channels. All other watersheds and sub- basins on the Island are drained by natural streams and roadside ditches only. The existing natural drainage system consists of wetlands, streams, springs, ditches, and culverts crossing roadways and is labor intensive to maintain. Surface and storm water is management by the City as a utility. A recent Surface and Stormwater Management Plan and ongoing system evaluation are used to identify capital projects. In addition, the City places priority on the improvement and restoration of natural stream channels, particularly undersized or perched culverts, for the improvement of fish passage and fish habitat. City of Bainbridge Island 2008 Capital Facilities Plan Update 14 of 186 III. SIX-YEAR CAPITAL IMPROVEMENT PLAN Provided below is the Six-Year Capital Improvement Plan (CIP) for the City of Bainbridge Island. This CIP list shows the anticipated expense and timing of each project and contains a project description, if available, and the results of the Comprehensive Plan consistency review and level of service (LOS) deficiency analysis. The CIP lists for the special districts on Bainbridge Island are provided in the appendices attached to this document. City of Bainbridge Island 2008 Capital Facilities Plan Update 15 of 186 2008 Capital Improvement Project (CIP) List - 2nd Reading 12/12/07 Projects With Planned Spending in 2008 thru 2013 M E/M E E/N N U Major maintenance, repair, renovation, or replacement of an existing facility that does not add additional capacity Combination of E and M New facilities or improvements to existing facilities that provide added capacity to serve the existing population Combination of E and N New facilities or improvements to existing facilities that are built primarily to provide added capacity to serve future population or employment growth Unclassified Comprehensive Plan Categories GC SC F I U Generally Consistent with Comp Plan Specifically Consistent with Comp Plan Flagged; May not be consistent with Comp Plan Inconsistent with Comp Plan Unclassified Comprehensive Plan Consistency Codes LOS Level of Service $ amounts are rounded to the nearest $1,000 City of Bainbridge Island 2008 Capital Facilities Plan Update 16 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Affordable Housing Affordable Housing - All 2,3500000378 Affordable Housing (Quay Apartment)1,600 Purchase land for affordable housing - Quay Apartment. N No Level of Service Established GC The Bainbridge Island Comprehensive Plan contains policies supporting the use of public lands and fudns for affordable housing. If City bonding is used, housing must be available for less than 80% of median income in Kitsap County. Multi-family units may be a conditional use depending on the zoning. Total for Affordable Housing - All 2,35000001,600 Total for Affordable Housing 2,35000001,600 City of Bainbridge Island 2008 Capital Facilities Plan Update 17 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Facilities Community 281 4,192 3,500 0 0117 Senior Center/Commons Expansion Contribution (to Senior Center)265 Remodel and expand the Senior Center/Commons building. Final design dependent upon needs assessment underway and possible IAC conversion at Waterfront Park. E/N No Level of Service Established SC The Park District Comprehensive Plan specifically identifies the need for expanding the existing Senior Center. 00000669 Senior Center/Commons Roof Repair 25 Re-roof worn section of the Senior Center/Commons Building. M No LOS established besides repair and maintenance of existing facilities. GC Maintenance Total for Community 281 4,192 3,500 0 0290 City Government 00000693 City Hall Emergency Power Generator Upgrade 49 Upgrade the emergency power generator to run the entire City Hall building. E Improvements to existing facilties to maintain LOS. GC General operational improvement project. 0000011 City Hall Lighting 40 Replace parking lot pole lights to comply with lighting ordinance. U No LOS established; project needed to comply with lighting ordinance. GC General operational improvement project. City of Bainbridge Island 2008 Capital Facilities Plan Update 18 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Facilities City Government 50 100 100 0 0663 Head of the Bay Property Storage Yard Restoration 0 Restore North portion of the Head of the Bay property pursuant to the approved Conditional Use Permit. M Repair and environmental preservation of facilties to support LOS. GC Maintenance 250000662 Mechanic Bay Floor Sealer/Non-skid surface 0 Apply floor sealer and non-skid surface to the mechanic bays to improve safety and preserve the existing area. M No LOS besides repair and maintenance of existing facilities. GC General operational improvement project. 3,0003,00000088 Police & Court Facility 829 Design & construct new police & court facility. Cost information from 2006 P&C Needs Analysis Study does not include land acquisition. Design costs assumed at 4% of building & site construction costs. "Soft Costs" cited in the Study are included in the CN cost total. E/N Address space, security and other deficiencies in existing police and court facilities. GC The City of Bainbridge Island Comprehensive Plan Capital Facility Element policy CF 1.9 calls for the joint planning, siting, development, and use of public facilities and services in areas of mutual concern and benefit in order to maximize efficiency, reduce costs, and minimize impacts on the environment. This new facility will consolidate two closely related City departments, one of which is currently housed in a leased facility. 00000742 Public Works Restroom Facility - O&M 100 Install a restroom facility adjacent to the Public Works maintenance building. E/M No Level of Service Established GC General operational improvement project. Total for City Government 3,075 3,100 100 0 01,018 City of Bainbridge Island 2008 Capital Facilities Plan Update 19 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Total for Facilities 3,356 7,292 3,600 0 01,308 City of Bainbridge Island 2008 Capital Facilities Plan Update 20 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Parks & Open Space Open Space & Habitat 00000727 Blakely Harbor Park Shoreline Restoration 250 Evaluate the feasibility and conceptual design of restoration at Blakely Harbor Park, which could include the following elements. Remove wood waste, piling, and other debris to restore intertidal and subtidal habitat. Remove jetties and rip-rap to restore fish passage and geohydrologic dynamics. Remove concrete structure to restore estuarine wetland habitat. Project is partnership between City's Shoreline Stewardship Program and the Wyckoff Superfund Site Trustee Council through the Natural Resource Damage Assessment/Restoration (NRDA) process. Parks District has agreed to conceptual/feasibility evaluation and coordination with Parks District will help inform park plan update. M No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. 0000083 Open Space Improvements 56 Programmatic improvements on yet-to-be acquired open space properties. Capital improvements may include activities such as trail construction and sign installation. The location and scope of these projects will be defined on a case-by-case basis and integrated into future CFPs. E This project help address an existing difficiency in park and open space lands and is not expected to exceed the general level-of-service (LOS) standard of 1,777 acres for park and open space lands. GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage trail systems, the preservation of open space, and the development of park and recreation facilities. The Environmental Element (AG 1) also encourages the preservation of agricultural lands, which some of the open space improvements may help accomplish. The Bainbridge Isalnd Park District Comprehensive Plan, an adopted part of the City's Comprehenisve Plan, also encourages the preservation and improvement of open space. City of Bainbridge Island 2008 Capital Facilities Plan Update 21 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Parks & Open Space Open Space & Habitat 2490000214 Pritchard Park - East Bluff 103 Relocate access road away from eroding bluff to location identified through early 2007 Pritchard Park Master Planning Process, EPA consultation, & geotechnical analysis. Preliminary evaluation suggest road is at risk of bluff failure within the near future (2006 + 3yrs) and design/construction in 2007 is ideal. Remove bulkhead to restore feeder bluff function and revegetate top of slope as a shoreline stewardship/salmon recovery project. Consider planning bulkhead work at same time as Strawberry Plant Restoration Project, Waterfront Park Beach Restoration Project, and/or Creosote Treated Wood Project. Salmon Recovery Funding Board grant ($235k requested, $100k City match) application was submitted September 2006 and has high likelihood of being awarded. E This project help address an existing difficiency in park and open space lands and is not expected to exceed the general level-of-service (LOS) standard of 1,777 acres for park and open space lands. GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. 3000000728 Pritchard Park Milwaukee Dock Eelgrass Restoration 0 Restore approximately 3 acres of eelgrass habitat on the east side of Pritchard Park by filling in an old dredged Wyckoff dock basin. Project may utilize eelgrass transplants or rely on natural colonization. M No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. City of Bainbridge Island 2008 Capital Facilities Plan Update 22 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Parks & Open Space Open Space & Habitat 3000000726 Pritchard Park West Rip-Rap Removal/Beach Restoration 100 Remove remaining rip-rap and intertidal fill and restore beach on western shoreline of Pritchard Park between existing habitat beach and the memorial. This is currently a conceptual project being considered in partnership between the City Shoreline Stewardship Program and the Wyckoff Superfund Site Trustee Council through the Natural Resource Damage Assessment/Restoration process. Beach restoration will also enhance public recreation at Pritchard Park. 2008: $50k-Private, $50k-State grant 2009: $150k-private, $150k-State grant M No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. 2580000213 Shoreline Stewardship Program - Creosote Treated Wood Removal 0 Remove abandoned/derelict creosote treated wood (piles & driftwood) from the shoreline environment. Project funded by and managed in partnership with WA Dept of Natural Resources E This project help address an existing difficiency in park and open space lands and is not expected to exceed the general level-of-service (LOS) standard of 1,777 acres for park and open space lands. GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. City of Bainbridge Island 2008 Capital Facilities Plan Update 23 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Parks & Open Space Open Space & Habitat 00000211 Strawberry Plant Park and Shoreline Restoration 844 Park improvements and shoreline/stream restoration. City is lead and coordinating with Park District on planning and improvements. Salmon Recovery Funding Board grant awarded in 2007 for design. Construction funding is anticipated to largely come from an additional SRFB grant and Natural Resource Damage Assessment funds from the Wyckoff Superfund Site Trustee Council. E This project help address an existing difficiency in park and open space lands and is not expected to exceed the general level-of-service (LOS) standard of 1,777 acres for park and open space lands. GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. 663332000153 WF Park Shoreline Improvements - ALEA Grant 179 Restore the beach including removing all or most of rip-rap bulkhead, renourishment with sand/gravel, and placement of large woody debris (drift wood). Swimming facilities with sand beach where bulkhead is removed. Construct additional dinghy moorage, build boardwalk along shoreline, rebuild stairs, retaining wall, construct ADA pathway on eastern edge of WF Park connecting the waterfront trail (bridge) with Bjuen Drive, landscape, park furniture, signage, A&E, overlook. Required completion June, 2010 E Completion of planned facilities GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. Total for Open Space & Habitat 1,7703320001,532 City of Bainbridge Island 2008 Capital Facilities Plan Update 24 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Parks & Open Space Parks & Road-ends 00000650 Fields For Our Future (Battle Point Soccer Fields)300 Contribution to Park District to replace Battle Point fields 4 & 5 with an infill field system (either FieldTurf or a similar Product) U Need comment GC The Park District Comprehensive Plan establishes LOS standards for soccer fields. This project appears to generally be maintenance. 0000079 Nikkei Memorial Phase II 348 Design & construct memorial wall and related improvements, and relocate existing Taylor Avenue Well building and controls. U U 40 40 40 10 10110 Road-end - Minor Improvements and Maintenance 4 Minor improvements and maintenance for road-ends, including trails and signage. Projects may be in implemented by Parks District. E The City of Bainbridge Island Comprehensive Plan adopts the levels-of-service (LOS) established in the Park District Comprehenisve Plan for parks. There is no specific LOS for road-ends, but policy indicates that all appropriate sites should be improved. SC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmetnal Element, and the Transportation Element, including the Non-Motorized Transportation Plan, which encourage trail systems, the preservation of open space, and the development of park and recreation facilities (GW 1,2,3,4; TR 2), including road-ends and other shoreline access. The Park District Comprehensive Plan also contains policies supporting the improvement of road-ends. City of Bainbridge Island 2008 Capital Facilities Plan Update 25 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Parks & Open Space Parks & Road-ends 00000148 WF Park Dock Repair (until replacement by project 156)129 Repair existing dock facilities at Waterfront Park M Repair of existing facilities GC Maintenance 00000149 WF Park Restrooms 300 Design & construct new restroom for waterfront park. E Completion of planned facilities GC The Winslow Master Plan contains policies calling for improvements to parks and open space, including the development of a master plan for Waterfront Park improvements. Proposed project is replacement of previously removed bathrooms. Total for Parks & Road-ends 40 40 40 10 101,080 Total for Parks & Open Space 1,810 372 40 10 102,612 City of Bainbridge Island 2008 Capital Facilities Plan Update 26 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Transportation Non-motorized 000003 Blakely School NM Improvements 255 Community involvement, design & construction of non-motorized improvements to increase safety of walking & bicycling students within approximately 1 mile of Blakely Schools. E No LOS established besides completion of planned facilities. C The City of Bainbridge Island Non-Motorized Transportation Plan, a sub-element of the Transportation Element of the City Comprehensive Plan, identifies non-motorized improvements in these areas. The proposed projects include facilities called for in the Non-Motorized Plan and other facilites to help make for safe routes to the schools. 5410000704 C40 - 101 N. Madison: SR 305 to Day Rd 762 Maintenance – based shoulder widening program for 40 miles of “core” roadways to enhance non-motorized access and connectivity island-wide. E/M No LOS established besides completion of planned facilities. SC Proposed facilites are called for in the Non-Motorized Transportation Plan. 2620000705 C40 - 103 Eagle Harbor, Bucklin Hill: Wyatt to Blakely (Head of the Bay)161 Maintenance – based shoulder widening program for 40 miles of “core” roadways to enhance non-motorized access and connectivity island-wide. E/M No LOS established besides completion of planned facilities. SC Proposed facilites are called for in the Non-Motorized Transportation Plan. 4400000706 C40 - 106 Miller Road: SR 305 to New Brooklyn 500 Maintenance – based shoulder widening program for 40 miles of “core” roadways to enhance non-motorized access and connectivity island-wide. E/M No LOS established besides completion of planned facilities. SC Proposed facilites are called for in the Non-Motorized Transportation Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 27 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Transportation Non-motorized 00000761 Non-Motorized Trail Construction 1 Construct trails using trail priority recommendations from the Non-motorized Advisory Committee. (Funding of $100,000 from the Non-motorized reserve fund - CC approval of AB 0107, March 14, 2007) 00000126 SR305 NM Improvements Shoulder Widening CO 100 U No LOS established besides completion of planned facilities. F The City of Bainbridge Island Non-Motorized Transportation Plan, a sub-element of the Transportation Element of the City Comprehensive Plan, identifies non-motorized improvements along this road. Without a general scope-of-work, consistency is dependent upon compliance with the planned facilities and design standards of the Non-Motorized Transportation Plan. 00000339 Wilkes School NM Improvements 161 Community involvement, design & construction of non-motorized improvements to increase safety of walking & bicycling students within approximately 1 mile of Wilkes Schools. E C The City of Bainbridge Island Non-Motorized Transportation Plan, a sub-element of the Transportation Element of the City Comprehensive Plan, identifies non-motorized improvements in these areas. The proposed projects include facilities called for in the Non-Motorized Plan and other facilites to help make for safe routes to the schools. Total for Non-motorized 1,24300001,941 Roads & Parking City of Bainbridge Island 2008 Capital Facilities Plan Update 28 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Transportation Roads & Parking 0000033 Ft. Ward Hill Road Reconstruction Phase 1 (Country Club to Bolero) C40 300 Realign and resurface Ft Ward Hill Road, improve utilities, build non-motorized facilities and trail from Country Club to Bolero. E/M Repair of existing facilities plus addition of bicycle lanes. No LOS established for bike lanes besides completion of planned facilities. F This is generally a maintenance project, but will include realignment and expansion of non-motorized transportation facilities. Without further details about planned facilities and the roads location along several sensitive areas, consistency is dependent upon compliance with the Non-Motorized Transportation Plan and Critical Areas Ordinance. 0000042 Halls Hill Road Repairs 37 Road reconstruction of 1,300 ft. including storm drainage, retaining walls, shoulders, and 3T intersection. M Repair of existing facilities. F This project includes the addition of non-motorized facilities and is located along sensitive areas where realignment and slope stabilization will occur. Consistency will be dependent upon compliance with the Non-motorized Transportation Plan and Critical Areas Ordinance. 0000086 Parking Structure Evaluation/Planning 200 Build a 300 car underground City owned and operated parking structure south of Civic center Park & BPA. Includes construction of "Market Lane" street connection on top of structure, connecting Harbor St. North & Madrone Lane. Planning & engineering estimates include permitting. E/N Address deficiency in available parking supply in Winslow and City Hall areas. SC The Winslow Master Plan, an adopted sub-area plan to the City of Bainbridge Island Comprehensive Plan, recommended a parking garage with one possible site identified as part of the civic plaza next to City Hall. City of Bainbridge Island 2008 Capital Facilities Plan Update 29 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Transportation Roads & Parking 800 800 800 800 800111 Roads Capital Preservation Program 503 Annual pavement repair and overlay program. M Repair of existing facilities GC Maintenance 8000000161 Wing Pt. Way Reconstruction NM Improvements (Ferncliff to Fairview)692 Reconstruct Wing Point Way and utilities between Ferncliff and Fairview. Improve sidewalk and bike facilities consistent with the Non-Motorized Transportation Plan. E/M No LOS established besides completion of planned facilities. SC Consistent with Non-Motorized Transportation Plan, Transportation Element, and Utilities Element of the City of Bainbridge Island Comprehensive Plan. Some maintenance. 00000166 Winslow Way Preliminary Design (SR305 to Grow)250 Preliminary design & engineering of multi-phase project to widen sidewalks, replace paving, underground overhead utilities, upgrade water supply and storm drainage, improve intersections at Winslow/Ericksen/Bjune & Winslow/Madison to maintain LOS. Includes streetscape & landscape design to approx. 50%, utility engineering for entire corridor to 90%, roadway, intersection and traffic engineering to approx. 