ORD 2013-26 CFP 2014 - 2019ORDINANCE NO. 2013-26 AN ORDINANCE of the City of Bainbridge Island, Washington, adopting the 2014 -2019 update of the six -year Capital Facilities Plan and amending the Capital Facilities Element of the Bainbridge Island Comprehensive Plan. WHEREAS, in accordance with the Growth Management Act, the City of Bainbridge Island adopted a Comprehensive Plan on September 1, 1994, and revised it on December 8, 2004. The Plan contains a Capital Facilities Element that establishes goals and policies for the provision and financing of capital facilities for the citizens of Bainbridge Island; and WHEREAS, the Growth Management Act requires that the six -year Capital Facilities Plan be updated at least biennially and adopted as an amendment to the Comprehensive Plan and Comprehensive Plan Policies CF 1.3, 1.4, and 1.5 require an annual update; and WHEREAS, the 2014 -2019 update of the six -year Capital Facilities Plan addresses all of the goals and requirements set forth in the Growth Management Act and the Bainbridge Island Comprehensive Plan; and WHEREAS, the 2014 -2019 update of the six -year Capital Facilities Plan is in accordance with the decision criteria for amendments of the Comprehensive Plan as set forth in BIMC Chapter 2.16.190; and WHEREAS, the Planning Commission and the City Council have received, discussed, and considered testimony, written comments, and materials from the public; now, therefore, THE CITY COUNCIL OF THE CITY OF BAINBRIDGE ISLAND, WASHINGTON, DOES ORDAIN AS FOLLOWS: Section 1. The 2014 -2019 update of the six -year Capital Facilities Plan of the Capital Facilities Element of the Bainbridge Island Comprehensive Plan, attached as Exhibit A, is hereby adopted. Section 2. In the event that there are instances where the dollar amounts or timing of capital projects included in this update differ from those in other sections of the Comprehensive Plan, the amounts and timing in this update shall prevail. Section 3. This ordinance authorizes the reformatting of Exhibit A into a final edition for publication and the reformatting of information and the transmission of this information to the State of Washington as the City's annual State Transportation Improvement Program (STIP). Page 1 of 2 Section 4. The six -year Capital Facilities Plan of the Bainbridge Island School District No. 303 adopted on October 24, 2013 is adopted by reference. Section 5. The six -year Capital Facilities Plan of the Bainbridge Island Metropolitan Park & Recreation District adopted on November 7, 2013 is adopted by reference. Section 6. The Strategic Plan 2013 -2022 of the Bainbridge Island Fire Department adopted on October 16, 2013 is adopted by reference. Section 7. The six -year Capital Facilities Plan of the Kitsap County Sewer District No. 7 for the years 2013 -2018 is adopted by reference. Section 8. The six -year Capital Facilities Plan of the Kitsap County Public Utilities District No. 1 for projects on Bainbridge Island is adopted by reference. Section 9. If any section, sentence, clause or phrase of this ordinance shall be held to be invalid or unconstitutional by a court of competent jurisdiction, such invalidity or unconstitutionality shall not affect the validity or constitutionality of any other section, sentence, clause or phrase of this ordinance. Section 10. This ordinance shall take effect and be in force five (5) days from and after its passage, approval and publication as required by law. PASSED BY THE CITY COUNCIL this 25th day of November, 2013. APPROVED BY THE MAYOR this 25th day of November, 2013. ti S en Bonkowski, Mayor ATTEST /AUTHENTICATE: �ra ltr,r�� kd 560 -* Rosalind D. Lassoff, City Ulerk FILED WITH THE CITY CLERK: October 16, 2013 PASSED BY THE CITY COUNCIL: November 25, 2013 PUBLISHED: December 6, 2013 EFFECTIVE DATE: December 11, 2013 ORDINANCE NUMBER: 2013 -26 Page 2 of 2 Ord. 2013 -26: Exhibit A CITY OF BAINBRIDGE ISLAND 2014 -2019 CAPITAL FACILITIES PLAN UPDATE October 10, 2013 City Council TABLE OF CONTENTS I. INTRODUCTION ....................................................................................................................... ..............................3 RELATIONSHIP OF CAPITAL FACILITIES PLAN TO THE BUDGET... ............................................... ......... ................... _4 WHAT1S A CAPITAL FACILITY? .................... . ............................ ........................................... ................. .................. ...4 HOW ARE CAPITAL FACILITY PROJECTS IDENTIFIED? ....................................................,.,............ ...................,.....,....5 Levelsof Service ( LOS) .............................................................................................. ............................... ...5 PRIORITIZINGCAPITAL PROJECTS ..........................................................................................,...... ............,......,._........5 II. CAPITAL FACILITIES INVENTORY & PLANNING ..................................