50% completion. E No LOS established besides completion of planned facilities. SC Consistent with Non-Motorized Transportation Plan, Transportation Element, Utilities Element, and Winslow Master Plan of the City of Bainbridge Island Comprehensive Plan. Project is along several sensitive areas and final consistency is dependent upon compliance with the Shoreline Management Master Program. City of Bainbridge Island 2008 Capital Facilities Plan Update 30 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Transportation Roads & Parking 2,0670000163 Winslow Way Streetscape (Erickson to Madison)550 Final engineering & preparation of contract documents; ROW acquisition & construction. Widen sidewalks, replace paving, underground overhead utilities. Coordinate with Project No. 173 - Wyatt Way (Grow To Madison). Final engineering estimate includes permitting. E/N No LOS established besides completion of planned facilities. SC Consistent with Non-Motorized Transportation Plan, Transportation Element, Utilities Element, and Winslow Master Plan of the City of Bainbridge Island Comprehensive Plan. 5,7870000164 Winslow Way Streetscape (Madison to Grow)650 Final engineering & preparation of contract documents; ROW acquisition & construction. Final stage of Winslow Way Master Project. Widen sidewalks, replace paving, underground overhead utilities, upgrade stormwater, sewer and water supply. Coordinate with Project No. 173, Wyatt Way (Grow To Madison). Final engineering estimate includes permitting. E/N No LOS established besides completion of planned facilities. SC Consistent with Non-Motorized Transportation Plan, Transportation Element, Utilities Element, and Winslow Master Plan of the City of Bainbridge Island Comprehensive Plan. 2,0670000165 Winslow Way Streetscape (SR305 to Ericksen)777 Final engineering & preparation of contract documents; ROW acquisition & construction. First construction stage of Winslow Way Master Project. Widen sidewalks, replace paving, underground overhead utilities, upgrade stormwater, sewer and water supply. Final engineering estimate includes permitting. E No LOS established besides completion of planned facilities. SC Consistent with Non-Motorized Transportation Plan, Transportation Element, Utilities Element, and Winslow Master Plan of the City of Bainbridge Island Comprehensive Plan. Project is along several sensitive areas and final consistency is dependent upon compliance with the Shoreline Management Master Program. City of Bainbridge Island 2008 Capital Facilities Plan Update 31 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Transportation Roads & Parking 00000173 Wyatt Way NM & Road Imp. Phase 4 (Grow to Madison)1,724 Add a roundabout at the intersection of Madison and Wyatt to maintain acceptable LOS, plus bike lanes, curb and gutter, planter strips, utilities, and sidewalks on both sides of Wyatt Way between Madison Ave and Grow Ave. E/N Maintains adopted Auto LOS and completes of planned facilities. GC Consistent with Non-Motorized Transportation Plan, Transportation Element, Utilities Element, and Winslow Master Plan of the City of Bainbridge Island Comprehensive Plan. Total for Roads & Parking 11,520 800 800 800 8005,684 Total for Transportation 12,763 800 800 800 8007,625 City of Bainbridge Island 2008 Capital Facilities Plan Update 32 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Sanitary Sewer Collection & Transmission 0000049 Horizon View Sewer LID Construction 15 Close out sewer Local Improvement District. U REMOVE - CITY WORK COMPLETED U Need more information. 82 84 87 89 051 Infiltration/Inflow (I&I) Reduction Program 129 Annual program to locate, identify and repair sources of groundwater infiltration and inflow into sanitary sewers. M Repair, renovation of existing facilities. GC Maintenance 01,000000741 Land Acquisition WWTP 0 Acquire land for WWTP ($1ml Sewer in 2010), E/N The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for flow for existing and future development and to meet water quality standards. GC Required to meet regulatory requirements and provide operational improvements. (Should be consolidated with project #342 or 169) 00320052 Lift Station Upgrade - Island Terrace 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 146000053 Lift Station Upgrade - Klickitat 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilties to maintain adequate LOS. GC Maintenance City of Bainbridge Island 2008 Capital Facilities Plan Update 33 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Sanitary Sewer Collection & Transmission 3818500054 Lift Station Upgrade - Lovell 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 3416500061 Lift Station Upgrade - Lower Hawley 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 0 0 21 95 055 Lift Station Upgrade - Lynwood Center 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 00200056 Lift Station Upgrade - N. Town Woods 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 0251650057 Lift Station Upgrade - Old Treatment Plant 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance City of Bainbridge Island 2008 Capital Facilities Plan Update 34 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Sanitary Sewer Collection & Transmission 0 0 11 51 058 Lift Station Upgrade - Sakai Village 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 0000060 Lift Station Upgrade - SR 305 (Harborview)393 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 270000063 Lift Station Upgrade - Village 70 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilties to maintain adequate LOS. GC Maintenance 4421800064 Lift Station Upgrade - Wing Pt.0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance 01364 0 059 Lift Station Upgrade - Woodward School 0 Upgrade lift station mechancial, electrical equipment and control technology. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance City of Bainbridge Island 2008 Capital Facilities Plan Update 35 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Sanitary Sewer Collection & Transmission 1,1000000759 Pt. Monroe and Lafayette Sewer LID 200 Form a Local Improvement District, and design and install a new sewer collection system for the Pt. Monroe and Lafayette neighborhoods. The collection system will connect to the proposed Fay Bainbridge State Park waste water treatment plant. The project may also include undergrounding of overhead utilities. 116 119 123 126 13012 Sanitary Sewer Collection System Upgrades 112 Annual program to upgrade & replace existing sanitary sewer collection system elements. M Repair, replace existing facilties to maintain LOS. GC Maintenance 027 029 0134 Sanitary Sewer Telemetry Upgrade Program 26 Upgrade or replace existing telemetry supervisory control and data collection equipment. M Repair or replace existing facilties to maintian LOS. GC General operational improvement project. 00000127 Sunday Cove Lift Station Modifications CO 10 Improve the reliability with the installation of a new motor control center, new power and control conductors and conduit, new wetwell, improved current cathodic protection, storm drain rerouting, and landscaping. U REMOVE?- CITY WORK COMPLETED GC Maintenance City of Bainbridge Island 2008 Capital Facilities Plan Update 36 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Sanitary Sewer Collection & Transmission 00000159 Wing Point Sewer 48 Repair/replace a force main that has exceeded its life expectancy and caused two emergency breakages in the last two years. M Repair or replace existing facilties to protect shoreline and meet LOS. GC Maintenance Total for Collection & Transmission 1,697 1,897 523 391 1301,004 Treatment 5,150100000169 Sanitary Sewer Treatment Plant Upgrade - Construction 7,734 Wastewater treatment plant upgrade to meet Washington State Department of Ecology permit effluent limits, reliability and redundancy requirements, as well as addressing noise and odor problems. E/N No LOS established besides completion of planned facilities and compliance with State regulations. GC Required to meet regulatory requirements and provide operational improvements. (Should be consolidated with project #342) 00000342 Sanitary Sewer Treatment Plant Upgrade - Design 216 Engineering to support the plant upgrade E/N No LOS established besides completion of planned facilities and compliance with state regulations. GC Required to meet regulatory requirements and provide operational improvements. (Should be consolidated with project #169) City of Bainbridge Island 2008 Capital Facilities Plan Update 37 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Sanitary Sewer Treatment 4500000657 Wastewater Treatment Plant Outfall 50 Design and extend the outfall of the wastewater treatment plant beyond the existing placement. M No LOS established; project needed to avoid damage fees from DNR for loss of Geoduck harvests near outfall. U Need more information. Total for Treatment 5,6001000007,999 Total for Sanitary Sewer 7,297 1,997 523 391 1309,004 City of Bainbridge Island 2008 Capital Facilities Plan Update 38 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Stormwater Drainage & Treatment 475 475 475 475 47520 Drainage/Culvert Annual Upgrade Program 542 Annual program to identify and replace failing, damaged or undersized drainage culverts. M Repair of existing facilities GC Maintenance Total for Drainage & Treatment 475 475 475 475 475542 Total for Stormwater 475 475 475 475 475542 City of Bainbridge Island 2008 Capital Facilities Plan Update 39 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Production 30240000654 Commodore Well Perched Aquifer Enhancement Source-5 0 Drill an additional well and try to relocated water rights to expand well capacity at the site. E/N Completion of planned facilities; intended for existing and future growth. U Need more information. 0 120 540 0 0655 Fletcher Bay Aquifer Well 0 Drilling of a new well in the Fletcher Bay Aquifer. E/N Completion of planned facilities for existing and future growth to maintain LOS. U Need more information. 080000684 Generator Sands Ave and Head of the Bay Pump Stations 0 Install permanent emergency power generators to Sands Ave and Head of the Bay pump stations to allow water system to provide water during a power outage. M Replace, retrofit existing equipment to support LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 00000644 Head of the Bay Well 2 & 5 Rehabilitation 85 Rehabilitate wells 2 & 5 to increase production of the well field. In addition, install overflow pipe for tank storage. E/N Repair and maintenance of existing facilities for existing and future growth to maintain LOS U Need more information. City of Bainbridge Island 2008 Capital Facilities Plan Update 40 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Production 00000341 Head of the Bay Wellfield Upgrade, Phase III 376 Increase booster pump capacity and add an emergency generator at wellfield to meet LOS. E/M Completion of planned facilities for existing and future growth to maintain LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 80 82 506 0 0311 High School Reservoir Well & Building 168 Build new well and building E/N Completion of planned facilities for existing and future growth to maintain LOS. U Need more information. 0 0 0 60 280656 Sands Well #2, New Well 0 Drill a new well to replace Sands Well #2. E/N Completion of planned facilities for existing and future growth to maintain LOS. U Need more information. 830000646 Taylor Ave Well Rehabilitation and future aquifer resource planning.0 Rehabilitate the Taylor Ave Well and conduct future aquifer resource acquisition planning. E/N Repair and maintenance of existing facilities for existing and future growth to maintain LOS U Need more information. City of Bainbridge Island 2008 Capital Facilities Plan Update 41 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Production 50615000131 Water Supply - New Well (Drilling & Building)0 Drill new well to provide redundancy for current water supplies (especially during peak summer demand) and provide the ability to better manage water resources by redistributing water system demand on aquifers. E/N Completion of planned facilities for existing and future growth to maintain LOS. GC This project is to provide redundancy for existing infrastructure and better manage existing water resources. This project is consistent with the City of Bainbridge Island Comprehensive Plan. 2060000132 Water Supply - Weaver Facility Reconstruction 49 Relocation of non-potable pumping station. E/N Completion of planned facilities for existing and future growth to maintain LOS. U Need more information. 0000600739 Water System Improvements/Upgrades 0 The updated Water System Master Plan will provide projected improvements to maintain a functional system E/N Study of existing system intended for existing and future populations to maintain LOS; project needed to comply with DOH. U Need more information. 0003010147 Water Wellhead Protection 0 Restoration/reclamation of wellhead protection area at Head of the Bay from past city activities. M Repair and environmental preservation of facilties to support LOS. GC Maintenance. Total for Production 448 1,137 1,046 361 880678 Storage & Distribution City of Bainbridge Island 2008 Capital Facilities Plan Update 42 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Storage & Distribution 0 0 45 93 09 Cave Ave Watermain Upgrade (Gilmore to Winslow Way)0 Replacement of old and undersized water mains to improve pressure and fire flow to meet LOS standards. M Replace existing facilities to maintain adequate LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 0561160010 Cherry Ave Watermain Upgrade (South of Wing Pt)0 Replacement of old and undersized water mains to improve pressure and fire flow to meet LOS standards. M Replace existing facilities to maintain LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 60300000734 Fletcher Bay Well Building Replacement Phase IV-Source 4 0 Replace damaged wood building with a new structure made from CMU, which is more appropriate for wet and corrosive conditions such as those at the Fletcher Bay Well facility. Project to include permanently mounted generator and salt storage. E/M Repair, renovation of existing facilities to maintain adequate LOS. GC Maintenance City of Bainbridge Island 2008 Capital Facilities Plan Update 43 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Storage & Distribution 0 0 57 383 036 Grow Ave Watermain Upgrade (High School Rd. to Wyatt)0 Replacement of old and undersized water mains to improve pressure and fire flow to meet LOS standards. M Replace existing facilities to maintain LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 0 0 28 93 040 Grow High Zone Main (Wyatt to Shepard) WM 0 Water main replacement project to increase fire flow and eliminate undersized AC pipe. M Replace existing facilities to maintain adequate LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 0004500687 High School Reservoirs Recoating (Exterior/Interior)0 Resurface the interior and exterior of the existing High School Reservoirs (1.0 Million Gallon Tank & 1.5 Million Gallon Tank) which have exceed there life expectancy. M Repair and maintenance of existing facilities to maintain LOS. GC Maintenance 0 0 45 167 081 Olympic Dr. SE Watermain Upgrade (Winslow Way to Ferry Terminal)0 Replacement of old and undersized water mains to improve pressure and fire flow to meet LOS standards. M Repair, renovation of existing facilties to maintain adequate LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 44 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Storage & Distribution 000182090 Pressure Zone Extension 0 Water System Plan projects to improve water pressure E/N Extension of facilities to maintain LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City 0 131 328 0 091 Pressure-Grand Ave Reservoir 0 Improved use of water stored in reservoir. E/M Repair or replace existing facilties to maintian LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for storage, pressure, and fire flow in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 12066000092 Pressure-High School Reservoir 0 Improved use of water stored in reservoir. E/M Repair or replace existing facilties to maintian LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for storage, pressure, and fire flow in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 45 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Storage & Distribution 0 0 17 68 0118 Shepard-High Zone Watermain Upgrade (Grow to Government Way)0 Replacement of water main and conversion from low to high pressure zone M Replace existing facilities to maintain LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 3000000642 Telemetry Technology Conversion 0 The City will upgrade all its telemetry software for both the water and the wastewater system to digital technology M Replace existing facilities to support LOS. GC General operational improvement project. 0 0 0 21 112733 Water Main Upgrade-Madison Ave from High School Rd to Wallace Way 0 Replace 1,100 feet of 6" AC water main on Madison Ave from High School Rd to Wallace with a 12" ductile iron. E/N Replace existing facilties to maintain adequate LOS. GC The Comprehensive Plan establishes LOS standards for water utilities. This project will update existing facilities to meet LOS standards. 116 122 126 127 128145 Water Mains Upgrade - Annual 112 Replacement of old and undersized water mains to improve pressure and fire flow to meet LOS standards. M Replace existing facilities to improve water pressures and fire flow to meet LOS. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 46 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Storage & Distribution 161816000130 Water Supply - New Reservoir 0 New reservoir to address storage deficiencies identified in Water System Plan. E/N Completion of planned facilities for existing and future growth to maintain LOS. GC The project will add storage infrastructure to meet adopted level-of-service (LOS) standards for storage, pressure, and fire flow in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. 27 0 28 0 30137 Water Telemetry Upgrade Program 0 Annual upgrade of water monitoring and control technology (telemetry) equipment. M Repair or replace existing facilties to maintian LOS. GC Project supports operations of water system. 1,8000000756 Winslow Way Utilities (Erickson to Madison)0 Design and construct failing water, sewer, and stormwater assets. E/M The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and flow for existing and future development and to increase reliability. GC Maintenance and improvements to meet LOS standards. 4,5000000757 Winslow Way Utilities (Madison to Grow)0 Design and construct failing water, sewer, and stormwater assets. E/M The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and flow for existing and future development and to increase reliability. GC Maintenance and improvements to meet LOS standards. City of Bainbridge Island 2008 Capital Facilities Plan Update 47 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Water Storage & Distribution 2,7000000758 Winslow Way Utilities (SR305 to Erickson)0 Design and construct failing water, sewer, and stormwater assets. E/M The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and flow for existing and future development and to increase reliability. GC Maintenance and improvements to meet LOS standards. 1670000177 Wyatt-High Zone Main (Madison to Grow)57 Replacement of 6-inch AC watermain with 8-inch DI to improve fire flow/pressure and reliablility (in conjunction with Wyatt Way NM & street improvements). See: 2006 Winslow Water Plan page 4-11. E/M The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and flow for existing and future development and to increase reliability. GC The project will upgrade existing infrastructure to meet adopted level-of-service (LOS) standards for pressure and fire flow for existing development in accordance with the City's Comprehensive Water System Plan and the Water Resources Element of the City of Bainbridge Island Comprehensive Plan. Total for Storage & Distribution 9,949 2,085 790 1,583 270169 Total for Water 10,398 3,222 1,837 1,945 1,150847 City of Bainbridge Island 2008 Capital Facilities Plan Update 48 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Tax Supported 00000352 2007 Vehicle Replacement - Pickup #4203 55 Replace vehicle # 4203 in O&M Roads section M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 00000353 2007 Vehicle Replacement - Pickup #7201 30 Replace vehicle #7201 in Engineering M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 4400000750 Capital Equipment Replacement Program - 2009 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 4112 (replacement) 1999 International Dumptruck $175,000, Roads Division 2. Vehicle 4204 (replacement) 2001 Dodge pickup $35,000, Roads Division 3. Vehicle 4211(replacement) 2001 Chevy pickup $35,000, Roads Division 4. Vehicle 4305 (replacement) 2004 Bandit chipper $35,000, Roads Division 5. Vehicle 5203 (replacement) 2001 Chevy pickup $35,000, Facilities Division 6. Vehicle 6202 (replacement) 1998 Chevy pickup $35,000, Facilities Division 7. Vehicle 7208 (replacement) 1999 Jeep Cherokee $25,000, Engineering Division 8. Vehicle 8208 (replacement) 2000 Ford pickup $25,000, Planning Department 9. Capital Equipment-Annual Expenditures (Undesignated) $20,000 10. Capital Equipment-O&M Roads, Fleet & Facilities (Earmark funds for breakage, obsolescence or new mission requirements) $20,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. City of Bainbridge Island 2008 Capital Facilities Plan Update 49 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Tax Supported 0375000751 Capital Equipment Replacement Program - 2010 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 4205 (replacement) 2003 Chevy flatbed $55,000, Roads Division 2. Vehicle 4206(replacement) 2003 Chevy flatbed $55,000, Roads Division 3. Vehicle 4209 (replacement) 2000 Ford boom truck $75,000, Roads Division 4. Vehicle 4303 (replacement) 2002 Spectre trailer $15,000, Roads Division 5. Vehicle 5202 (replacement) 2001 Chevy pickup $35,000, Facilities Division 6. Vehicle 5205 (replacement)2000 Chevy pickup $35,000, Facilities Division 7. Vehicle 5302 (replacement)2002 Spectre trailer $15,000, Facilities Division 8. Vehicle 7209 (replacement)1999 Ford pickup $25,000, Engineering Division 9. Vehicle 8207 (replacement)1998 Ford Taurus $25,000, Planning Department 10. Capital Equipment-Annual Expenditures (Undesignated) $20,000 11. Capital Equipment-O&M Roads, Fleet & Facilities (Earmark funds for breakage, obsolescence or new mission requirements) $20,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 0033500749 Capital Equipment Replacement Program - 2011 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 4104 (replacement) 2003 Elgin Street Sweeper $175,000, Roads Division 2. Vehicle 4109 (replacement) 1994 International Dumptruck $125,000, Roads Division 3. GPS installation in mowers/sweepers (new equipment) $15,000, Roads Division 4. Capital Equipment-O&M Fleet and Facilities (Earmark funds for breakage, obsolescence or new mission requirements) $20,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. City of Bainbridge Island 2008 Capital Facilities Plan Update 50 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Tax Supported 0002150748 Capital Equipment Replacement Program - 2012 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 4203 (replacement) 1996 Ford Pickup $55,000, Roads Division 2. Vehicle 4308 (replacement) 1984 Pup Trailer $120,000, Roads Division 3. Capital Equipment-Annual Expenditures (Undesignated) $20,000 4. Capital Equipment-O&M Fleet and Facilities (Earmark funds for breakage, obsolescence or new mission requirements) $20,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 0000405755 Capital Equipment Replacement Program - 2013 0 Capital Equipment Annual Vehicle Replacement 1. 