„.................. ..............................6 CITY OFFICES, FACILITIES, & UNDEVELOPED LAND ._ .................................................................. ..............................6 PARKS& TRAILS ........................................................................................................................... ..............................8 TRANSPORTATION FACILITIES (ROADS, BIKE LANES, SIDEWALKS, TRAILS) .............................. ..............................1 1 WATER..................................................................._.................................................................... .............................12 WinslowWater System........:... ...:........................................................................,................. ..................,..,.......13 SANITARYSEWAGE DISPOSAL ..................... .................................. ............ o..................... ......................................... 14 SURFACE & STORM WATER MANAGEMENT ................................................................................ .............................15 III. SIX -YEAR CAPITAL IMPROVEMENT PLAN ........„ .................................................... .............................17 APPENDICES: A. Bainbridge Island School District — 2013 -2019 Capital Facilities Plan C. Bainbridge Island Metropolitan Park and Recreation District CIP D. Bainbridge Island Fire District Financial Plan E. Kitsap County Sewer District 7 Response F. Kitsap Public Utility District Capital Improvements LIST OF TABLES TABLE 1: CITY LAND AND OFFICE FACILITY INVENTORY ...............................................,....,.............. ..............................6 TABLE 2: CITY PUBLIC WORKS FACILITIES INVENTORY ........ ......................................................................................... 7 TABLE 3: CITY UNDEVELOPED LAND INVENTORY _ .....................,..,...............................................,. .,.....,......................7 TABLE 4: PARK FACILITY LEVELS OF SERVICE ............................................................... .... ...... ....... , ...... ....,,...,.............. 8 TABLE5: PARKS & TRAILS INVENTORY ..........................................,...................................,.............. ..,.,..........,..............9 TABLE 6: TRANSPORTATION FACILITIES INVENTORY................ ...................................................... .............................12 TABLE 7: WATER SYSTEM LEVELS OF SERVICE ..............................................................,............... .........................,...12 TABLE8: GROUP A & B WATER SYSTEMS ................................. .. .............................................. ...., ....,............... ,........ 13 TABLE 9: WATERS SYSTEMS WITH OVER 100 CONNECTIONS ........................................................ ............................... 13 TABLE 10: WINSLOW WATER SYSTEM WELL INVENTORY ................... ....................... ................. ............................... 13 TABLE 11: WINSLOW SEWER FACILITY INVENTORY ............. ___ ................. ............................................................. 15 2 I. INTRODUCTION Capital Facilities Plans (CFPs) are required under State law to identify capital facility deficiencies needed to serve our existing population, plan for capital facility improvements to meet the needs of our future population, and ensure that local governments have the fiscal capacity to afford to construct and maintain those capital facilities. The 2014 CFP update includes an inventory of existing facilities, a 20 -year forecast of capital facility needs, and a 6- year Capital Improvement Plan (CIP) for the years 2014 -2019. The Capital Facilities Plan includes summary details of the major capital projects of the City and a financial capacity analysis. As the general purpose government on Bainbridge Island, the City is required to analyze and integrate the capital facilities plans from special purpose districts (Schools, Parks, Fire, etc) into its Capital Facilities Plan. The City and the special purpose districts continue to work together to integrate their capital planning efforts to provide a more even tax impact and to prioritize their projects while still providing quality facilities and services for the citizens they serve. This is consistent with Goal 6 of the Framework of the Comprehensive Plan: All government entities strive to cooperate and serve their constituents in a fiscally sound manner; and Policy CF]. 