4102 Mower boom and head (retain tractor) $40,000 (Roads) 2. 4103 Mower boom and head (retain tractor) $40,000 (Roads) 3. 4301 2002 Patch King $50,000 (Roads) 4. 6204 2002 Chevy Malibu $25,000 (Admin) 5. 7211 2001 Chevy Malibu $25,000 (Admin) 6. 4302 1974 T-Weld Pup Trailer $110,000 (Roads) 7. 7205 1998 Chevy Pickup $25,000 (Eng) 8. 7206 1998 Chevy Pickup $25,000 (Eng) 9. 7207 1998 Ford Pickup $25,000 (Eng) 10. Capital Annual Expenditures (undesignated) $20,000 11. Capital Equipment (Roads, Fleet and Facililties) $20,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. City of Bainbridge Island 2008 Capital Facilities Plan Update 51 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Tax Supported 000075675 Capital Equipment, Asphalt Zipper 0 Asphalt Zipper, used for grinding out asphalt to prepare for paving or repairing roads. E/N Purchase equipment to maintain LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 1200000651 City Boat for Harbor and Shoreline Activities 0 Purchase a boat for the use of the Harbormaster, the Shoreline Management and Stewardship Programs, and Water Resources Program. A multi-purpose work vessel of at least 21' in length is needed for existing and new city water borne programs and policies. These include managing activities in the city’s harbors, water flow monitoring, and educational stewardship activities such as beach seining. It would also be useful for O&M to bring people and materials to road ends and outfalls that are otherwise inaccessible. E No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports important operations in support of the Comprehensive Plan. 00000763 Crack Sealer - Roads 45 Purchase chipper box 250505754 Generator Load Testing and Sound Attenuation Program 0 Replace portable generator #4 out of the City equipment fleet that has exceeded its life expectancy with a 150 KW portable generator. M No Level of Service Established GC Maintenance City of Bainbridge Island 2008 Capital Facilities Plan Update 52 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Tax Supported 49 48 48 49 5084 Other Capital Equipment - Annual 48 Unplanned capital equipment replacement due to breakage or obsolecence. M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 218 230 266 197 109181 Police vehicle replacement 161 Provide for lease payments on police vehicles: 2008 - 5 new, 11 remaining leases 2009 - 5 new, 13 remaining leases 2010 - 5 new, 10 remaining leases 2011 - 5 new, 10 remaining leases 2012 - 5 new, 5 remaining leases 2013 - 5 new M No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports public safety operations Total for Capital Equipment - Tax Supported 852 653 655 461 644339 Capital Equipment - Fee Supported 00000351 2007 Vehicle Replacement - Dump Truck #4108 105 Replace vehicle # 4108 in O&M Roads section E/M C The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. City of Bainbridge Island 2008 Capital Facilities Plan Update 53 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Fee Supported 00000670 Capital Equipment Replacement Program - 2008 95 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 1207(replacement) 2001 GMC Pickup $55,000, Water Division 2. Stormwater & Sewer Camera (upgrade) $25,000, Stormwater/Sewer Division 3. Capital Equipment-O&M Utilities Water (Earmark funds for breakage, obsolescence or new mission requirements) $15,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 300000673 Capital Equipment Replacement Program - 2009 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 3301 (replacement) 2001 Spectre Trailer $15,000, Stormdrain Division 2. Capital Equipment-O&M Utilities Water (Earmark funds for breakage, obsolescence or new mission requirements) $15,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 070000674 Capital Equipment Replacement Program - 2010 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 1206 (replacement) 1999 GMC Service Van $55,000, Water Division 2. Capital Equipment-O&M Utilities Stormdrain (Earmark funds for breakage, obsolescence or new mission requirements) $15,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. City of Bainbridge Island 2008 Capital Facilities Plan Update 54 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Fee Supported 0013000672 Capital Equipment Replacement Program - 2011 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 2201 (replacement) 2003 Chevy Express Van $35,000, Sewer Division 2. Vehicle 1202(replacement) 2003 Chevy Express Van $35,000, Water Division 3. Vehicle 1208 (replacement) 1992 Chevy Service Van $45,000, Water Division 4. Capital Equipment-O&M Utilities Sewer (Earmark funds for breakage, obsolescence or new mission requirements) $15,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 0002500671 Capital Equipment Replacement Program - 2012 0 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 2101 (replacement) 1994 Aquatech $200,000, Sewer Division 2. Vehicle 1203(replacement) 2001 Chevy Express Van $35,000, Water Division 3. Capital Equipment-O&M Utilities Stormwater (Earmark funds for breakage, obsolescence or new mission requirements) $15,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 000015737 Capital Equipment Replacement Program - 2013 0 Capital Equipment Annual Vehicle Replacement 1. Capital Equipment (Sewer) $15,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. City of Bainbridge Island 2008 Capital Facilities Plan Update 55 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Capital Equipment Capital Equipment - Fee Supported 15 15 10 15 10736 Generator Load Testing and Sound Attenuation Program 35 This project provides the installation of sound attenuation to three of the four generators in urban areas that do not have any sound dampening devices. In addition, the project provides load bank testing to the City emergency generators. M Repair and maintenance of existing facilities to maintain LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. Noise control is consisent with Comprehensive Plan. Total for Capital Equipment - Fee Supported 45 85 140 265 25235 Total for Capital Equipment 897 738 795 726 669574 City of Bainbridge Island 2008 Capital Facilities Plan Update 56 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Software Purchase 00000180 MUNIS Software Module Additions 75 Purchase and implement additional MUNIS modules. U U n/a - not a capital facility Total for Purchase 0000075 Total for Software 0000075 City of Bainbridge Island 2008 Capital Facilities Plan Update 57 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2013 Plan 2012 Plan 2011 Plan 2010 Plan 2009 Plan 2008 Plan Project ID Total All Projects 39,346 14,895 8,069 4,346 3,23424,186 City of Bainbridge Island 2008 Capital Facilities Plan Update 58 of 186 IV. FINANCIAL CAPACITY ANALYSIS The City conducts a financial capacity analysis in order to evaluate the City’s ability to fund capital expenditures along with general operations. The following pages analyze the City’s financial capacity including anticipated revenues from grants, low-interest loans, bonds, and other sources. City of Bainbridge Island 2008 Capital Facilities Plan Update 59 of 186 2008 2009 2010 2011 2012 2013 BEGINNING CASH BALANCES 7,958 7,751 8,807 10,791 10,767 14,616 GENERAL REVENUES Property Taxes - General Levy 6,250 6,460 6,660 6,851 7,034 7,210 Sales & Use Tax 3,585 3,908 4,259 4,643 5,061 5,516 Utility, B & O / Other Taxes 3,885 4,157 4,448 4,759 5,093 5,449 Real Estate Excise Tax 2,570 2,737 2,915 3,104 3,306 3,521 Licenses & Permit Fees 317 338 360 383 408 434 Intergovernment 384 453 473 494 516 542 Charges for Services 198 211 225 239 255 271 Fines & Forfeits 312 332 354 377 401 427 B&DS + ROW Charges 2,115 2,252 2,399 2,555 2,721 2,898 Grants Received - Operating 235 300 268 284 276 280 Interest, Misc & Other (incl FAR Purch's)1,335 1,674 2,252 2,883 3,568 4,470 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL GENERAL REVENUES 21,186 22,822 24,612 26,572 28,638 31,019 DEDICATED REVENUES Commercial Parking & Hotel/Motel Tax 675 668 715 737 773 804 Property Taxes - GO Bond Levies 560 544 1,122 1,123 1,252 1,252 MV Fuel Tax 580 596 632 669 709 756 Parking Revenues 445 463 481 501 521 541 Utility Charges - Water 2,338 2,572 2,772 2,989 3,222 3,473 Utility Charges - Sewer 2,594 2,957 3,188 3,437 3,705 3,994 Utility Charges - Storm Water 1,905 2,229 2,403 2,590 2,792 3,010 Other Utility Revenues 1,201 932 1,093 1,150 1,212 1,284 Grants & Other Contributions - Capital 4,092 6,822 3,000 3,000 2,000 2,000 L.I.D. Assessments 410 684 667 781 768 754 Interest, Misc & Other 615 374 548 593 592 679 FAR / ROW - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL DEDICATED REVENUES 15,416 18,841 16,622 17,569 17,546 18,547 TOTAL OPERATING REVENUES 36,601 41,663 41,234 44,141 46,184 49,565 OTHER SOURCES Voter Approved Bonds - 7,000 - - - - City Council Approved Bonds 7,500 4,428 1,100 - - - PWTF Debt Issued 3,000 9,000 5,000 1,000 1,000 - Revenue Bonds 5,000 7,000 - - - - LID Bonds Issued - - 1,500 - - - Land Proceeds 750 2,750 - - - - Capital Leases - 250 3,000 - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL REVENUES AND OTHER SOURCES 52,851 72,091 51,834 45,141 47,184 49,565 CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS SOURCES OF FUNDS City of Bainbridge Island 2008 Capital Facilities Plan Update 60 of 186 2008 2009 2010 2011 2012 2013 GENERAL OPERATING EXPENDITURES Executive / Legislative 3,841 4,071 4,316 4,575 4,849 5,140 Intergovernment Expend's (Except Util)702 744 788 836 886 939 Municipal Court 456 483 512 543 575 610 Finance & I.T - General Government 4,151 4,400 4,664 4,944 5,241 5,555 Police 2,800 2,968 3,146 3,335 3,535 3,747 Planning / Building 4,029 4,271 4,527 4,799 5,086 5,392 Public Works 2,767 2,933 3,109 3,295 3,493 3,703 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL GENERAL OPERATING EXPENDITURES 18,745 19,870 21,062 22,326 23,666 25,086 SPECIFIED OPERATING EXPENDITURES Street & Road Maintenance 1,350 1,431 1,517 1,608 1,704 1,806 Utility Opr'g - Water 1,651 1,734 1,820 1,911 2,007 2,107 Utility Opr'g - Sewer 1,838 1,930 2,026 2,128 2,234 2,346 Utility Opr'g - Storm Water 1,506 1,596 1,692 1,793 1,901 2,015 Capitalized Employee Support & Planning - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL SPECIFIED OPERATING EXPENDITURES 6,344 6,690 7,055 7,440 7,846 8,274 OPERATING EXPENDITURES 25,090 26,560 28,117 29,766 31,512 33,360 DEBT SERVICE COST 3,782 5,129 6,835 7,329 7,477 7,467 CAPITAL EXPENDITURES (from CIP) Non-Motorized Transportation 1,941 1,243 - - - - Transportation Projects 5,684 11,520 800 800 800 800 Capital Equipment 574 897 738 795 726 669 Parks, Trails & Open Space 2,612 1,810 372 40 10 10 Utility - Water 847 3,998 3,222 1,837 1,945 1,150 Utility - Sewer 9,004 11,097 1,997 523 391 130 Utility - Storm Water 542 3,075 475 475 475 475 Affordable Housing 1,600 2,350 - - - - Facilities/City Offices 1,383 3,356 7,292 3,600 - - ----------- ----------- ----------- ----------- ----------- ----------- CAPITAL EXPENDITURES 24,186 39,346 14,896 8,070 4,347 3,234 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL EXPENDITURES 53,058 71,035 49,849 45,165 43,335 44,060 INCREASE/(DECREASE) - FUND BALANCES (207) 1,056 1,985 (24) 3,849 5,505 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL USES OF FUNDS 52,851 72,091 51,834 45,141 47,184 49,565 CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS USES OF FUNDS City of Bainbridge Island 2008 Capital Facilities Plan Update 61 of 186 2008 2009 2010 2011 2012 2013 POPULATION 23,030 23,450 23,800 24,140 24,461 24,951 REAL ECONOMIC GROWTH 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% GDP FACTOR 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% PRIOR YR 2nd 1/2 SEATTLE CPI (U)4.00% 4.00% 4.00% 4.00% 4.00% 4.00% PER CAPITA STATE SHARED FUNDS : Liquor Profits 7.41 7.78 8.17 8.58 9.01 9.46 Liquor Tax 3.93 4.13 4.33 4.55 4.78 5.02 MV Excise Tax - - - - - - Crim Justice $0.97 1.02 1.07 1.12 1.18 1.24 -------- -------- -------- -------- -------- -------- SUB-TOTAL 12.31 12.93 13.57 14.25 14.96 15.71 Gas Tax (unrestr.)21.16 23.28 24.44 25.66 26.94 28.29 Gas Tax (Arterial)- - - - - - Utility Rate Increase - Water 5.80% 8.00% 5.80% 5.80% 5.80% 5.80% Utility Rate Increase - Sewer 9.19% 12.00% 5.80% 5.80% 5.80% 5.80% Utility Rate Increase - Storm Water 15.00% 15.00% 5.80% 5.80% 5.80% 5.80% ASSESSED VALU'N ($ in MM's)6,600 6,600 6,600 6,600 6,600 6,600 New Cosntruction ($ in MM's)150 150 150 150 150 150 LEVY RATE ($ per $1,000 AV)0.981 0.903 0.831 0.765 0.704 0.704 SPECIAL LEVY RATE 0.086 0.079 0.073 0.067 0.111 0.111 INVESTMENT YIELD 5.00% 4.50% 4.50% 4.50% 4.50% 4.50% CITY STAFF - FTE 151.00 151.00 151.00 151.00 151.00 151.00 GROWTH IN EXPENDITURES & DEBT SERVICE 0.0% 9.8% 10.3% 6.1% 5.1% 4.7% OPERATING COST GROWTH RATE FACTOR 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS ASSUMPTIONS City of Bainbridge Island 2008 Capital Facilities Plan Update 62 of 186 EXISTING DEBT : 2008 2009 2010 2011 2012 2013 GENERAL OBLIGATION DEBT 1996 / 2005 L.T.G.O. Bonds 603 668 910 913 908 907 1997 L.T.G.O. Bonds - - - - - - Loans, Land Contracts & Leases 244 238 129 60 42 - 1998 L.T.G.O. Bonds 671 667 842 838 839 833 1999 L.T.G.O. Bonds 238 242 - - - - 2002-04 .G.O. Bonds 542 544 536 537 666 666 UTILITY DEBT 1998 L.T.G.O. Bonds (Utility Share)65 66 67 68 69 69 1995 L.T.G.O. (Water/Sewer) Bonds 287 289 - - - - PWTF LOANS PWTF Loans for Sewer 502 494 486 477 467 457 PWTF Loans for SSWM 198 190 182 179 175 172 L.I.D. No - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL EXISTING DEBT SERVICE 3,350 3,398 3,151 3,071 3,166 3,103 NEW DEBT : 2011-2012 G.O. Bonds - - 586 586 586 586 L.T.G.O. Bonds 441 1,069 1,439 1,531 1,531 1,531 L.T.G.O. Bonds - Sewer - - - - - - Loans & Capital Leases 118 86 23 274 274 274 PWTF Loans for Water - - 53 53 53 53 PWTF Loans for Sewer - 158 421 527 579 632 PWTF Loans for SSWM - - 158 158 158 158 PWTF Loans for Streets - - - - - - Revenue Bonds for Water - - 167 167 167 167 Revenue Bonds for Sewer - 418 837 837 837 837 LID Bonds - Streets - - - 126 126 126 LID Bonds - Water - - - - - - LID Bonds - Sewer - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL OF ALL DEBT SERVICE 3,909 5,129 6,835 7,329 7,477 7,467 TOTAL G.O./LTGO BONDS 2,495 3,190 4,313 4,405 4,530 4,523 TOTAL UTILITY DEBT 352 931 1,703 1,809 1,863 1,916 L.I.D. DEBT / PWTF Loans 700 684 667 781 768 754 Capital Leases 362 324 152 334 316 274 CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS DEBT SERVICE PROJECTIONS City of Bainbridge Island 2008 Capital Facilities Plan Update 63 of 186 2008 2009 2010 2011 2012 2013 BEGINNING WORKING CAPITAL 3,702 3,899 4,021 5,001 4,451 3,886 REVENUES Charges for Service 2,338 2,572 2,772 2,989 3,222 3,473 Capital Contributions 365 374 383 400 418 437 L.I.D. Assessments - - - - - - Interest & Other Revenues 186 190 195 204 213 222 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL REVENUES 2,888 3,136 3,350 3,592 3,853 4,132 OPERATING EXP. + DEBT SVC Finance - Billing & Acct'g + Rent 646 678 712 748 785 824 Finance - Debt Service 123 215 294 338 361 383 Public Works 1,005 1,055 1,108 1,164 1,222 1,283 ----------- ----------- ----------- ----------- ----------- ----------- OPERATING EXP. + DEBT SVC 1,774 1,949 2,114 2,249 2,368 2,490 CAPITAL EXPENDITURES Finance - - - - - - Public Works - Equipment 70 66 34 56 106 10 Public Works - Projects 847 3,998 3,222 1,837 1,945 1,150 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL CASH OUTLAYS 2,691 6,013 5,370 4,142 4,419 3,650 Voter Approved Bonds - - - - - - City Council Approved Bonds - - - - - - PWTF Debt Issued - 1,000 3,000 - - - Revenue Bonds - 2,000 - - - - LID Bonds Issued - - - - - - Capital Leases - - - - - - NET TRANSFERS IN/(OUT)- - - - - - ----------- ----------- ----------- ----------- ----------- ----------- ENDING WORKING CAPITAL 3,899 4,021 5,001 4,451 3,886 4,368 MEMO : DEPRECIATION - - - - - - CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS WATER UTILITY City of Bainbridge Island 2008 Capital Facilities Plan Update 64 of 186 2008 2009 2010 2011 2012 2013 BEGINNING WORKING CAPITAL 1,005 939 399 395 888 1,602 REVENUES Charges for Service 2,594 2,957 3,188 3,437 3,705 3,994 Capital Contributions 425 400 410 428 448 468 L.I.D. Assessments 400 410 420 439 459 480 Interest & Other Revenues 75 77 79 82 86 90 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL REVENUES 3,494 3,844 4,097 4,387 4,698 5,031 OPERATING EXP. + DEBT SVC Finance - Billing & Acct'g + Rent 595 625 656 689 724 760 Finance - Debt Service 660 1,291 2,044 2,186 2,253 2,318 Public Works 1,243 1,305 1,370 1,439 1,510 1,586 ----------- ----------- ----------- ----------- ----------- ----------- OPERATING EXP. + DEBT SVC 2,497 3,221 4,071 4,314 4,487 4,663 CAPITAL EXPENDITURES Finance - - - - - - Public Works - Equipment 60 66 34 56 106 10 Public Works - Projects 9,004 11,097 1,997 523 391 130 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL CASH OUTLAYS 11,561 14,384 6,102 4,893 4,984 4,803 Voter Approved Bonds - - - - - - City Council Approved Bonds - - - - - - PWTF Debt Issued 3,000 5,000 2,000 1,000 1,000 - Revenue Bonds 5,000 5,000 - - - - LID Bonds Issued - - - - - - Capital Leases - - - - - - NET TRANSFERS IN/(OUT)- - - - - - ----------- ----------- ----------- ----------- ----------- ----------- ENDING WORKING CAPITAL 939 399 395 888 1,602 1,830 MEMO : DEPRECIATION - - - - - - CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS SEWER UTILITY City of Bainbridge Island 2008 Capital Facilities Plan Update 65 of 186 2008 2009 2010 2011 2012 2013 BEGINNING WORKING CAPITAL 331 136 475 615 824 1,105 REVENUES Charges for Service 1,905 2,229 2,403 2,590 2,792 3,010 L.I.D. Assessments - - - - - - Interest & Other Revenues 151 (109) 26 35 48 67 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL REVENUES 2,056 2,120 2,429 2,626 2,840 3,077 TAXPAYER SUPPORT - - - - - - OPERATING EXP. + DEBT SVC Finance - Billing & Acct'g + Rent 399 423 448 475 504 534 Finance - Debt Service 99 77 105 121 129 137 Public Works 1,107 1,173 1,244 1,318 1,397 1,481 ----------- ----------- ----------- ----------- ----------- ----------- OPERATING EXP. + DEBT SVC 1,605 1,673 1,797 1,914 2,030 2,152 CAPITAL EXPENDITURES Finance - - - - - - Public Works - Equipment 105 33 17 28 53 5 Public Works - Projects 542 3,075 475 475 475 475 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL CASH OUTLAYS 2,251 4,781 2,289 2,417 2,558 2,632 Voter Approved Bonds - - - - - - City Council Approved Bonds - - - - - - PWTF Debt Issued - 3,000 - - - - Revenue Bonds - - - - - - LID Bonds Issued - - - - - - Capital Leases - - - - - - NET TRANSFERS IN/(OUT)- - - - - - ----------- ----------- ----------- ----------- ----------- ----------- ENDING WORKING CAPITAL 136 475 615 824 1,105 1,550 MEMO : DEPRECIATION - - - - - - CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS STORM & SURFACE WATER MANAGEMENT UTILITY City of Bainbridge Island 2008 Capital Facilities Plan Update 66 of 186 2008 2009 2010 2011 2012 2013 GENERAL PROPERTY TAXES : Levy Rate 0.9815 0.9029 0.8311 0.7649 0.7041 0.7041 SPECIAL LEVY PROPERTY TAXES : Levy Rate 0.0862 0.0795 0.0731 0.0672 0.1106 0.1106 ----- ----- ----- ----- ----- ----- TOTAL CITY PROPERTY TAXES : 1.0676 0.9824 0.9042 0.8321 0.8147 0.8147 ANNUAL COST TO $500,000 HOME: General Property Taxes 490.73 451.47 415.56 382.45 352.06 352.06 Special Levy Property Taxes 48.46 46.48 44.44 42.55 72.76 75.67 ---- ---- ---- ---- ---- ---- TOTAL CITY PROPERTY TAXES : 539.19 497.95 460.00 424.99 424.82 427.73 ANNUAL COST TO $500,000 HOME ASSUMING 7.5% ANNUAL CHANGE IN ASSESSED VALUE : General Property Taxes 490.73 485.33 480.23 475.11 470.16 505.43 Special Levy Property Taxes 46.60 42.97 39.51 36.37 59.80 59.80 ---- ---- ---- ---- ---- ---- TOTAL CITY PROPERTY TAXES : 537.33 528.31 519.74 511.48 529.97 565.23 Assessed Value 562.4320 584.9293 608.3265 632.6595 657.9659 684.2845 Assessed Value (with 7.5% change in assessed value) 500.0000 537.5000 577.8125 621.1484 667.7346 717.8147 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% 4.00% ---- ---- ---- ---- ---- ---- 4.00%4.00%4.00%4.00%4.00%4.00% 272.56 283.47 294.80 306.60 318.86 331.61 391.45 407.11 423.40 440.33 457.94 476.26 38.33 39.09 39.88 40.67 41.49 42.32 ---- ---- ---- ---- ---- ---- $3,378.78 $3,406.83 $3,443.85 $3,489.53 $3,628.90 $3,810.64 CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS EFFECT OF FINANCING PLAN ON THE PUBLIC City of Bainbridge Island 2008 Capital Facilities Plan Update 67 of 186 2008 2009 2010 2011 2012 2013 2006 L.T.G.O Bonds - - - - - - 2007 L.T.G.O Bonds - - - - - - 2008 L.T.G.O Bonds 7,500 - - - - - 2009 L.T.G.O Bonds - 4,428 - - - - 2010 L.T.G.O Bonds - - 1,100 - - - 2011 L.T.G.O Bonds - - - - - - 2012 L.T.G.O Bonds - - - - - - ---- ---- ---- ---- ---- ---- TOTAL L.T.G.O. BONDS TO BE ISSUED :7,500 4,428 1,100 - - - CUMULATIVE TOTAL LTGO BONDS : 18,644 23,072 24,172 24,172 24,172 24,172 LESS : PRINCIPAL REPAYMENTS - - - - - - ---- ---- ---- ---- ---- ---- NEW LTGO BONDS OUTSTANDING 7,500 11,928 13,028 13,028 13,028 13,028 TRANSPORTATION/OTHER PROJECTS TOTAL L.T.G.O. BONDS TO BE ISSUED : 7,500 4,428 1,100 - - - G.O. BONDS - 7,000 - - - - CUM TOTAL NEW G.O. DEBT : 18,644 30,072 31,172 31,172 31,172 31,172 CUM PRINCIPAL REPAYM'TS TOTAL G.O. DEBT OUTSTANDING 18,644 30,072 31,172 31,172 31,172 31,172 Capital Leases - 250 3,000 - - - PWTF Loans for Water - 1,000 3,000 - - - PWTF Loans for Sewer 3,000 5,000 2,000 1,000 1,000 - PWTF Loans for SSWM - 3,000 - - - - PWTF Loans for Streets - - - - - - STREETS LID BONDS - - 1,500 - - - WATER LID BONDS - - - - - - SEWER LID BONDS - - - - - - ---- ---- ---- ---- ---- ---- LID BONDS OUTSTANDING - - 1,500 1,500 1,500 1,500 INTEREST RATE ON BONDS 5.50% 5.50% 5.50% 5.50% 5.50% 5.50% INTEREST RATE ON PWTF LOANS 0.50% 0.50% 0.50% 0.50% 0.50% 0.50% CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS SUMMARY OF PLANNED DEBT FINANCING City of Bainbridge Island 2008 Capital Facilities Plan Update 68 of 186 2008 2009 2010 2011 2012 2013 DEBT SERVICE COST OF NEW BONDS ISSUED G.O. Bonds - - 586 586 586 586 Open Space & Transportation (G.O. Bonds)441 1,069 1,439 1,531 1,531 1,531 Sewer Treatment Plant Upgrade - LTGO Bonds - - - - - - Loans & Leases (Includes Open Space Contracts)118 86 23 274 274 274 PWTF Loans for Water - - 53 53 53 53 PWTF Loans for Sewer - 158 421 527 579 632 PWTF Loans for SSWM - - 158 158 158 158 PWTF Loans for Streets - - - - - - L.I.D. Bonds for Streets - - - 126 126 126 L.I.D. Bonds for Water - - - - - - L.I.D. Bonds for Sewer - - - - - - ---- ---- ---- ---- ---- ---- ADDED DEBT SERVICE COST 559 1,313 2,680 3,254 3,306 3,359 NEW REVENUE BONDS : WATER REVENUE BONDS - 2,000 - - - - SEWER REVENUE BONDS 5,000 5,000 - - - - CUM TOTAL NEW REVENUE BONDS : WATER REVENUE BONDS - 2,000 2,000 2,000 2,000 2,000 SEWER REVENUE BONDS 5,000 10,000 10,000 10,000 10,000 10,000 DEBT SERVICE COST OF REVENUE BONDS ISSUED WATER REVENUE BONDS - - 167 167 167 167 SEWER REVENUE BONDS - 418 837 837 837 837 SUMMARY OF PLANNED DEBT FINANCING (CONTINUED…..) CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS City of Bainbridge Island 2008 Capital Facilities Plan Update 69 of 186 2008 2009 2010 2011 2012 2013 BEGINNING CASH BALANCES All Funds Except Utilities 2,919 2,777 3,911 4,780 4,603 8,022 Less: L.I.D. Balances - - - - - ----------- ----------- ----------- ----------- ----------- ----------- = Tax-Supported Fund Balances 2,919 2,777 3,911 4,780 4,603 8,022 GENERAL REVENUES Property Taxes - General Levy 6,250 6,460 6,660 6,851 7,034 7,210 Sales & Use Tax 3,585 3,908 4,259 4,643 5,061 5,516 Utility, B & O / Other Taxes 3,885 4,157 4,448 4,759 5,093 5,449 Real Estate Excise Tax 2,570 2,737 2,915 3,104 3,306 3,521 Licenses & Permit Fees 317 338 360 383 408 434 Intergovernment 384 453 473 494 516 542 Charges for Services 198 211 225 239 255 271 Fines & Forfeits 312 332 354 377 401 427 B&DS + ROW Charges 2,115 2,252 2,399 2,555 2,721 2,898 Grants Received - Operating 235 300 268 284 276 280 Interest, Misc & Other (incl FAR Purch's)1,335 1,674 2,252 2,883 3,568 4,470 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL GENERAL REVENUES 21,186 22,822 24,612 26,572 28,638 31,019 DEDICATED REVENUES Commercial Parking & Hotel/Motel Tax 675 668 715 737 773 804 Property Taxes - GO Bond Levies 560 544 1,122 1,123 1,252 1,252 MV Fuel Tax 580 596 632 669 709 756 Parking Revenues 445 463 481 501 521 541 L.I.D. Assessments 10 274 247 342 309 274 Interest, Misc & Other 615 374 548 593 592 679 FAR / ROW - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL DEDICATED REVENUES 2,885 2,919 3,745 3,964 4,156 4,306 Grants & Other Contributions - Capital (Developer and Public/Private Contributions/ FAR & ROW)4,092 6,822 3,000 3,000 2,000 2,000 TOTAL REVENUES 28,163 32,563 31,357 33,536 34,794 37,325 OTHER SOURCES Voter Approved Bonds - 7,000 - - - - City Council Approved Bonds 7,500 4,428 1,100 - - - PWTF Debt Issued - - - - - - Revenue Bonds - - - - - - LID Bonds Issued - - 1,500 - - - Land Proceeds 750 2,750 - - - - Capital Leases - 250 3,000 - - - NET TRANSFERS IN/(OUT)- - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL REVENUES AND OTHER SOURCES 39,332 49,769 40,868 38,316 39,397 45,347 SOURCES OF FUNDS -- TAX-SUPPORTED FUNDS ONLY CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS City of Bainbridge Island 2008 Capital Facilities Plan Update 70 of 186 2008 2009 2010 2011 2012 2013 GENERAL OPERATING EXPENDITURES Executive / Legislative 3,841 4,071 4,316 4,575 4,849 5,140 Intergovernment Expend's 702 744 788 836 886 939 Judicial 456 483 512 543 575 610 Finance - General Government 4,151 4,400 4,664 4,944 5,241 5,555 Police 2,800 2,968 3,146 3,335 3,535 3,747 Planning / Building 4,029 4,271 4,527 4,799 5,086 5,392 Public Works 2,767 2,933 3,109 3,295 3,493 3,703 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL GENERAL OPERATING EXPENDITURES 18,745 19,870 21,062 22,326 23,666 25,086 SPECIFIED OPERATING EXPENDITURES Street & Road Maintenance 1,350 1,431 1,517 1,608 1,704 1,806 Operating Capital Expend's - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL SPECIFIED OPERATING EXPENDITURES 1,350 1,431 1,517 1,608 1,704 1,806 TOTAL GENERAL OPERATING EXPENDITURES 20,095 21,301 22,579 23,934 25,370 26,892 DEBT SERVICE COST 2,901 3,546 4,393 4,684 4,735 4,629 CAPITAL EXPENDITURES (from CIP) Non-Motorized Transportation 1,941 1,243 - - - - Transportation Projects 5,684 11,520 800 800 800 800 Capital Equipment 339 732 653 655 461 644 Parks & Trails 2,612 1,810 372 40 10 10 Affordable Housing 1,600 2,350 - - - - Facilities/City Offices 1,383 3,356 7,292 3,600 - - ----------- ----------- ----------- ----------- ----------- ----------- CAPITAL EXPENDITURES 13,558 21,011 9,117 5,095 1,271 1,454 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL EXPENDITURES 36,555 45,857 36,088 33,712 31,375 32,975 TRANFERS TO OTHER FUNDS Taxpayer Support for SSWM Utility - - - - - - Net Transfers to Water & Sewer Utility - - - - - - Taxpayer Support for L.I.D.'s - - - - - - ENDING FUND BALANCES 2,777 3,911 4,780 4,603 8,022 12,372 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL USES OF FUNDS 39,332 49,769 40,868 38,316 39,397 45,347 CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS USES OF FUNDS -- TAX-SUPPORTED FUNDS ONLY City of Bainbridge Island 2008 Capital Facilities Plan Update 71 of 186 2008 2009 2010 2011 2012 2013 BEGINNING WORKING CAPITAL 5,038 4,973 4,895 6,011 6,163 6,593 REVENUES Charges for Service 6,837 7,758 8,363 9,016 9,719 10,477 Capital Contributions 790 774 793 829 866 905 L.I.D. Assessments 400 410 420 439 459 480 Interest & Other Revenues 412 158 300 321 346 379 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL REVENUES 8,439 9,100 9,877 10,605 11,390 12,240 TAXPAYER SUPPORT - - - - - - OPERATING EXP. + DEBT SVC Finance - Billing & Acct'g 1,640 1,726 1,817 1,912 2,012 2,118 Finance - Debt Service 881 1,583 2,443 2,645 2,742 2,837 Public Works 3,355 3,533 3,722 3,920 4,129 4,350 ----------- ----------- ----------- ----------- ----------- ----------- OPERATING EXP. + DEBT SVC 5,876 6,843 7,981 8,478 8,884 9,305 CAPITAL EXPENDITURES Finance - - - - - - Public Works-Equipment 235 165 85 140 265 25 Public Works-Projects 10,392 18,170 5,694 2,835 2,811 1,755 ----------- ----------- ----------- ----------- ----------- ----------- 10,627 18,335 5,779 2,975 3,076 1,780 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL CASH OUTLAYS 16,504 25,178 13,760 11,453 11,960 11,085 Voter Approved Bonds - - - - - - City Council Approved Bonds - - - - - - PWTF Debt Issued 3,000 9,000 5,000 1,000 1,000 - Revenue Bonds 5,000 7,000 - - - - LID Bonds Issued - - - - - - Land Proceeds - - - - - - Capital Leases - - - - - - NET TRANSFERS IN/(OUT)- - - - - - ----------- ----------- ----------- ----------- ----------- ----------- ENDING WORKING CAPITAL 4,973 4,895 6,011 6,163 6,593 7,749 MEMO : DEPRECIATION - - - - - - CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS CONSOLIDATED UTILITY FUND City of Bainbridge Island 2008 Capital Facilities Plan Update 72 of 186 2008 2009 2010 2011 2012 2013 BEGINNING BALANCES 7,958 7,751 8,807 10,791 10,767 14,616 OPERATING REVENUES Property Taxes 6,250 6,460 6,660 6,851 7,034 7,210 Other General Taxes 7,470 8,065 8,707 9,402 10,153 10,965 Intergovernmental Revenues 384 453 473 494 516 542 Total Utility Revenues 8,439 9,100 9,877 10,605 11,390 12,240 B&DS + ROW Charges 2,115 2,252 2,399 2,555 2,721 2,898 All Other General Revenues 6,207 6,615 7,613 8,594 9,577 10,900 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL OPERATING REVENUES 30,864 32,945 35,729 38,500 41,391 44,756 OPERATING COSTS General Government 9,149 9,698 10,280 10,897 11,551 12,244 Police & Planning 6,829 7,239 7,673 8,134 8,622 9,139 Public Works & Street Maintenance 4,117 4,364 4,625 4,903 5,197 5,509 Utility Costs 4,995 5,260 5,539 5,832 6,142 6,468 Operating Capital - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL OPERATING COSTS 25,090 26,560 28,117 29,766 31,512 33,360 OPERATING MARGIN 5,774 6,385 7,612 8,734 9,880 11,396 NON-OPERATING REVENUES Property Taxes - Bond Levies 560 544 1,122 1,123 1,252 1,252 Commercial Parking & Hotel/Motel Tax 675 668 715 737 773 804 LID Assessments 410 684 667 781 768 754 Capital Grants 4,092 6,822 3,000 3,000 2,000 2,000 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL NON-OPR REVENUES 5,737 8,718 5,504 5,640 4,793 4,810 DEBT SERVICE COST 3,782 5,129 6,835 7,329 7,477 7,467 AMOUNT AVAIL. FOR CAPITAL 15,686 17,725 15,087 17,837 17,963 23,355 CAPITAL SPENDING 24,186 39,346 14,896 8,070 4,347 3,234 AMOUNT NEEDED FOR CAPITAL 8,499 21,621 (191) (9,767) (13,616) (20,121) CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS FINANCIAL SUMMARY - ALL FUNDS City of Bainbridge Island 2008 Capital Facilities Plan Update 73 of 186 2008 2009 2010 2011 2012 2013 BEGINNING BALANCES 2,919 2,777 3,911 4,780 4,603 8,022 OPERATING REVENUES Property Taxes 6,250 6,460 6,660 6,851 7,034 7,210 Other General Taxes 7,470 8,065 8,707 9,402 10,153 10,965 Real Estate Excise & Dedicated Taxes 2,570 2,737 2,915 3,104 3,306 3,521 Intergovernmental Revenues 384 453 473 494 516 542 Total Utility Revenues - - - - - - B&DS + ROW Charges 2,115 2,252 2,399 2,555 2,721 2,898 All Other General Revenues 4,712 4,956 5,834 6,665 7,503 8,663 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL OPR REVENUES 23,501 24,923 26,988 29,071 31,233 33,799 OPERATING COSTS General Government 9,149 9,698 10,280 10,897 11,551 12,244 Police & Planning 6,829 7,239 7,673 8,134 8,622 9,139 Public Works & Street Maintenance 4,117 4,364 4,625 4,903 5,197 5,509 Utility Costs - - - - - - Operating Capital - - - - - - ----------- ----------- ----------- ----------- ----------- ----------- TOTAL OPR COSTS 20,095 21,301 22,579 23,934 25,370 26,892 OPERATING MARGIN 3,405 3,623 4,409 5,138 5,864 6,907 NON-OPERATING REVENUES Property Taxes - Bond Levies 560 544 1,122 1,123 1,252 1,252 LID Assessments 10 274 247 342 309 274 Capital Grants 4,092 6,822 3,000 3,000 2,000 2,000 ----------- ----------- ----------- ----------- ----------- ----------- TOTAL NON-OPR REVENUES 4,662 7,640 4,369 4,464 3,561 3,526 DEBT SERVICE COST 2,901 3,546 4,393 4,684 4,735 4,629 AMOUNT AVAIL. FOR CAPITAL 8,086 10,494 8,297 9,698 9,293 13,826 CAPITAL SPENDING 13,793 21,176 9,202 5,235 1,536 1,479 AMOUNT NEEDED FOR CAPITAL 5,708 10,682 905 (4,463) (7,757) (12,347) FINANCIAL SUMMARY -- TAX SUPPORTED FUNDS ONLY CITY OF BAINBRIDGE ISLAND -- YEAR 2008 FINANCIAL CAPACITY ANALYSIS City of Bainbridge Island 2008 Capital Facilities Plan Update 74 of 186 Appendix A City of Bainbridge Island List of projects not included in 2008-2013 Capital Improvement Project List The projects shown in this appendix were originally included in the City’s preliminary CIP list published on 6/28/07. These projects have not been included in the 2008-2013 CIP because they were shifted to years beyond the current 6- year planning horizon or removed from further consideration for a variety of reasons. City of Bainbridge Island 2008 Capital Facilities Plan Update 75 of 186 2008 Capital Improvement Project (CIP) List - 2nd Reading 12/12/07 Projects With Planned Spending Only in 2014 and Beyond M E/M E E/N N U Major maintenance, repair, renovation, or replacement of an existing facility that does not add additional capacity Combination of E and M New facilities or improvements to existing facilities that provide added capacity to serve the existing population Combination of E and N New facilities or improvements to existing facilities that are built primarily to provide added capacity to serve future population or employment growth Unclassified Comprehensive Plan Categories GC SC F I U Generally Consistent with Comp Plan Specifically Consistent with Comp Plan Flagged; May not be consistent with Comp Plan Inconsistent with Comp Plan Unclassified Comprehensive Plan Consistency Codes LOS Level of Service $ amounts are rounded to the nearest $1,000 City of Bainbridge Island 2008 Capital Facilities Plan Update 76 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Affordable Housing Affordable Housing - All 632 COBI Shepard/Weaver Property - Affordable Housing 502 In March 2006, the Housing Trust Fund awarded HRB a grant of $6,450 to undertake a feasibility study and preliminary site planning for a possible multi-family affordable housing project on the COBI-owned Weaver/Shepard property. The 0.68 acre parcel on the NE corner of Weaver and Shepard Way is zoned R-3.5. It is an undeveloped parcel, with a portion of the site occupied by a City pumping facility that supplies non-potable water for construction dust control and other uses. The study found that: 1. Under present zoning and existing land use development standards, the parcel can be sub-divided to accommodate, with the 50% affordable housing bonus, a total of six units of housing (three duplexes). 2. These six units of affordable housing could be either rental, limited-equity home ownership or a combination of both. 3. While there are no environmental constraints that would significantly hamper a housing project on the site, there are a number of other site-related constraints and additional costs that make the property expensive to develop for affordable housing. 4. Preliminary development cost estimates indicate that with COBI and other funding support, families with household incomes of between 80% and 110% of Kitsap AMI would be able to afford the units. If the City supports making the property available for affordable housing, HRB will seek a variety of outside construction grants and loans to write down the initial front-end costs and to subsidize annual payments. COBI support is requested to help offset two extraordinary costs of developing the property (total of $302,000): 1. The cost of transferring the property from the Utility Fund to the General Fund. A 2003 appraisal of the property conducted by Anthony Gibbons indicated a property value of approximately $225,000; and 2. The cost of decommissioning the existing well and relocating the well. A 2006 estimate by Browne Engineering puts this cost at approximately $76,000. The existing well has been perfected to municipal use at 160 acre feet annually with an estimated water right value of $220,000. The capacity of the well is currently included in the City’s water system plan. It is the City’s desire to transfer the water right to another parcel without limitation to avoid a loss in water system capacity. Failure to do so will necessitate purchasing new water rights that may be perfected to municipal use at a cost of more than $220,000. The City is currently investigating whether the water right may be transferred to another parcel without limitation. N No Level of Service Established GC The Bainbridge Island Comprehensive Plan contains policies supporting the use of public lands and fudns for affordable housing. If City bonding is used, housing must be available for less than 80% of median income in Kitsap County. Multi-family units are a conditional use in the R-3.5 zone. Total for Affordable Housing - All 502 City of Bainbridge Island 2008 Capital Facilities Plan Update 77 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Total for Affordable Housing 502 City of Bainbridge Island 2008 Capital Facilities Plan Update 78 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Facilities Community 703 Community Cultural Center 2,000 As described in the Final Report of the Cultural Facilities Feasibility Study, February 2006, the Community Cultural Center would comprise two linked structures (13,000 sq. ft. and 18,000 sq. ft.) above COBI-proposed underground parking garage. Intended uses included: multi-purpose events space with commercial kitchen, winter Farmer's Market, office and meeting spaces, arts education classrooms, multi-age gathering spaces, exhibition spaces, arts/community cafe. (Define the project funding requirements) E/M No Level of Service Established GC The Bainbridge Island Comprehensive Plan contains policies related to the identification an improving utilization of existing facilities and conducting a feasability study for long-term needs. There is no specific call for a new facility in the Comprehensive Plan, but it appears that there was intent to support long-term facilities needs. The Bainbridge Island Arts and Humanities Council maintains an inventory of exisiing cultural facilities, completed a Cultur Facilities Needs Assessment in 2003, and completed a Cultural Facilities Feasibility Study in 2006. The proposed project appears to be consistent with the feasibility study. Total for Community 2,000 City Government 695 City Hall HVAC Software Upgrade 50 Upgrade City Hall HVAC software M No LOS established besides repair and maintenance of existing facilities. GC General operational improvement project. 694 Decant Fuel Storage 100 Install Fuel Storage and dispensing system at the decant facility to support the south end of the Island. E Completion of planned facilities to support LOS. GC General operational improvement project. City of Bainbridge Island 2008 Capital Facilities Plan Update 79 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Facilities City Government 692 Public Works Fuel Storage Upgrade 120 Upgrade the City's fuel storage capacity at the Public Works Yard. E Improvements to existing facilties to support LOS. GC General operational improvement project. Total for City Government 270 Total for Facilities 2,270 City of Bainbridge Island 2008 Capital Facilities Plan Update 80 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Parks & Open Space Open Space & Habitat 636 Blossom/Point White Drive/Pleasant Beach 75 Blossom/Point White Drive/Pleasant Beach - addition of public parking and public restrooms E/N No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage trail systems, the preservation of open space, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space. Consistency is dependent upon compliance with applicable shoreline and critical area policies and regulations. 635 Lost Valley Property 8 Lost Valley Property - Construct trails through the property as well as bridge and boardwalk over wetland areas E/N No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage trail systems, the preservation of open space, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space. Consistency is dependent upon compliance with applicable shoreline and critical area policies and regulations. 252 Open Space - Farm Trails & Parking (OS lead)26 Perform a planning effort for trail and parking improvements through a cooperative effort to bring consensus with the farmers, property owners, neighbors, Non-Motorized Advisory Committee and community on access to and through the farmland. Construct priority trails or parking as funds allow. E No LOS established besides completion of planned facilities. GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage trail systems, the preservation of open space, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space. City of Bainbridge Island 2008 Capital Facilities Plan Update 81 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Parks & Open Space Open Space & Habitat 698 Open Space - Meigs Trail 20 Meigs - Trail Creation/Construction and creation of parking area E No LOS established besides completion of planned facilities. GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage trail systems, the preservation of open space, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space. Consistency is dependent upon compliance with applicable shoreline and critical area policies and regulations. 731 Schel-Chelb Estuary Expansion (E-2)50 Expand the existing Schel-Chelb Estuary by creating interconnected tidal and fringing wetlands on 3-5 acres of adjacent land. Project is in partnership with willing landowner. M No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage habitat restoration, the preservation of open space, trail systems, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space and environmental restoration. 284 Waterfront Trail Extension 455 Extend the waterfront trail west across "draw" from end of storm drainage outfall property. E No LOS established besides completion of planned facilities. GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Winslow Master Plan (pgs 33-36), Environmental Element (GW 1, 2,3,4) and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage trail systems, the preservation of open space, and the development of park and recreation facilities, including these two trail systems. The Bainbridge Isalnd Park District Comprehensive Plan, an adopted part of the City's Comprehenisve Plan, also encourages the preservation and improvement of trails and open space. Without a general scope-or-work, consistency is dependent upon compliance with City policies and regulations. City of Bainbridge Island 2008 Capital Facilities Plan Update 82 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Parks & Open Space Open Space & Habitat 634 Yama Property Trail 15 Yama Property - Provide Public access via the construction of trails and also provide educational signage E/N No Level of Service Established GC The City of Bainbridge Island Comprehensive Plan contains goals and policies in the Shoreline Management Master Program, Environmental Element (GW 1, 2,3,4), and the Transportation Element (TR 9), including the Non-Motorized Transportation Plan, that encourage trail systems, the preservation of open space, and the development of park and recreational facilities. The Bainbridge Island Park District Comprehensive Plan also encourages the preservation and improvement of open space. Consistency is dependent upon compliance with applicable shoreline and critical area policies and regulations. Total for Open Space & Habitat 649 Parks & Road-ends 653 Open Water Marina 100 The city’s anchoring and mooring plan for Eagle Harbor delineates an open water marina within the middle harbor zone for transient, short-term, and long-term use with room for an estimated 50 vessels. This project is to purchase and install the necessary mooring buoys and anchors for that marina. The anchoring and mooring area is expected to accommodate up to 50 vessels. New private moorings will not be permitted on public aquatic lands within Eagle Harbor. All long-term and live-aboard vessels anchoring and mooring on public bedlands within the middle harbor will occur within the designated open water marina. Transient and short-term anchoring is not restricted to the open water marina, although the city will provide mooring to encourage use of the area by transient and short-term vessels when space is available. E/N No Level of Service Established F Consistency is dependent upon amendment of the Shoreline Management Master Program Total for Parks & Road-ends 100 Total for Parks & Open Space 749 City of Bainbridge Island 2008 Capital Facilities Plan Update 83 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Transportation Roads & Parking 113 Rockaway Beach Road Stabilization 2,000 Stabilize or realign road away from shoreline and improve non-motorized transportation facilities. Scope of project will be further defined following the completion of the current Shoreline Road Stabilization Study. E/M Repair of existing facilities. F Without a general scope of work and being located along several environmentally sensitive areas, this project cannot be adequately analyzed at this time and should be reviewed when further defined. Total for Roads & Parking 2,000 Total for Transportation 2,000 City of Bainbridge Island 2008 Capital Facilities Plan Update 84 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Capital Equipment Capital Equipment - Tax Supported 747 Capital Equipment Replacement Program - 2008 285 Capital Equipment-Annual Vehicle Replacement 1. Vehicle 4210 (replacement) 1998 Chevy Flatbed Hooklift system $75,000, Roads Division 2. Vehicle 8201 (replacement) 1995 Chevy Pickup $25,000, Planning Department 3. Vehicle 8206 (replacement) 1994 Chevy Pickup $25,000, Planning Department 4. Hooklift Attachments[flatbed, container box, crane] (new equipment) $75,000, Roads Division 5. Scissors Lift (new equipment) $25,000, Facilities Division 6. Utility Trailer (new equipment) $15,000, Facilities Division 7. Capital Equipment-Annual Expenditures (Undesignated) $20,000 8. Capital Equipment-O&M Fleet and Facilities (Earmark funds for breakage, obsolescence or new mission requirements) $25,000 M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. 