10 of the Capital Facilities Element: The City shall coordinate with other public entities which provide public services within the City to ensure that the Capital Facilities Plans of each of these entities are consistent with the City's Comprehensive Plan. This CFP update has been developed in accordance with the RCW 36.70A, the Growth Management Act (GMA), and WAC 365 -196, the Procedural Criteria. It begins with a short review of some of the concepts behind the Capital Facilities Plan. This Capital Facilities Plan is the product of many separate but coordinated planning documents and planning bodies. Each of the special districts (Schools, Parks, Fire, etc) has its own capital facilities plans, which are attached as appendices to this document. The City's Comprehensive Plan has various elements that relate land use and population growth management to water resources and transportation, which in turn have various adopted plans, including a Non - Motorized Transportation Plan, Water System Plan, a Sewer System Plan, a Storm and Surface Water Management Plan, and a Pavement Management System Plan — each providing an inventory of existing facilities, an analysis of deficiencies and future demand, and recommendation for capital improvements. Most facilities must be planned for years in advance, which means determining not only when a facility will be needed but how it will be financed. For facilities that are projected for four to six years in the future, capital costs are more estimates than actual. As the time for construction nears, actual costs are narrowed as design and engineering are completed. It is important to remember that capital facilities planning is not a once a year or once every two years effort, but an ongoing process requiring continual review as new information becomes available, conditions change, and priorities evolve. The GMA requires that the Capital Facilities Element contain a financing plan that identifies the type and location of expanded or new capital facilities and the sources of funding that will used to pay for them. There are two questions that must be satisfactorily answered: 1) What is the quantity of the public facilities that will be required during the six years? (identified in the inventory and needs analysis); 2) Is it financially feasible to provide the quantity of facilities that are required? (do we now, or will we, have the money to pay for them ?) Dependable revenue sources must be identified that equal or exceed the anticipated costs. If the costs exceed the revenue, the local government must reduce its level of service, reduce its costs (or increase revenue), or modify the land use element of its Comprehensive Plan to bring future development into balance with available or affordable facilities and services. This plan will examine each type of facility separately. The costs of all the facilities will then be added together in order to determine the financial feasibility of the plan. The Capital Facilities Plan is intended to be a planning document. It, therefore, does not contain the level of detail that the annual budget must contain. Some costs in the plan are estimated in order to give citizens a general idea of how much certain types of projects or facilities may cost. Relationship of Capital Facilities Plan to the Budget The Capital Facilities Plan and the City's budget serve different but related purposes. The budget authorizes the amount to be spent during the coming biennium; whereas the Capital Facilities Plan identifies needed capital facilities over a six year period. A requirement of the Capital Facilities Plan is that it show how the needed facilities will be paid for during at least a six -year period. Because State law requires that no money can be spent on capital projects which are not shown in the Capital Facilities Plan, it is important that the budget not authorize spending on capital facilities not in the Plan. What is a Capital Facility? Capital facilities are those public facilities, including utilities, which are necessary for a government to carry out its functions to provide services to its citizens. Examples are roads, public buildings, schools, parks, water and sewer systems, fire protection and police protection facilities, and libraries. Often the entire collection of these facilities is referred to as infrastructure. Studies or plans (e.g. transportation studies) are not capital facilities and are not included in the Capital Facilities Plan. There are several categories of capital projects and a key distinction is whether new or expanded facilities will serve existing residents or future population growth. Projects may also be proposed to maintain or repair existing capital facilities (cure deficiencies). The categories are as follows and will be used to identify specific projects proposed in the Plan: (M) Major maintenance, repair, renovation, or replacement of an existing facility that do not add additional capacity. (E) New facilities or improvements to existing facilities that provide added capacity to serve the existing population. (N) New facilities or improvements to existing facilities that are built primarily to provide added capacity to serve future population or employment growth. 