735 Replace Portable Generator #4 55 Replace portable generator #4 out of the City equipment fleet that has exceeded its life expectancy with a 150 KW portable generator. M Replace existing equipment to support LOS. GC The City of Bainbridge Island Comprehensive Plan does not specifically address capital equipment. This equipment supports operations and maintenance activities necessary to maintain and improve capital facilities. Total for Capital Equipment - Tax Supported 340 Total for Capital Equipment 340 City of Bainbridge Island 2008 Capital Facilities Plan Update 85 of 186 Project Title Comp Plan Category and LOS Analysis Comp Plan Consistency Code and Analysis Project Description 2014 Thru 2018 Plan Project ID Total All Projects 5,861 City of Bainbridge Island 2008 Capital Facilities Plan Update 86 of 186 2008 Capital Improvement Project (CIP) List - 2nd Reading 12/12/07 Projects Excluded in the 2008 Capital Facilities Planning Process M E/M E E/N N U Major maintenance, repair, renovation, or replacement of an existing facility that does not add additional capacity Combination of E and M New facilities or improvements to existing facilities that provide added capacity to serve the existing population Combination of E and N New facilities or improvements to existing facilities that are built primarily to provide added capacity to serve future population or employment growth Unclassified Comprehensive Plan Categories GC SC F I U Generally Consistent with Comp Plan Specifically Consistent with Comp Plan Flagged; May not be consistent with Comp Plan Inconsistent with Comp Plan Unclassified Comprehensive Plan Consistency Codes LOS Level of Service $ amounts are rounded to the nearest $1,000 City of Bainbridge Island 2008 Capital Facilities Plan Update 87 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Facilities City Government 344 Land Acquisition - Harbor Street This scope of work is a duplicate of Project 43 - Harbor Street Road Addition. Acquire land for Harbor Street $1,250,000 (Land acquistion for WWTP $1,000,000 moved to new Project ID 741-Land Acquisition - WWTP) U REMOVE - DELETED FROM CIP U Need more information. 668 Police Building Painting Planned completion of Police and Court project will occur prior to or simultaneous to this maintenance. Paint exterior section of Police Building M No LOS established besides repair and maintenance of existing facilities. GC Maintenance 667 Police Building Roof Repair Planned completion of Police and Court project will occur prior to or simultaneous to this maintenance. Re-roof the Police Department building. M No LOS established besides repair and maintenance of existing facilities. GC Maintenance Community City of Bainbridge Island 2008 Capital Facilities Plan Update 88 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Facilities Community 379 Community Facilities - Undefined Specific community projects need to be defined. Holding fund for undefined community facilities (Define the facility) U REMOVED? I Without specific projects defined, consistency cannot be determined. A programmatic project for these types of facilities are not appropriate in CIP. 699 Community Recreation Center Project should be included in the Metro Park and Recreation District capital project plans. An indoor facility for gymnastics, kitchen, indoor basketball and multi-use and cultural events. U U Duplicate to project in Park District CFP. 267 Post Office site Land Acquisition Project is no longer considered a viable project. Purchase Post Office site $2,000,000 U REMOVE - DELETED FROM CIP U Need more information. City of Bainbridge Island 2008 Capital Facilities Plan Update 89 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Parks & Open Space Parks & Road-ends 278 Ericksen Park - Excluding Storm Modifications Duplicate scope of work planned in Project 24-Ericksen-Hildebrand Connection (Wallace to High School Rd.) M Repair of existing facilities GC The Winslow Master Plan, an adopted sub-area plan to the City of Bainbridge Island Comprehensive Plan, calls for a number of new parks of various types downtown. This project is consistent provided that park improvements are done as envisioned in the Winslow Master Plan. Additionally, since this project is the result of an intersection realignment , it will enhance the pedestrian environmenment. 277 Ericksen Park - Storm Modifications Duplicate scope of work planned in Project 24-Ericksen-Hildebrand Connection (Wallace to High School Rd.) Modify existing drainage pond and outlet to meet current requirements. E Repair of existing facilities GC The Winslow Master Plan, an adopted sub-area plan to the City of Bainbridge Island Comprehensive Plan, calls for a number of new parks of various types downtown. This project is consistent provided that park improvements are done as envisioned in the Winslow Master Plan. Additionally, since this project is the result of an intersection realignment and will include stormwater improvements, it will enhance the pedestrian environmenment and further protect the ravine. 257 WF Park Boardwalk and Dinghy Dock - ALEA Grant Duplicate of Project # 153 - WF Park Shoreline Improvements (ALEA grant) Construct additional dinghy moorage at waterfront park with funds from ALEA grant. Build boardwalk along Waterfront Park shoreline per Waterfront Park Master Plan.. E No LOS established besides completion of planned facilities. GC The Winslow Master Plan contains policies calling for improvements to parks and open space, inlcuding the development of a master plan for Waterfront Park improvements. The current Waterfront Park master plan calls for dock expansion. City of Bainbridge Island 2008 Capital Facilities Plan Update 90 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Parks & Open Space Parks & Road-ends 263 WF Park Boathouse/Community Pavilion Scope of work is not included in the Parks master plan. Build a boathouse for storage of rowing shells and community pavilion where existing tennis courts are located per Waterfront Park Master Plan. E REMOVE - DELETED FROM CIP F The Winslow Master Plan contains policies calling for improvements to parks and open space, inlcuding the development of a master plan for Waterfront Park improvements. Consistency is dependent upon the final adopted Waterfront Park master plan. 256 WF Park Pathway and Stair Restoration (by Ravine) - ALEA Grant Duplicate of Project # 153 - WF Park Shoreline Improvements (ALEA grant) Rebuild stairs and construct new ADA pathway on eastern edge of waterfront park connecting the waterfront trail (bridge) with Bjune Drive per Waterfront Park Master Plan. E No LOS established besides completion of planned facilities. F The Winslow Master Plan contains policies calling for improvements to parks and open space, inlcuding the development of a master plan for Waterfront Park improvements. Consistency is dependent upon the final adopted Waterfront Park master plan. 255 WF Park Portal Park ADA Access & Terraces - ALEA Grant Duplicate of Project # 153 - WF Park Shoreline Improvements (ALEA grant) Improve access into Waterfront Park from Brien Drive & the Ravine per Waterfront Park Master Plan. E No LOS established besides completion of planned facilities. F The Winslow Master Plan contains policies calling for improvements to parks and open space, inlcuding the development of a master plan for Waterfront Park improvements. Consistency is dependent upon the final adopted Waterfront Park master plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 91 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Parks & Open Space Parks & Road-ends 152 WF Park Promenade Old project no longer being considered. Sidewalk, tree planting and furnishings along Bjune- Cost from Attaway MP. (Old LALA project - need to define project) E REMOVE - DELETED FROM CIP F The Winslow Master Plan contains policies calling for improvements to parks and open space, inlcuding the development of a master plan for Waterfront Park improvements. Consistency is dependent upon the final adopted Waterfront Park master plan. 270 WF Park Ravine Expansion (ALEA grant) Duplicate of Project # 153 - WF Park Shoreline Improvements (ALEA grant) Build trials and improve views creating a ravine greenway per Waterfront Park Master Plan. Remove the bulkhead, restore the shoreline and beach with the addition of sand and gravel to create a habitat for forage fish. Relocate the trail, planting, overlook, and boardwalk. (ALEA grant) E/M No Level of Service Established F The Winslow Master Plan contains policies calling for improvements to parks and open space, inlcuding the development of a master plan for Waterfront Park improvements. Consistency is dependent upon the final adopted Waterfront Park master plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 92 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Sanitary Sewer Collection & Transmission 738 Sewer Improvement/Upgrade Projects Duplicate scope of work planned in Project 12-Sanitary Sewer Collection System Upgrades The 2008 Sewer System Master Plan will provide projected improvements to maintain a functional system. U Study of existing system intended for existing and future populations to maintain LOS; project needed to comply with DOH. U Need more information. City of Bainbridge Island 2008 Capital Facilities Plan Update 93 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Stormwater Drainage & Treatment 23 Eagle Harbor Drive Culvert Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program Replace failing culvert under Eagle Harbor Drive at [ASK MELVA LOCATION ON E.H. DRIVE] M Repair of existing facilities U Need more information. 25 Fairview/Madrona Area Drainage Improvement Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program Improve drainage in the Fairview/Madrona area of Wing Point with new outfall to Puget Sound. U Repair of existing facilities U Need comment 41 Halls Hill Area Drainage Improvements (3-T's) Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program Replace deteriorated culverts and outfall. U REMOVE - CITY WORK COMPLETED U Need comment 65 Lynwood Center/Pt. White CB to Outfall Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program E/M Repair of existing facilities U Need more information. City of Bainbridge Island 2008 Capital Facilities Plan Update 94 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Stormwater Drainage & Treatment 70 Manzanita Area Drainage Improvements Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program E/M Repair of existing facilities U Need more information. 71 McRedmond/Wardwell Area Drainage Improvements Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program E/M Repair of existing facilities U Need more information. 74 Mountain View Drive Drainage Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program U Need comment U Need more information. 85 Park Avenue Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program U Need comment U Need more information. City of Bainbridge Island 2008 Capital Facilities Plan Update 95 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Stormwater Drainage & Treatment 112 Rockaway Beach Culvert Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program M Repair of existing facilities U Need more information. 115 Rose Loop Ravine Crossing Culvert Replacement Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program Replace culvert with larger culvert or small bridge. E/M Repair of existing facilities U Need more information. 133 Taylor and Pine Culvert Replacement Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program Replace two culverts. E/M Repair or replace existing facilities U Need more information. 142 Venice Loop Area - Conveyance Improvements Scope of work is included in Project 20 - Drainage/Culvert Annual Upgrade Program U Need comment U Need more information. Habitat City of Bainbridge Island 2008 Capital Facilities Plan Update 96 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Stormwater Habitat 47 Culvert Upgrade - Hidden Cove at Coho Creek Project scope of work is a duplicate. Replace and upgrade culverts for fish passage. E Repair or replace existing facilities GC The Environmental Element of the City of Bainbridge Island Comprehensive Plan calls for the restoration of degraded stream habitat (AQ 1.12), which would include correcting fish passage barriers. The projects in this programmatic effort are consistent with the City of Bainbridge Island Comprehensive Plan. 26 Fish Passage Improvements Project scope of work is a duplicate. Programmatic effort to upgrade island streams to better support fish passage. Typical projects include lowering and over-sizing culverts, stream habitat restoration, and removal of man-made obstacles. E Replace or repair existing facilities GC The Environmental Element of the City of Bainbridge Island Comprehensive Plan calls for the restoration of degraded stream habitat (AQ 1.12), which would include correcting fish passage barriers. The projects in this programmatic effort are consistent with the City of Bainbridge Island Comprehensive Plan. 73 Miller Road at Manzanita Creek Project scope of work is a duplicate. E Repair of existing facilities GC The Environmental Element of the City of Bainbridge Island Comprehensive Plan calls for the restoration of degraded stream habitat (AQ 1.12), which would include correcting fish passage barriers. The projects in this programmatic effort are consistent with the City of Bainbridge Island Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 97 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Stormwater Habitat 123 Springbrook Creek Culvert Upgrade (FletcherBay/HS) Project scope of work is a duplicate. Replace and upgrade culverts for fish passage. E Repair or replace existing facilities GC The Environmental Element of the City of Bainbridge Island Comprehensive Plan calls for the restoration of degraded stream habitat (AQ 1.12), which would include correcting fish passage barriers. The projects in this programmatic effort are consistent with the City of Bainbridge Island Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 98 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Transportation Non-motorized 175 Wyatt Way NM Improvements Phase 2 (Finch to Grow sidewalk infill) Scope of work is included in Project 173 - Wyatt Way NM & Road Imp. (Grow to Madison) Sidewalk Completion between Grow Ave. & Finch Ave.: NORTH SIDE, between Grow & Weaver, adjacent to Hillandale; SOUTH SIDE, between Grow & Weaver, to replace existing crushed rock section west of Grow; SOUTH SIDE, between Finch and a point approximately 150 feet east of Eakin, to replace existing crushed rock section east of Eakin and to complete concrete section between Eakin & Finch, as shown in NMTP. E No LOS established besides completion of planned facilities. SC Proposed facilites are called for in the Non-Motorized Transportation Plan. Roads & Parking 18 Downtown Business Employee Temporary Parking Program Winslow Tommorrow street & parking garage scope of work will include this work. Identify opportunities/options for replacing the temporary loss of employee parking when existing employee parking is lost during construction of the parking structure (see project II below) and, if necessary, construct a new temporary parking area. Cancelled - Street & parking garage carry their elements. E/N REMOVE - DELETED FROM CIP GC The Winslow Master Plan, as updated in 2006, calls for relocating or developing employee parking off Winslow Way. 140 Urban Corridors Preservation PE/RW Duplicate of the scope of work planned in Project 139 - Urban Corridors Preservation (Path, walkway, trains in Winslow) Identify and acquire corridors for future motorized and non-motorized transportation facilities, utilities, and greenways. (Duplicate of Project 139) E/N REMOVE - DELETED FROM CIP GC The Winslow Master Plan, as updated in 2006, calls for acquisition of corridores for motorized and non-motorized transportation. City of Bainbridge Island 2008 Capital Facilities Plan Update 99 of 186 Project Title Comprehensive Plan Category and Level of Service (LOS) AnalysisComprehensive Plan Consistency Code and Analysis Project Description Project Exclusion CommentID Transportation Roads & Parking 167 Winslow/Ericksen Intersection Improvements + Bjune Drive Scope of work is no longer being considered in the recommended streescape plan. Final engineering & contract documents, ROW acquisition and construction of Winslow Way/Ericksen/Bjune Dr. intersection, and Bjune Dr. from Winslow Way to Waterfront Park. Widen sidewalks, replace paving, underground overhead utilities, upgrade storm drain, sewer and water supply. Final engineering estimate includes permitting. (Out of project scope) E/N REMOVE - DELETED FROM CIP GC Consistent with Non-Motorized Transportation Plan, Transportation Element, Utilities Element, and Winslow Master Plan of the City of Bainbridge Island Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 100 of 186 Appendix B Bainbridge Island School District Adopted Capital Facilities Plan 2007-2013 The School District adopted the following CFP on June 21, 2007. The projects included in this CFP are consistent with the City’s Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 101 of 186 An Equal Educational and Employment Opportunity School District BOARD OF DIRECTORS Bruce Weiland Cheryl Dale Dave Pollock Mary Curtis Michael Foley SUPERINTENDENT Dr. Ken E. Crawford ASSOCIATE SUPERINTENDENT Faith Chapel 8489 Madison Avenue NE * Bainbridge Island, Washington 98110-2999 * (206) 842-4714 * Fax: (206) 842-2928 August 15, 2007 To Whom It May Concern: Attached is the Bainbridge Island School District Capital Facilities Plan 2007, an annual revision of the original document submitted to the City of Bainbridge Island in December of 2006. The following is a guide that summarizes the updates made in this current document version. Page Content 49 Table 4 revised to illustrate an incorporated third demographic study that has been added and used to update student enrollment and projections until the year 2010-11. 54 Figure 1 revised to illustrate an incorporated third demographic study that has been added and used to update student enrollment and projections until the year 2010-11 58 Figure 5 revised to illustrate an incorporated third demographic study that has been added and used to update student enrollment and projections until the year 2010-11 59 Figure 6 revised to illustrate an incorporated third demographic study that has been added and used to update student enrollment and projections until the year 2010-11 Please feel free to contact the BISD Capital Facilities Department at 780-1590 with any questions. City of Bainbridge Island 2008 Capital Facilities Plan Update 102 of 186 Six-Year Capital Facilities Plan 2007 - 2013 Wilkes Elementary Mandus Olson Property Sakai Intermediate School Woodward Middle School Blakely Elementary District Transportation Center Ordway Elementary School District Administration Office Commodore Options School Bainbridge High School District Maintenance Facility Sands Avenue Property Presented to the City of Bainbridge Island August 2007 City of Bainbridge Island 2008 Capital Facilities Plan Update 103 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 ________________________________________________________________________ Chapters Page # 1. Executive Summary 1 Glossary of Terms 3 2. Educational Objectives 4 3. Inventory of Existing Facilities 16 4. Enrollment 22 5. Current Level of Service 26 6. Capital Projects Finance Plan and Timeline 30 7. Impact Fee Analysis 32 Tables Table 1 BISD School Capacity and Utilization Formulas 35 Table 2 BISD Space Allocation Model (SAM) and Practical Capacity Model (PCM) Inventory 47 Table 3 BISD Capacity District Total 48 Table 4 BISD FTE October Enrollment History and Projections/ Kindergarten Enrollment Comparison to Live Births 49 Table 5 BISD FTE Growth and Loss Calculations 50 Table 6 Bainbridge Island Estimated Population Totals 51 Table 7 Bainbridge Island Estimated Six-Year Finance Plan 52 Table 8 Capital Facilities Plan - Bond 2006 53 Figures Figure 1 BISD Enrollment and Projections 54 Figure 2 Bainbridge Island Building Permits 1990-2004 55 Figure 3 Bainbridge Island Estimated Population Totals 56 Figure 4 Master Plan Proposed District Modernization Schedule 57 Figure 5 1993-2011Cohort Growth Projections 58 Figure 6 Cohort Enrollment Growth 1993-2011 59 Supporting The BISD Facilities Master Plan is available at the website: Document: www.bainbridge.wednet.edu or in hard copy at the District office Table of Contents City of Bainbridge Island 2008 Capital Facilities Plan Update 104 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 1 This Six-Year Capital Facilities Plan (CFP) has been prepared by the Bainbridge Island School District (District). The purpose of the CFP is to provide the City of Bainbridge Island a six-year facility planning document in compliance with the requirements of the Washington State Growth Management Act1. This document in and of itself is not intended to describe all of the District’s planning needs. In addition to this plan, the Bainbridge Island School District prepared a Facilities Master Plan2 in 2005. The Facilities Master Plan was developed to analyze the physical condition and program configuration of all existing District facilities in relationship to their ability to support the District’s mission and educational goals. The Facilities Master Plan incorporates current educational and demographic trend data into comprehensive goals for the District facilities. Ultimately, the Facilities Master Plan provides detailed information and the comprehensive support necessary to develop this current CFP. The CFP has six major components: ¾ Educational Objectives: District Basic Standard ¾ Inventory of Existing and Planned Facilities ¾ Enrollment ¾ Current Level of Service ¾ Capital Projects Finance Plan and Timeline ¾ Impact Fee Analysis The 2007-2013 CFP continues to address the first six years outlined within the Master Plan framework. It will guide District’s repair and modernization projects for existing facilities, and it will support the District’s decision to provide new capital facilities in the future. 1 RCW Chapter 36.70A 2 The Facilities Master Plan is available at the website: www.bainbridge.wednet.edu or in hard copy at the BISD District Office. 1 Executive Summary City of Bainbridge Island 2008 Capital Facilities Plan Update 105 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 2 In addition, the District understands adoption of the CFP and its ultimate adoption into the City’s Comprehensive Plan will allow impact fees to be collected by the City to be disbursed to the District. The CFP and the Facilities Master Plan are reviewed on an annual basis and revised accordingly, based on updated enrollment data, future financial information, and evolving educational needs of students. City of Bainbridge Island 2008 Capital Facilities Plan Update 106 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 3 Glossary of Terms BIEA- Bainbridge Island Education Association Cohort Survival- The net percentage of a cohort of students enrolled in the first grade in a given school-year who remain in the Bainbridge Island School District until grade twelve. CFP-Capital Facilities Plan District-The Bainbridge Island School District Facilities Master Plan- Document published in 2005 that is a 15-year framework and facility decision-making tool. (FTE) Full-time Equivalent – State funding is determined by the number of students attending 6 hours per day. OSPI- Office of the Superintendent of Public Instruction Plan- The 2007-2013 Bainbridge Island School District Capital Facilities Plan (PCM) Practical Capacity Model- A method for measuring capacity that involves identifying program spaces at a site, determining which spaces are core and elective instructional spaces, then multiplying those spaces by class size and utilization formulas. (SAM) Space Allocation Model- A method for measuring capacity by dividing the square footage of a site by the square foot per student space allocation. City of Bainbridge Island 2008 Capital Facilities Plan Update 107 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 4 Educational Vision Vision 2010 is a long-range planning document for the future of the school district. Under the banner of “strong minds, strong hearts, strong community,” it details the shared vision, mission, core beliefs, and goals for the District’s instructional program, climate, finance, and facilities. As learning and assessment methodologies continue to change, school districts face a host of choices and challenges when it comes to making decisions on how to best serve students. Educators across the nation are re-examining academic traditions and exploring a variety of approaches to the way pupils are grouped, administered, and taught. Growing use of alternative student assessment methods, team teaching, interdisciplinary instruction, and multi-age classes represents a departure from the traditional instructional practices of the past and consequently requires more flexible facilities. In addition, a national growth of the Small Schools concept underscores the value of relationship-based learning and community clusters that promote a positive learning environment. This CFP is grounded in Vision 2010 and is guided by an understanding of national education research on best practices and highly effective learning environments. Basic Standard The following definitions outline the basic standard program assumptions for each school as described in the District’s Facilities Master Plan. The core classroom spaces in the basic standard program accommodate flexible and integrated learning opportunities, and are supported by Vision 2010. 2 Educational Objectives City of Bainbridge Island 2008 Capital Facilities Plan Update 108 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 5 ELEMENTARY SCHOOL BASIC STANDARD PROGRAM SPACES Core Instruction • General classrooms • Small group study • Teacher work area/planning • Student toilets • Shared teaching/learning space Special Education • Developmental Preschool/Kindergarten • Occupational/Physical Therapy • Resource Room Functional Skills • Functional Skills classroom • Office • Kitchenette • Toilet Art/Science/Music/Tech • Art/Science classroom and storage • Music classroom and storage • Computer classroom Library/Media Center • Reading room/collection storage • Class seating/ story area • Circulation desk • Workroom/AV production Physical Education • Gymnasium • PE office/ storage • Community storage • Emergency supplies Food Service • Kitchen with office area • Food storage City of Bainbridge Island 2008 Capital Facilities Plan Update 109 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 6 ELEMENTARY SCHOOL BASIC STANDARD PROGRAM SPACES (continued) Commons/Cafeteria • Seating area for 225 students • Collapsible stage storage • Community storage • Table/chair storage Administration • Reception/waiting/office manager • Principal’s office • Conference room • Staff workroom • Storage Student Services • Counselor • Speech/Language Pathologist • Title 1 Reading • Itinerant office • Health room/ office Faculty/Staff Support • Staff room Building Support • Student toilets • Staff toilets • Custodial spaces/receiving/building storage • Exterior covered play area ELEMENTARY SCHOOL BASIC STANDARD PROGRAM ASSUMPTIONS General • Maximum enrollment is 450 students, grades Pre-K through 4 • Central food preparation is off-site • Gymnasium will be sized to support community athletic use • Program will include three (3) kindergarten spaces • Program will accommodate Developmental Pre-school • Functional Skills spaces will be provided at the Ordway site only • Program anticipates interior hallways Site Basic standard program suggests a minimum site area of ten (10) acres City of Bainbridge Island 2008 Capital Facilities Plan Update 110 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 7 INTERMEDIATE SCHOOL BASIC STANDARD PROGRAM SPACES Core Instruction • General classrooms • Small group study • Teacher work area/planning • Student toilets • Shared teaching/learning space • Science classrooms • Science Prep Special Education • Resource room • Office • Time Out • Storage • Testing Functional Skills • Functional Skills classroom • Office • Kitchenette • Toilet Art/Science/Music/Tech • Art classroom and storage • Music classroom, music storage, instrument storage • Computer lab Library/Media Center • Reading room/collection storage • Class seating • Circulation desk • Workroom/AV production • AV equipment storage Physical Education • Gymnasium • PE office/ storage • Community storage Food Service/Commons • Prep kitchen with office area • Food storage • Seating area for 300 • Stage and storage Administration • Reception/waiting/office manager • Principal’s office • Assistant Principal’s office • Conference room City of Bainbridge Island 2008 Capital Facilities Plan Update 111 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 8 INTERMEDIATE SCHOOL BASIC STANDARD PROGRAM SPACES (continued) • Staff workroom • Storage Student Services • ELL (English Language Learner)/ Title 1 Reading office and resource area • Counselor • Speech/Language Pathologist • Counseling area small group room • Health room/ office Faculty/Staff Support • Staff lounge Building Support • Student toilets • Staff toilets • Custodial spaces/receiving/building storage • Exterior covered play area INTERMEDIATE SCHOOL BASIC STANDARD PROGRAM ASSUMPTIONS General • Maximum enrollment is 600 students, grades 5 and 6 • Personalized learning is emphasized • Two (2) Special Education classes are included • Functional Skills area is provided to serve up to eight (8) students • Lunch will be served in three (3) shifts, each accommodating 200 students • Interior hallways Site Basic standard program suggests a minimum site area of twenty (20) acres City of Bainbridge Island 2008 Capital Facilities Plan Update 112 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 9 MIDDLE SCHOOL BASIC STANDARD PROGRAM SPACES Core Instruction • General classrooms • Small group study • Teacher work area/planning • Student toilets • Shared teaching/learning space • Science classrooms • Science Prep Special Education • Resource room • Office • Time Out • Storage • Testing Functional Skills • Functional Skills classroom • Office • Kitchenette • Toilet Art/Science/Music/Tech • Art classroom and storage • Music classroom, music storage, instrument storage • Computer lab Library/Media Center • Reading room/collection storage • Career Center • Class seating • Circulation desk • Workroom/AV production • AV equipment storage Physical Education • Gymnasium • PE office/ storage • Community storage • Student lockers/showers/toilets Food Service/Commons • Prep Kitchen/ food storage/ office/ toilet • Seating area for 325 • Stage and table storage Administration • Reception/waiting/office manager • Principal’s office City of Bainbridge Island 2008 Capital Facilities Plan Update 113 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 10 MIDDLE SCHOOL BASIC STANDARD PROGRAM SPACES (continued) • Assistant Principal’s office • Attendance/ records storage • Conference room • Staff workroom • Storage Student Services • ELL (English Language Learner) office and resource area • Counselor • Speech/Language Pathologist • Health room/ office Faculty/Staff Support • Staff room/ kitchen/ workroom Building Support • Student toilets • Staff toilets • Custodial spaces/receiving/building storage • Exterior covered play area MIDDLE SCHOOL BASIC STANDARD PROGRAM ASSUMPTIONS General • Maximum enrollment is 650 students, grades 7 and 8 • Personalized learning is emphasized • Two (2) special education classes are included • Functional Skills area is provided to serve up to eight (8) students • Central food prep is on-site • Lunch will be served in two (2) shifts, each accommodating 325 students • Interior hallways • A full-size gymnasium is programmed; dividable into two (2) practice courts. With spectator accommodation on each side. Site Basic standard program suggests a minimum site area of twenty (20) acres City of Bainbridge Island 2008 Capital Facilities Plan Update 114 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 11 HIGH SCHOOL BASIC STANDARD PROGRAM SPACES Core Instruction • General classrooms • Shared instructional area • Small group / seminar • Faculty planning Special Education • Learning Strategies / special education Functional Skills • Functional Skills classroom • Toilet/ shower/ changing/ laundry Science • Physics/Prep • Chemistry/Prep • Biology/Prep • General science/ prep • Central science/ prep storage Occupational Ed./Unified Arts • Art studio/ materials storage/ kiln • Business Education/ storage • Journalism/ annual workroom • Industrial technology lab • Photography lab/ darkroom • Home & Family Life/storage • Clean lab/ storage • Technology lab/ laser/ storage • Production • Foyer/ gallery Music • Vocal music classroom • Office/ storage • Instrumental music classroom • Office/ storage • Practice rooms (Performance space in Large Group Instruction (LGI) Space or Great Hall) Large Group Instruction • Drama classroom • Large Group Instruction/ Theater/ stage/ support 300-600 seats1 • Concessions • Ticket area 1 Seating capacity to be determined during educational specification process. City of Bainbridge Island 2008 Capital Facilities Plan Update 115 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 12 HIGH SCHOOL BASIC STANDARD PROGRAM SPACES (continued) Library/Media Center • Reading room/collection storage • Career Center • Librarian Workroom/ office • AV equipment storage • Copy center • Media production room • Large conference room Physical Education • Gymnasium • Auxiliary Gymnasium • Weight room • Movement/ wrestling • Movement/ gymnastics • Storage • Training/ testing classroom • Health classroom • PE lockers • Athletics lockers • Toilets • PE office/ storage • Laundry Food Service/Commons • Prep kitchen with office area • Commons/ cafeteria-600 seats • Student store/ storage Administration • Reception/waiting/office manager • Principal’s office • Assistant Principal’s office • Attendance/ waiting • Athletic Director • Bookkeeper • Conference room • Staff workroom/ mailboxes/ storage • PTSA/ parent area Student Services • Reception • Registrar • Itinerant • Conference/ testing • Counselor • ASB office • Workroom/ storage • Health room/ office City of Bainbridge Island 2008 Capital Facilities Plan Update 116 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 13 HIGH SCHOOL BASIC STANDARD PROGRAM SPACES (continued) Faculty/Staff Support • Staff room/ kitchen/ workroom Building Support • Student toilets • Staff toilets • Custodial spaces/receiving/building storage • Exterior covered area HIGH SCHOOL BASIC STANDARD PROGRAM ASSUMPTIONS General • Maximum enrollment is 1,450 students, grades 9 through 12 • Personalized learning is emphasized • Increased opportunities for collaboration • Full-time staff will be assigned to a specific classroom • Part-time staff will share classrooms • Lunch will be served in two (2) shifts, each accommodating 600 students (assumes that a partial open campus concept will continue) Site Basic standard program suggests a minimum site area of forty (40) acres City of Bainbridge Island 2008 Capital Facilities Plan Update 117 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 14 OPTIONS SCHOOL BASIC STANDARD PROGRAM SPACES Core Instruction • Eagle Harbor High School (EHHS) classroom • EHHS shared instruction • Odyssey 7 and 8 learning setting (classrooms) • Odyssey 7 and 8 shared instruction • Odyssey 1 through 6 learning setting (classrooms) • Odyssey 1 through 6 shared instruction • Home School classroom • Flexible classroom • Teacher workroom/ prep/ storage Art/Science/Music/Tech • Art classroom and storage • Dark room • Science classroom • Science prep/ storage Music/ Drama • Music/ Drama classroom • Office/ storage Library/Media Center • Library • Computer lab Physical Education • Gymnasium/ lockers/ office/ storage Food Service/Commons • Serving kitchen • Dining/ commons Administration • Reception/waiting/office manager • Principal’s office • Assistant Principal’s office • Attendance/ waiting • Athletic Director • Bookkeeper • Conference room • Staff workroom/ mailboxes/ storage • PTSA/ parent area Student Services • Reception • Registrar • Itinerant • Health Room/ office City of Bainbridge Island 2008 Capital Facilities Plan Update 118 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 15 OPTIONS SCHOOL BASIC STANDARD PROGRAM SPACES (continued) Faculty/Staff Support • Staff lounge Building Support • Student toilets • Staff toilets • Custodial spaces/receiving/building storage • Exterior covered play area OPTIONS BASIC STANDARD PROGRAM ASSUMPTIONS General • Maximum enrollment is 325 students, grades 1 through 12 • Personalized learning is emphasized • Assumes that the Options school will continue to serve four (4) academic programs represented by: Eagle Harbor High School Odyssey grades 1-6 Odyssey grades 7-8 Home school program • Staff will not be assigned to specific classrooms • Lunch will be served in a common cafeteria but be prepared off site • Interior hallways • Community program are not included in the basic standard program Site Basic standard program suggests a minimum site area of ten (10) acres City of Bainbridge Island 2008 Capital Facilities Plan Update 119 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 16 Educational Objectives The Educational Objectives formed during the Master Plan process in 2005 developed a basic standard model for program delivery on Bainbridge Island. As described in Chapter 2, each facility in the school was comprehensively evaluated to determine whether the existing space was sufficient to meet educational need, District vision, educational trends and enrollment (current and future). Although the State Superintendent of Public Instruction establishes square footage guidelines for capacity, those guidelines do not consider local program needs. The basic standard model provides the framework to determine capacity for the programmatic needs of the Bainbridge Island School District. Future facility improvements will address deficiencies identified by the Facilities Master Plan and will accommodate future growth. Methods for Measuring Capacity in the Past In the District’s prior Capital Facilities Plans, capacity was measured by comparing current enrollment to the space available to serve that site’s population. The amount of space needed was based on the school’s population divided into the number of available classrooms (with consideration of class size). General education, elective/specialist, and special education class size were defined within the Bainbridge Island Education Association’s (BIEA) negotiated contract. If the site could not serve the entire student population, then short-term space was utilized and reported under the label of ‘temporary space’. These capacity calculations were often inconsistent. Methods for Measuring Capacity at Present In preparing this CFP, the District has taken the opportunity to standardize its calculations for capacity. To determine the total capacity of the District, the existing District facilities were listed by grade level. This included three elementary schools (grades K-4), intermediate school (grades 5-6), middle school (grades 7-8), high school (grades 9-12), Options school (grades 1-12 including the Odyssey and Eagle Harbor 3 Inventory of Existing and Planned Facilities City of Bainbridge Island 2008 Capital Facilities Plan Update 120 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 17 programs), and ancillary facilities. The total student capacity was calculated by program use (utilization) and class size determined by the BIEA contract. Seven categories have been identified at each site to determine school program capacity (Table 1). They include: core instruction, elective/specialist, physical education, special education, non- school, temporary, and support space. These seven categories have been applied to site maps (pages 36-46) and recorded by category to measure total program space and capacity (Table 3). Currently, the District has permanent program capacity to house 4,0881 students and temporary classroom capacity to house 507 students. This capacity is based on the basic standard program as described in Chapter 2 and detailed in the Facilities Master Plan. This chapter will outline (1) the District definition and use of temporary facilities; (2) a visual display of core instruction and elective permanent classrooms at each site; (3) an explanation of how spaces are measured and utilized when determining capacity; and (4) current classroom capacity and projected capacity for the next six years. Definition of and Use of Temporary Classrooms Within this plan, temporary spaces are defined as spaces that do not meet adjacency, program, or long-term plan requirements as set forth by the District’s Master Plan. These spaces, which include portables, are used for a limited amount of time. During the 2005-2006 school year, overall the District used nineteen (19) temporary classrooms to house students in excess of permanent capacity for classroom purposes at school locations, and six (6) temporary classrooms for other program purposes. Currently Bainbridge High School is using eleven (11) classroom spaces at the Commodore building. These spaces are considered temporary at BHS because they are not adjacent to complementary programs and the spaces do not meet the District’s Master 1 This includes the Commodore/Options programs as listed under the PCM category in Table 2 and listed under 2005-06 Permanent Building Capacity in Table 3 City of Bainbridge Island 2008 Capital Facilities Plan Update 121 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 18 Plan specifications. An additional four (4) portable classrooms were brought on site to accommodate students during the 2006-2007 school year. Current core classroom space at the high school is inadequate to service a student population of 1,450 and there is no additional temporary space available for use. The new BHS building 200 currently under construction will reduce the need for temporary housing at BHS by adding permanent classroom core capacity to adequately house 1,450 students. Temporary classrooms may be used as interim or transitional facilities: • To prevent overbuilding or overcrowding of permanent school facilities. • To cover the gap between the time of demand for increased capacity and completion of permanent school facilities to meet that demand. • To meet unique program requirements. • To provide temporary housing for classes displaced as a result of construction activities. The information within this CFP projects that the District will use temporary classrooms to accommodate interim housing needs for the next six years. The use of temporary housing, its impact on permanent facilities, life cycle and operational costs, and the interrelationships between temporary classrooms, emerging technologies, and educational restructuring will continue to be examined. Due to the fact that temporary facilities do not address permanent capacity, short and long term goals are outlined within the Facilities Master Plan to help each school site maximize permanent capacity potential. As student enrollment fluctuates, temporary classrooms provide the flexibility to accommodate immediate needs and interim housing. The use and need for temporary classrooms will continue to be balanced against instructional program needs. In addition to temporary re-locatable classrooms, the District