4 How are Capital Facilily Proiects Identified? Capital facility projects are generally identified from a planning process for a particular type of facility (e.g. roads, sewer, water, schools, parks, etc) that includes an inventory of existing facilities, an analysis of existing and future demand for service, an analysis of existing or anticipated deficiencies in service (often based on adopted levels of service), and maintenance needs. This planning process is typically incorporated into a local government's Comprehensive Plan or a specific system plan which is then adopted as part of a Comprehensive Plan. Levels of Service (LOS) Levels of Service (LOS) are usually quantifiable measures of the amount and /or quality of public facilities or services that are provided to the community and are usually expressed as a ratio of amount of service to a selected demand unit. For example, sewer LOS is expressed as 100 gallon per capita per day, public school LOS may be expressed as the number of square feet available per student or as the number of students per classroom. Police or Fire protection may be expressed as the average response time for emergency calls. Parks LOS is often expressed as the number of acres of park per 1,000 population. Once the level of service is decided upon it can then be determined what capital improvements are necessary to 1) cure any existing deficiencies, and 2) maintain that level as the community grows. Prioritizing Capital Proiects Since it is unlikely that there is adequate money and resources to implement every capital project in a one -year period, the City goes through a process to prioritize capital projects. The City uses a combination of criteria to prioritize and rank projects that are proposed in a Six -Year Capital Improvement Project (CIP) list, including consistency with the City's Comprehensive Plan, level -of- service deficiency, financial capacity, budgetary policies, and community need. A recommended Capital Facilities Plan is presented to the City Council for consideration and adoption. Public outreach and participation is integrated throughout this process. 5 II. CAPITAL FACILITIES INVENTORY & PLANNING The following is the City's capital facilities inventory. The inventory is organized by category and includes a current inventory of facilities, a narrative providing a general background of the planning activities and some discussion of future plans, and a discussion of level of service (LOS), if applicable. Citv Offices, Facilities, & Undeveloped Land City offices are located at several sites due to space constraints at City Hall. Additional City buildings and facilities provide a variety of functions, including public works operations and house cultural and social services. In recent years, the City has also lead an extensive effort to purchase open space and agricultural lands throughout the Island with revenue generated from an $8 million bond approved by voters in 2001. Table 1: City Land and Office Facility Inventory Building and Location Land Area Building Area Owned or Leased Uses City Hall Administration, Finance, Planning, & Engineering - 280 Madison Ave. N 1.92 Ac 24,107 SaFt Owned Police Station Police - 625 Winslow Way E 0.82 Ac 7,000 S Ft Owned Municipal Court Municipal Court - 10255 NE Valley Rd. n/a 2,289 Sq.Ft Leased Subtotal Staff Office Space 2.74 Ac 33,396 SnFt Bainbridge Island Commons Social Services & Public Meetings - 223 B'une Ave. 0.38 Ac 4,975 SgFt Owned Under renovation in 2012 Bainbridge Performing Arts (land only) Land leased to BPA for $1 /yr through Mau. 2081 - 200 Madison Ave. N. 2.45 Ac n/a Owned Public Works Facility O &M Offices, Shop, and - 7305 NE Hidden Cove Road 12.62 Ac 22,712 SgFt Owned Covered Equipment Storage Public Works Facility Covered Storage - 7305 NE Hidden Cove Road Included 1,524 SgFt Owned Public Works Facility I Fueling Facility - 7305 NE Hidden Cove Road Included - n/a Owned Land with City -owned utilities 15.42 Ac n/a Owned Wells, pump stations, etc. Total 1 34.68 Ac 67,007 S Ft 6 Table 2: City Public Works Facilities Inventory Facility Floor Area Function Portable office trailers 2,520 SgFt * Storage, safety & future arks buildings Steel sho building 2,400 SgFt Storage - holds telemetry PW Facility - Wood Building 100 SgFt Well house PW Facility - Shop 7,776 SgFt * Mechanics Shop / Equipment Maintenance PW Facility - Covered Equipment Storage 11,520 SgFt * Covered Equipment Storage PW Facility - Office Trailer 1,792 SgFt * O & M Office Fueling Facility Transferring to Park District Johnson Farm Vehicle Fueling inside covered equipment storage building Ac Owned Agricultural/Open space Suyematsu Farm Total 