also uses classrooms at Commodore Options School to alleviate the classroom shortage at the high school and City of Bainbridge Island 2008 Capital Facilities Plan Update 122 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 19 also to house the District’s Options programs. It is anticipated that these classrooms will be used for the life of the six-year plan, while additional permanent classrooms are constructed at the high school. Included in this plan are two independent ways of calculating square footage and capacity of existing schools (Table 2). The BISD capacity summary sheet (Table 3) provides individual school permanent and temporary capacities. The building capacity that is reflected in this CFP has been updated to reflect current programmatic needs as identified and described in the Facilities Master Plan. In the future, all updates to BISD school capacity figures will use the 2006 CFP as a baseline for comparison and reporting purposes. Two factors may change this baseline in the future: a negotiated BIEA contract that produces a change in class size, or program changes approved by the BISD board of directors. The CFP will be updated to reflect this information if either of these two variables changes. Core Instruction and Elective Permanent Classroom Formulas The configuration of schools in the district includes three elementary schools grades K-4; one intermediate school grades 5-6; one middle school grades 7-8; one high school grades 9-12; and an options school grades 1-12. Per BIEA agreement, class sizes are limited to the following numbers: Elementary Schools Grades K-4 Number of classes per grade Grades Class Size Limit at each site K 25 students 3 1 25 students 3 2 26 students 3.5 3 26 students 3.5 4 27 students 4 The number used to measure capacity for grades K-4 is 25.8, which is the average of class size limits. City of Bainbridge Island 2008 Capital Facilities Plan Update 123 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 20 Intermediate Programs Grades 5-6 Number of classes per grade Grades Class Size Limit at school site 5 27 students 11 6 27 students 11 The number used to measure capacity for grades 5-6 is 27, which is the average of class size limits. Secondary Programs 7-12 At the secondary level, capacity is determined by curriculum area. Per BIEA agreement, class sizes for each area shall be limited to: Curriculum Areas: Limits Core Instruction Lab Science 28 Language Arts/Comp. Block 28 Language Arts/Literature 29 Mathematics 29 Social Studies 29 Average class size for core instruction: 28.6 Utilization of classrooms is 85%1, therefore the total average for core instruction class size is 24.3 Curriculum Areas: Limits Electives/Specialists Art 29 Business Education 35 Foreign Language 29 Home & Family Life 29 Music 38 Science 29 Technology 29 1 15% for teacher planning/prep. Per BIEA agreement City of Bainbridge Island 2008 Capital Facilities Plan Update 124 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 21 Production 25 Drafting 28 Photography 28 Traffic Safety 29 Average class size for elective instruction: 29.8 Utilization of classrooms is 85%1, therefore the total average for Electives/specialists instruction class size is 25.3 The number used to measure capacity for grades 7-12 is determined by taking the average of class size limits for core and elective instruction based on 85% utilization (5 of 6 periods a day the class is in use). The core number of 24.3 and the elective number of 25.3 are the two averages used to measure capacity. Projected Six-Year Classroom Capacity Program capacity is periodically updated for changes in special programs. Projected enrollments and capacities for the District’s schools determine the need for facilities to be large enough to address current and projected enrollments (Table 4). Enrollment is reported to the Office of the Superintendent of Public Instruction (OSPI) on Form P-223 on a monthly basis. Apportionment funding is based on Annual Average Percentage FTE (AAFTE). The first school day of October is set by OSPI as the official enrollment count date for the year. FTE projections through 2010 are based on enrollment growth or loss percentages (calculations) at each grade level based on the past three actual FTE October counts (Figure 5). For this report the trend data (three years) from 2004 to 2006 has been used (Table 5). Based on enrollment forecasts, current inventory and capacity, current standard of service, and temporary classroom capacity, the District anticipates having sufficient capacity to house students in grades K-8 over the next six years. Insufficient capacity at the high school, grades 9-12, that results in part from residential development on the island, requires improvements and expansion of the high school facility. 1 ibid. City of Bainbridge Island 2008 Capital Facilities Plan Update 125 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 22 In order to put current enrollment in perspective, it is important to consider past enrollment history. For capital facilities planning purposes, student growth projections are typically based on several factors. The first is the net percentage of students who remain in Bainbridge Island schools from 1st through 12th grade, or cohort survival. The second is three-year trend data of the percentage of growth or loss from actual October FTE enrollment counts. The third factor is estimated kindergarten enrollment in comparison to Bainbridge Island live birth rates (Table 4). The final factor is regional population growth, based on population studies conducted by Puget Sound Regional Council (small area forecast released October 2006). To determine the number of kindergartners projected to enter the system, actual kindergarten enrollments were compared to the number of live births on Bainbridge Island over the past ten years. Actual kindergarten enrollment for October 2005 was 220 students; this number represents 129% of the 170 Bainbridge Island live births in 2000. Within the past five years, actual kindergarten enrollment on average has been 138% of the island’s live birth rate. Enrollment exceeds the live birth rate within the District because new residents on the island with pre-school children move into new and existing housing. The cohort survival method will be used within this CFP to illustrate historical enrollment data and then forecast the number of students projected until 2010-11. The District’s elementary school population decreased when comparing the 1998-99 school year to the 2005-2006 school year (Table 4). The elementary school population peaked at 1320 during the 1999-2000 school year. Enrollment declined slightly each year and is reported in the 2006 October P223 at 1,175. The elementary population is projected to increase slightly through the 2010-11 school year with enrollment projected at 1269. Student population increased at the intermediate and middle schools through 2004-05. These populations are projected to plateau at approximately 1200 students by the 2010-11 school year. The high school population has increased at a consistently rapid rate from 1998-99 through 2006-07. It is projected to decline slightly from population 4 Enrollment City of Bainbridge Island 2008 Capital Facilities Plan Update 126 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 23 averages recently reported in the 1,500s and eventually stabilize through 2010-11 to a number closer to 1,450. Demographic Studies Used The most recent demographic study commenced in the spring of 2007. A final report was shared with the Board in July of 2007. This study was used along with the District’s Facilities Master Plan, which incorporated the District’s 2004 Six Year Capital Facilities Plan and two demographic studies as a basis for its 15-year plan. The first study was prepared in January of 2005 by Portland State University and blended cohort survival with regional growth to examine District enrollment counts and projections. The second study was prepared in May of 2005 by Harold Skow and blended cohort survival with Bainbridge Island live births. The third, and most recent study, prepared by Reed Hansen began in the spring of 2007. This recent study incorporates cohort survival, regional growth and Bainbridge Island live births. All studies demonstrate relative trends and provide a comprehensive picture of present and future enrollment numbers. Analysis of the most recent demographic information suggests that District enrollment stays within a constant range for the next two years and then will show a modest increase at the elementary grades by 2010. Grades 7 and higher show an increase in enrollment between the years 2005 and 2007. After 2007 enrollment slightly decreases and then stabilizes by 2010. Assumptions supported by the most recent census data suggest families moving on to the island are not first time home buyers. The majority of these families are moving in with children in the 3rd grade and above. When combined, the demographic data and the census data support the current District enrollment projections used in this CFP. Current Methodology In prior plans, headcount numbers were used to report enrollment and make enrollment projections primarily because the state reporting system did not require full time equivalent (FTE) information on its P-223 forms until the fall of 2005. In this CFP, the District has measured program capacity based on FTE and not headcount. Program specifications from the Master Plan will be used as guiding principles from this point on in facility planning. The District has determined through its Master Plan process that, City of Bainbridge Island 2008 Capital Facilities Plan Update 127 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 24 how each space is used and which students use it, are important components to long-term planning. Overall student-wide enrollment increased from 1998-99 to 2004-05. In general terms, the average annual growth rate of the District’s total enrollment from 1999 through 2010 is estimated to be 0.30%. (This data is displayed in Table 5 and illustrated in the corresponding Figure 1) The District’s highest actual enrollment numbers were reached during the 2005-06 school year. The growth rates in the student population are slowly starting to lose momentum and should plateau by 2010. Facility improvements recommended in the Facility Master Plan have considered enrollment projections through 2010. Enrollment projections support the need for continued elementary and high school improvements over the next six years. The District will continually monitor enrollment projections in comparison to growth of residential construction on the island. This will be done by using data available from the City of Bainbridge Island Building Department and permit information from the Puget Sound Regional Council. An annual average of 250 net new units has been built on the island since 1990. Of these new units, an average of 177 units has been developed as single-family housing and 73 as multi-family housing. These data (Figure 2) illustrate growth and development on the Island since 1990. There was a decline in residential construction in the early 1990s. It then peaked at the turn of the decade. Between 1992 and 1999 housing growth was steady. Following a small dip between 1999 and 2001, housing has continued to grow at a consistent pace. The number of residential units in multi-family housing surpassed single-family housing units in 2003, and this trend is likely to continue. Market and real estate indications are that the overall rate of development will continue into the near future. Between 2000 and 2006 the population of Bainbridge Island increased from 20,308 to 22,600 (Figure 3) an average annual change of 1.19% (Table 6). The Island population has been consistently increasing since the 1990 census and has continued since the 2000 census (Figure 3). City of Bainbridge Island 2008 Capital Facilities Plan Update 128 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 25 The CFP enrollment data is a combination of current district data (October P223 reports) and the Facility Master Plan data gathered from several demographic studies and published in 2005. The enrollment projections that were prepared in 2004 for the Facilities Master Plan took into consideration birth rates, enrollment history, and housing construction trends at 2004 levels. Again, the current projection forecasts that total District enrollment will plateau by 2010. The District projects the growth in the number of students experienced within the past five years will stabilize for the next three years. The largest impact to facilities at present is this large increase in enrollment that began in 2001: the student cohorts that have grown throughout grades K-12 within the District system. As Figure 6 shows, according to the cohort survival method, the 1,075 students enrolled in grades 1-4 in the District in 1996/97 should have resulted in a population of grades 9-12 of approximately the same number. Instead, there were 1,464 students enrolled in grades 9-12 in 2005/06. This means that, as of 2005/06, there are approximately 389 additional students in that cohort who have moved into the District since 1996-1997. The majority of those 389 new students entered the District due to the development of the approximately 250 new dwelling units constructed on the island each year since 1990 (approximately 4,000 new dwelling units over the entire sixteen year period). The only other source of this increase could be migration from private schools; however, the District estimates the total private school transfers in grades 9-12 to be no more than 30 students per year. In the high school as a whole, then, approximately 255 students of the expected future stabilized population of 1,450 high school students during the term of this CFP will have entered the District due to new housing development (1,450 less 1,075 from the surviving cohort, less 120 students from private schools over four years). But for new housing development and private school transfers, anticipated high school population would be expected to stabilize at a number much closer to 1,075 students, as the cohort survival method applied to the data set forth in Figure 6 would predict. City of Bainbridge Island 2008 Capital Facilities Plan Update 129 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ 26 Revised 08.15.07 Current Level of Service Based on the Facilities Master Plan analysis, the program evaluation indicates a significant space need largely due to new development at the high school campus in core facility and basic instructional classroom space. This is substantiated by the accreditation evaluation that was conducted at the high school campus in May 2005. Furthermore, all of the elementary school buildings lack sufficient accommodation for interdisciplinary learning, student services, team teaching, all school gatherings, and community use. In addition to the program evaluation, during the Master Plan process all District facilities had a physical assessment that summarized the condition of all primary site and building components. Current building codes, the Bainbridge Island Municipal Code, and other recent school district building surveys formed the basis of this evaluation. With the exception of Sakai Intermediate School, Woodward Middle School, and the most recent work at the high school campus and Commodore, none of the buildings satisfies the requirements of the current building codes. Additionally, most buildings are simply worn out in terms of basic infrastructure such as the septic systems, ventilating systems, windows, finishes, plumbing, and power and communications. If infrastructure issues are addressed, local agencies would likely require that entire facilities be brought to a condition that is consistent with current building codes. In a continued effort to improve the status of our existing facilities, the District will bring specific bond requests to the community in the future. The District will address the basic infrastructure improvements as identified by the Facilities Master Plan as voters approve future bond requests. 5 City of Bainbridge Island 2008 Capital Facilities Plan Update 130 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ 27 Revised 08.15.07 Methodology for Level of Service The Bainbridge School District's "level of service" has been defined in terms of the amount of permanent and temporary school space that is provided for the instruction of elementary, middle and high school students. Two different models were used to define level of service. The Space Allocation Model (SAM) was selected along with the Practical Capacity Model (PCM) because each paints a different picture of how capacity can be derived1 (Table 2). Space Allocation Model There are several advantages of the Space Allocation Model (SAM). First, SAM is a well-established and familiar model. WAC 180-30-110 set forth four factors that govern the level of state assistance provided to school districts for the funding of new school facilities. One of those factors is a "square foot per student" space allocation (i.e. 80 square feet per student in grades K-6, 110 square feet per student in grades 7 and 8, and 120 square feet per student in grades 9-12; a specially designated self-contained classroom is 140 square feet per student). The space allocation figures set forth in WAC 180-30-110 are only used for the purpose of determining a school district's eligibility for state matching funds. Clearly, those space allowances do not reflect an accurate total of the true space needed to carry out the District’s instructional programs. However, the state's square footage figures are very familiar to anyone associated with new school construction in the State of Washington. A second advantage is that SAM is an easier model to use, particularly at high school levels. Accurately assessing the practical capacity of a middle or senior high school is extremely difficult. Teacher planning periods, specialty areas like food service, laboratories, music rooms, shop classrooms, the Running Start Program, late arrival, early dismissal, and zero periods are just a few examples of the complexities of a secondary school's instructional program. 1 The Options school is intended to be located at the Commodore building during the life of this plan. Since the program is multi-age and has unique requirements, it is not included in the SAM analysis. City of Bainbridge Island 2008 Capital Facilities Plan Update 131 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ 28 Revised 08.15.07 Finally, the SAM is also a much easier model to explain. The straightforward calculations of the SAM are not difficult to understand, especially for someone who is not familiar with the complexities of the instructional programs of schools. Consistent with the state definition of temporary space, the District does not use portable classroom square footage as part of its permanent calculations, but continues to use portables and interim spaces in its overall District capacity calculations (Table 3). The District does not consider portables to be adequate long-term instructional space for students or staff members. By design, portable classrooms separate their occupants from the rest of a school's student body or staff. While portables accommodate increased enrollment they also tax the common areas of the permanent buildings, areas like the gymnasium, the library, the restrooms, the main office and the food service facilities. The Bainbridge Island School District reserves the right to adjust the benchmark “level of service" as needed to accommodate its instructional program within the District. As instructional programs evolve, obviously facilities requirements must also be adjusted. Practical Capacity Model The Practical Capacity Model (PCM) is more complex than the SAM, but important to use because of the District’s vision to provide a basic standard of service that is based on its educational objectives. A formula has been created using the BIEA negotiated contract to measure capacity at each school site, which is based on class size limits and space utilization. Spaces have been audited, color coded, and labeled according to program (Table 1). A formula of permanent space multiplied by class size equals permanent class space capacity (p x s = c). As set out in Table 1, the PCM is a complex measurement that focuses on current educational trends and programmatic needs. A formula of temporary space has been created in the same fashion that includes temporary space multiplied by class size equals temporary class space capacity (t x s = c). Capacity within this model is more complex because it has been determined through appropriate class size along with a grade appropriate utilization formula (defined in Chapter 3 and displayed in Table1). City of Bainbridge Island 2008 Capital Facilities Plan Update 132 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ 29 Revised 08.15.07 Table 2, which shows both the SAM and PCM building capacity for the District, illustrates the complexities of interpreting and reporting building capacity. City of Bainbridge Island 2008 Capital Facilities Plan Update 133 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 30 Capital Projects Finance Plan and Timeline Current Financing The 2005 Facilities Master Plan identified long-term District needs, provided a response to findings from an in-depth facility assessment, prioritized immediate needs based on health/life safety and core academic shortcomings, and suggested a proposed implementation plan for the next fifteen years. Voters passed the first phase of the Facility Master Plan in May of 2006. This $45 million bond primarily addresses classroom needs and the deficiencies of basic core facilities at the high school. The bond also addresses health/life safety and infrastructure issues across the school district, funds existing District commitments, provides for a new maintenance facility, improves athletic fields; and establishes a miscellaneous replacement allocation for use at Blakely, Ordway, Wilkes and Commodore. Recently the District developed educational specifications to identify specific classroom and core deficiencies. These specifications have been incorporated into the high school addition and modernization project. Classroom size is now at 990 square feet. The construction contract awarded in May, 2007 confirms construction costs, including soft costs of 53%, are now $482 per square foot. The District six-year finance plan in Table 7 summarizes projects identified in the recent bond, Facilities Master Plan recommended projects for future bond consideration, and anticipated funding sources for 2007-2013. Additional Revenue Sources In fact, the first phase of the Master Plan identified a total of $48.5 million in facility improvement needs (Table 8). In anticipation of collecting impact fees and state matching funds, the Board decided to bring a reduced bond package of $45 million to the voters. The District is currently pursuing state matching funds, and by adoption of this plan and its incorporation into the City’s Comprehensive Plan, the City will be able to continue disbursing the appropriate level of impact fees to the District. 6 City of Bainbridge Island 2008 Capital Facilities Plan Update 134 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 31 Future Facility Improvements The master plan implementation schedule (Figure 4) identifies the need for a second phase capital improvement bond to be presented to the voters in 2009. The District is currently in the process of working with a Master Plan Implementation Committee. The finalized demographic study and a district facility assessment will be presented to the School Board in fall of 2007. At that time the School Board will provide direction regarding additional information needed for their decision regarding Phase II of the Master Plan and the associated November 2009 bond request. The estimated Six-Year Finance Plan (Table 7) identifies each project that will be evaluated for Phase II inclusion. The November 2009 bond request is currently projected to be $60 million. Development of these expenditures for 20011/12 and 2012/13 are not identified as they are dependent on project identification and bond passage. City of Bainbridge Island 2008 Capital Facilities Plan Update 135 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 32 Impact Fee Analysis The Growth Management Act provides that impact fees may be collected and spent only for public facilities that are addressed by a capital facilities element of a comprehensive land use plan. The capital facilities plan must identify: (a) deficiencies in public facilities serving existing development and the means by which those existing deficiencies will be eliminated within a reasonable period of time; (b) additional demands placed on existing public facilities by new development; and (c) additional public facility improvement required to serve new development. RCW 82.02.050. A. Deficiencies in public facilities serving existing development and the means by which those existing deficiencies will be eliminated within a reasonable period of time. As set forth in greater detail in the Facilities Master Plan and noted above in Section 6, the District voters passed a $45 million dollar bond issue in March of 2006 to address, among other things, the following District facilities that are deficient in their capacity to serve existing development: the high school commons, cafeteria, library, and administration facilities; high school site improvements and infrastructure; health/life safety elements at other District facilities; the District maintenance facility, numerous athletic fields, and miscellaneous building systems at Blakely, Ordway, Wilkes, and Commodore schools. As explained below, a proportion of these costs can be directly attributed to new development. As stated in Chapter 6, a bond election to fund implementation of the next phase of the District’s Facilities Master Plan is tentatively scheduled for 2009 (see Figure 4). The November 2009 bond request is currently projected to be $60 million. Development of these expenditures for 20011/12 and 2012/13 are not identified as they are dependent on project identification and bond passage. A portion of these costs may be attributed to new residential development. They will be analyzed further in future District capital facilities plans. 7 City of Bainbridge Island 2008 Capital Facilities Plan Update 136 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 33 B. Additional demands placed on existing public facilities by new development. As discussed in Chapter 4, approximately 255 of the 1,450 student population expected in the high school will continue to be present as a direct result of new residential development. As also noted above and in Table 3, the existing classroom capacity at the high school is 1,216 students. Were it not for new residential development, current high school classroom capacity would be sufficient. Without new development, the needed classroom capacity would total approximately 1,195 students (which equals the sum of 1,075, the number of students predicted by the cohort survival method, plus 1201, the number of students expected from private school transfers). In order to create the additional classroom capacity needed to serve the 255 extra students that continue to be present as a direct result of new development, classroom capacity needs to be increased by an additional 234 students (which equals the projected stable population of 1,450, minus the current classroom capacity of 1,216). C. Additional public facility improvements required to serve new development. As discussed in paragraph B above, 100% of the increase in classroom capacity of the high school is required to serve students from new residential development. Approximately 17.6% of the total planned capacity of the high school will be needed to serve new growth (255 students out of the 1,450 student planned capacity). To increase the classroom capacity of the high school from 1,216 students to 1,450 students requires construction of 10 new core classrooms, at 990 square feet per classroom, for a total of 9,900 square feet of new construction. At a construction cost of $482 per square foot, this amounts to a total cost of $ 4,771,800 for 10 new classrooms. As stated above, all of this cost is directly attributable to new growth. The remaining elements of the high school construction project (science classrooms, additional library and administrative space, building support, additional commons and 1 Note: The 120 number represents new transfer students at the high school over a four-year period. This number is probably smaller because the District does not separately account for students who may have been in the District at earlier grades. City of Bainbridge Island 2008 Capital Facilities Plan Update 137 of 186 Bainbridge Island School District No. 303 Capital Facilities Plan ______________________________________________________________________________ Revised 08.15.07 34 cafeteria space, site and infrastructure improvements, and off-site improvements) will serve both new growth and existing needs. Accordingly, only 17.6% of the cost of these improvements is attributable to new growth (the ratio of new students to existing students). The cost of these remaining elements is estimated to be $ 28,944,398; 17.6% of that cost, or $ 5,094,214 is therefore the cost of these remaining elements that are directly attributable to new residential growth. The total cost directly attributable to new residential growth is therefore the sum of: (i) $ 4,771,800, which represents 100% of the cost of constructing 10 new core classrooms (9,900 square feet of new classroom space, multiplied by $482 per square feet in construction costs, equals $ 4,771,800); PLUS (ii) $ 5,094,214, which represents 17.6% of the cost of all elements of the High School other than classrooms ($ 28,944,398 multiplied by 17.6%, equals $5,094,214), for a total of $ 9,866,014. In summary, the District is authorized to collect a total of $ 9,866,014 in impact fees for the current high school project as confirmed by the construction contract awarded May 2007. City of Bainbridge Island 2008 Capital Facilities Plan Update 138 of 186 35 Revised 08.15.07 BISD School Capacity and Utilization Formulas All school capacity is determined by program use and class size as determined by the BIEA contract. The following categories have been identified at each site to determine school program capacity: Color code Letter code Program code Description of program components Purple C Core instruction Class size as determined by BIEA contract divided by the number of periods the space is utilized K-4: 25* 5-6: 27* 7-12: 29* Green E Elective/Specialist Class size for grades K-6 is the same as core instruction, with the exception of PE. Class size for grades 7-12 is dependent upon the elective; therefore, the class size indicated in the BIEA contract for that specific elective will be used to determine capacity. Orange P PE Physical Education is unique and has a different student: teacher ratio. The BIEA contract states PE capacity Blue S Special Education Average 8 students per teacher Beige N Non-school Spaces utilized for programs serving school aged students and not used for instructional purposes such as before & after school care or district use. Grey T Temporary Spaces (portables) currently utilized for programs serving school aged students and not counted as permanent building area. White Support Spaces utilized for student services, faculty/staff and building support. Table 1 -Overall utilization and capacity is determined by the number of periods a space is used (usually 6 to 7 periods a day depending on time blocks and the grade level served). *Most core spaces are used 85% of the time with 15% reserved for teacher planning. These percentages will be applied to spaces when determining overall capacity. Elective and specialist teachers also are given a 45-minute planning/preparation time as outlined in the BIEA contract, so these spaces fall under the same formula. Special education programs do not fall under this definition due to the number of support staff the cover planning time. -OSPI state match square footage calculations do not include portable classroom inventory. City of Bainbridge Island 2008 Capital Facilities Plan Update 139 of 186 Revised 08.15.07 36 City of Bainbridge Island 2008 Capital Facilities Plan Update 140 of 186 Revised 08.15.07 37 City of Bainbridge Island 2008 Capital Facilities Plan Update 141 of 186 Revised 08.15.07 38 City of Bainbridge Island 2008 Capital Facilities Plan Update 142 of 186 39 Revised 08.15.07 City of Bainbridge Island 2008 Capital Facilities Plan Update 143 of 186 40 Revised 08.15.07 \\ City of Bainbridge Island 2008 Capital Facilities Plan Update 144 of 186 41 Revised 08.15.07 E4 City of Bainbridge Island 2008 Capital Facilities Plan Update 145 of 186 42 Revised 08.15.07 E5 C22 City of Bainbridge Island 2008 Capital Facilities Plan Update 146 of 186 Revised 08.15.07 43 City of Bainbridge Island 2008 Capital Facilities Plan Update 147 of 186 Revised 08.15.07 44 C4 C5 C6 C7 City of Bainbridge Island 2008 Capital Facilities Plan Update 148 of 186 Revised 08.15.07 45 C19 C18 C17 C16 City of Bainbridge Island 2008 Capital Facilities Plan Update 149 of 186 Revised 08.15.0746 City of Bainbridge Island 2008 Capital Facilities Plan Update 150 of 186 Revised 08.15.07 47 Table 2 City of Bainbridge Island 2008 Capital Facilities Plan Update 151 of 186 Revised 08.15.07 48 Table 3 City of Bainbridge Island 2008 Capital Facilities Plan Update 152 of 186 Revised 08.15.07 49 Table 4 City of Bainbridge Island 2008 Capital Facilities Plan Update 153 of 186 Revised 08.15.07 50 Table 5 City of Bainbridge Island 2008 Capital Facilities Plan Update 154 of 186 Revised 08.15.07 51 Bainbridge Island Estimated Population Totals Year 2000 2001 2002 2003 2004 2005 2006 Estimated Population 20,308 20,740 20,920 21,350 21,760 22,200 22,600 Annual Change 2.13% 1.00% 1.02% 1.01% 1.02% 1.01% Sources: Washington State Office of Financial Mgt. Puget Sound Regional Council Note: Population totals available each April for prior year. Table 6 City of Bainbridge Island 2008 Capital Facilities Plan Update 155 of 186 Revised 08.15.0752 Table 7 City of Bainbridge Island 2008 Capital Facilities Plan Update 156 of 186 Revised 08.15.0753 Table 8 Revised 08.15..07 City of Bainbridge Island 2008 Capital Facilities Plan Update 157 of 186 Revised 08.15.07 54 Figure 1 BISD Enrollment and Projections 0 500 1000 1500 2000 2500 3000 3500 4000 4500 19 98 1999 20 0 0 20 0 1 20 02 2003 2004 20 0 5 20 06 20 07 2008 2009 20 1 0 FTE Ye a r Elementary School Interm. & Middle School High School Total FTE City of Bainbridge Island 2008 Capital Facilities Plan Update 158 of 186 Revised 08.15.07 55 Figure 2 Bainbridge lsland Building Permits 1990-2004 -100 0 100 200 300 400 500 600 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 Year Un i t s New Permits Lost Units Net Permits Single Family Multi Family Net Units City of Bainbridge Island 2008 Capital Facilities Plan Update 159 of 186 Revised 08.15.07 56 Figure 3 Bainbridge Estimated Population Totals 2000-2006 City of Bainbridge Island 2008 Capital Facilities Plan Update 160 of 186 Revised 08.15.07 57 Figure 4 November, 2009 City of Bainbridge Island 2008 Capital Facilities Plan Update 161 of 186 Revised 08.15.07 58 Figure 5 1993-2011 Cohort Growth Projections 0.00 100.00 200.00 300.00 400.00 500.00 600.00 700.00 800.00 900.00 19 92/1993 19 9 3 / 1 9 9 4 1994 / 199 5 1995/1996 19 96/19 9 7 19 9 7 / 1 9 9 8 1998 / 199 9 1999/2000 20 00/20 0 1 20 0 1 / 2 0 0 2 2002 / 2003 2003/2004 20 0 4 /20 0 5 20 0 5 / 2 0 0 6 2006 / 2007 2007/2008 20 0 8 /20 0 9 20 0 9 / 2 0 1 0 2010 / 2011 School Year FT E E n r o l l m e n t K 1-2 3-4 5-6 7-8 9-10 11-12 City of Bainbridge Island 2008 Capital Facilities Plan Update 162 of 186 Revised 08.15.07 59 Figure 6 City of Bainbridge Island 2008 Capital Facilities Plan Update 163 of 186 Appendix C Bainbridge Island Metropolitan Park & Recreation District Preliminary Capital Improvement Project List 2008-2013 The Park District adopted the following CFP on November 8, 2007. The projects included in this CFP are consistent with the City’s Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 164 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 165 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 166 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 167 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 168 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 169 of 186 Appendix D Bainbridge Island Fire Department Adopted Capital Facilities Plan 2007-2015 The Fire Department adopts a 9-year CFP along with its budget at the end of each calendar year. Since the City’s CFP is adopted earlier in the year, this appendix includes the Department’s adopted 2007-2015 CFP. The projects included in this CFP are consistent with the City’s Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 170 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 171 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 172 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 173 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 174 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 175 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 176 of 186 Appendix E Kitsap County Sewer District #7 Adopted Capital Facilities Plan 2006-2012 The Sewer District does not have any 2008 updates to its CFP and does not intend to adopt a 2008-2013 Capital Facilities Plan. This appendix includes the Districts adopted 2006 CFP and 2007 update. The District’s next CFP update will cover the years 2009-2014. The projects included in this CFP are consistent with the City’s Comprehensive Plan. City of Bainbridge Island 2008 Capital Facilities Plan Update 177 of 186 KITSAP COUNTY SEWER DISTRICT NO. 7 2006 CAPITAL FACILITIES PLAN District History The federal government sold the former Fort Ward military base, including land, buildings, and infrastructure, to private parties. In the early 1960s, some owners applied to Kitsap County to subdivide. Before the plats were approved, the County created Kitsap County Sewer District #7 to assume operation and maintenance of the existing sewer system. This “system”, created by the military, was simply a series of pipes draining into Rich Passage. There was no treatment of the effluent. Between 1960 and 1963, 272 lots were approved in the five Fort Ward Plats. The District is about 437 acres in size, lying within parts of Sections 10, 11, 14 and 15 in Township 24 North, Range 2 East, W.M. Some time after the district was formed; area citizens acquired the operation of the District from the County. These citizens, acting as the Board, installed interim treatment facilities. During the preparation of the first Comprehensive Plan & Engineering Report in 1990, an analysis of the land use in the district revealed a potential for 592 building sites. The immediately foreseeable need in the district was estimated at 408 homes and apartments. This information was used to establish the size of the treatment plant. After the Comprehensive Plan & Engineering Report was adopted, the District obtained grants and low interest loans from the Department of Ecology- administered Centennial Clean Water Fund that enabled the construction of the sewer system and a treatment plant. The plant started treating wastewater in August of 1996, and existing homes transferred their connections to the new sewer system. The last existing home was connected on April 14, 1999, and the old sewers ceased being used to convey sanitary sewage. In October of 1997, the District signed an Interlocal Agreement with the City of Bainbridge Island to provide treatment for 80 ERUs to reduce existing water pollution problems in the Lynwood Center area of the City. On September 25, 1998, the District’s Commissioners adopted Resolution 98-4, which deals with requests for sewage treatment plant service outside the District. That resolution states the District policy for providing services outside the existing borders of the District, which is that: City of Bainbridge Island 2008 Capital Facilities Plan Update 178 of 186 a. The proposal will correct or alleviate an existing water pollution problem, such as raw discharges or failed septic systems, etc., or serve to prevent a future such occurrence; or b. The proposed sewer service must have a clear benefit to the general community, such as permitting additional open space by permitting clustering of homes. In recognition of the City of Bainbridge Island’s need to provide sewer service to areas with failing septic systems on the South end of the Island, on September 24, 2003, the District executed an Interlocal Agreement with the City to serve up to an additional 250 residential connections. Because the District’s Commissioners have determined that its wastewater treatment plant will exceed DOE minimums for operations; and, because the addition of 250 additional residential connections will place the wastewater treatment plant near capacity; and, because there is a need for a second aeration basin to provide for maintenance of the current basin, on February 12, 2004, the District adopted a new Comprehensive Plan & Engineering Report to upgrade the existing plant. Current Planning The District is currently in the final design and preparation of bid documents phase of this treatment plant upgrade. The plan is to go to bid in the spring of 2006, and begin construction in June of 2006. Funding for this plant upgrade is expected to come from a combination of Connections Fees paid by the City under the September 24, 2003 Interlocal Agreement and a potential loan from the Public Works Trust Fund, which will be paid back from additional connection fees and service charges. When completed, the Phase II addition to the wastewater treatment plant will treat 190,000 gal/day without a clarifier and 230,000 gal/day with a clarifier. Phase II will be able to provide service to the areas currently unserved, as identified in the City’s South Island Facilities General Plan and Engineering Report (December 2001), should the City choose to service these areas. The only other capital expenditure anticipated in the next one to five years is to purchase/develop a facility to serve as a District office and a center for the Fort Ward community. City of Bainbridge Island 2008 Capital Facilities Plan Update 179 of 186 2005 2006 2007 2008 2009 2010 2011 6-yr. Total Funding Sources: LID Accounts 0000000 Connection Charges 1069 310 000001379 All Other Sources 0 1268 000001295 Total Funding 2674 Projects: Priority Treatment Plant Upgrade High 0 2324 000002324 District Office 0 350 00000350 Total Project 0 2674 000002674 Kitsap County Sewer District No. 7 Capital Facilities Plan City of Bainbridge Island 2008 Capital Facilities Plan Update 180 of 186 2007* 2008 2009 2010 2011 2012 6-yr. Total Funding Sources: LID Accounts 000000 0 Connection Charges 1129 100 0 0 0 1229 All Other Sources 457 0000 457 Total Funding 1586 100 1686 Projects: Priority Treatment Plant Upgrade High 1386 0000 1386 District Office 300 100 0 0 0 400 Total Project 1686 100 0 0 0 1786 *Note: Amounts shown in 2007 are carried over from 2006 CIP, because only First Phase of STP upgrade was awarded and completed in 2006. 2007-2012 Kitsap County Sewer District No. 7 Capital Improvement Project List City of Bainbridge Island 2008 Capital Facilities Plan Update 181 of 186 Peter Namtvedt Best From: Colleen Yuhl [mcyuhl@msn.com] Sent: Wednesday, August 15, 2007 8:18 AM To: Peter Namtvedt Best Subject: 2008 Capital Facilities Plan Page 1 of 1 8/15/2007 Peter: Per our conversation of earlier today, Kitsap County Sewer District No. 7 does not have any capital projects planned for 2008. Our sewage treatment plant upgrade, that was in our 2006-2007 plans will be completed by November 2007. We will prepare a new plan in 2008 for 2009 and beyond. Colleen Yuhl Manager KITSAP COUNTY SEWER DISTRICT NO. 7 206-459-2796 mcyuhl@msn.com City of Bainbridge Island 2008 Capital Facilities Plan Update 182 of 186 Appendix F Kitsap County Public Utility District No. 1 Adopted Capital Facilities Plan The PUD adopts a Capital Facilities Plan every 6-years when it updates its Comprehensive Plan. The PUD’s most recent adopted CFP does not include projects on Bainbridge Island since they did not own or operate any facilities on Bainbridge Island at the time it was prepared. Provided in this appendix is the PUD’s most recent capital budget which includes projects on Bainbridge Island. City of Bainbridge Island 2008 Capital Facilities Plan Update 183 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 184 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 185 of 186 City of Bainbridge Island 2008 Capital Facilities Plan Update 186 of 186