26,108 S Ft Agricult ral land *These facilities are also counted in the main office inventory above. Table 3: City Undeveloped Land Inventory Location / Description Land Area Owned or Leased Uses Hi h School Rd. near Madison 1.42 Ac Owned Proposed surplus property Head of the Bav 30.77 Ac Owned Wellhead protection Lum kin Property 11.00 Ac Owned Transferring to Park District Suzuki Property 15.00 Ac Owned Potential sur lus property Salter Property 5.00 Ac Owned Transferring to Park District Johnson Farm 14.51 Ac Owned Agricultural/Open space Suyematsu Farm 15.00 Ac Owned Agricult ral land Lovgren Pit Property 17.00 Ac Owned Transferring to Park District Miller Road Property 2.00 Ac Owned Proposed surplus property Head of the Bay (Myer's Pit) Property 6.00 Ac Owned Proposed surplus property Vincent Road Landfill 34.15 Ac Owned Public Works Facility /open space Manitou Beach Property, less tidelands 1.36 Ac Owned Open space M & E Tree Farm 13.00 Ac Owned Open space /Agricultural Morales Propertv 4.74 1 Ac Owned Agricultural land Crawford Property 2.30 Ac Owned Agricultural land Ft. Ward Estates 1.61 Ac Owned Opens ace Lost Valley Trail 8.06 Ac + Owned Open space Blossom - Sullivan Road 3.32 Ac Owned Transferring_ to Park District Unocal Site 1.03 Ac Owned Park Strawberry Plant 4.20 Ac Owned Shoreline restoration and park Bentryn Property 11.50 Ac Owned Agricultural land Pritchard Park Phase II - East 27.18 Ac Owned Shoreline restoration and park Meigs Farm 24.85 Ac Owned Transferring to Park District Misc. unimproved land 2.24 Ac Owned No use specified Total 259.7 Ac Open Space & Future Park Land Included in Above: 152.54 Ac Parks & Trails Most of the parks and trails on Bainbridge Island are owned and managed by the Bainbridge Island Metropolitan Park and Recreation District, The City has a few parks which are generally maintained (with the exception of Waterfront Park) by the Park District under contract to the City. During the past several years, the City has acquired or helped the Park District acquire a large amount of open space and park lands. A number of these parcels are being transferred to the Park District based on Resolution No. 2011 -16. The City has adopted the Bainbridge Island Park and Recreation District Comprehensive Plan for 2008 to 2014, which establishes levels of service for park and recreation facilities for the Island as summarized below. Note on columns: NRPA is National Park & Recreation Association; RCO is Washington State Recreation & Conservation Office (formerly the Interagency for Outdoor Recreation); BI P& R is property and facilities owned by the Bainbridge Island Metropolitan Park and Recreation District; All is all properties and facilities on Bainbridge Island; Recommend is the recommended additional properties and facilities included in the plan. Table 4: Park Facility Levels of Service NPRA RCO BI P &R All Recmmd. Acres of Park Land Ratio per Thousand Population 1413 2506 310 34.45 62.5 110.9 95.48 Waterfront - Freshwater Ratio per Thousand Population 1 1 0 0.04 0.04 0.03 Waterfront - Saltwater Ratio per Thousand Population 15 20 0 0.66 0.88 0.68 Kayaking and Canoeing Launch Sites Ratio per Thousand Population 4 4 7 0.18 0.18 0.37 Boat ramps - saltwater Ratio per Thousand Population 1 2 0 1.77 0.04 0.09 0.17 Picnic Tables Ratio per Thousand Population 54 151 106 2.39 6.68 8.71 Picnic Shelters Ratio per Thousand Population 7 10 8 0.31 0.44 0.61 Multipurpose bike and hike trails (miles) Ratio per Thousand Population 18.7 20.6 20.7 0.50 0.13 0.83 0.91 1.40 Beach Trail (miles) Ratio per Thousand Population 1.5 2.6 20.7 0.07 0.12 0.79 Hiking trail (miles) Ratio per Thousand Population 28.5 34.7 28.1 0.50 0.14 1.26 1.54 2.13 Off -leach dog parks 1 1 4 Ratio per Thousand Population 0.04 0.04 0.17 Playgrounds Ratio per Thousand Population 8 15 10 0.53 0.35 0.67 0.85 Skateboard courts Ratio per Thousand Population 1 1 9 0.04 0.04 0.34 Outdoor Basketball Courts Ratio per Thousand Population 2.5 9.5 12.0 0.30 0.09 0.11 0.42 0.73 Tennis Courts Ratio per Thousand Population 5 16 6 0.50 0.22 0.22 0.71 0.75 Soccer Fields - Youth 3 7 0 Ratio per Thousand Population Owner Facilities 0.13 0.31 0.24 Soccer Fields - Adult Ratio per Thousand Population Meigs Park 2 4 0 0.10 0.29 0.09 0.18 0.14 Baseball /softball fields - youth Ratio per Thousand Population Horse & pedestrian trails 120.0 6 10 0 240.0 Gazzam Lake Preserve (Close, Peters and Veterane) 0.27 0.44 0.34 Baseball /softball fields - youth Ratio per Thousand Population Park District Fishing pond, trails, picnicking 5 6 0 0.40 0.49 0.22 0.26 0.2.0 Swimming Pool - sq feet Ratio per Thousand Population Ted Olson Park Park District 9400 16400 0 0.05 503 416 725 546 Sport courts, fields, play area, trails, horse arena, maintenance facility 45.0 Strawberry Hill Park Park District Sport courts, field sports, classrooms, skate park , picnicking, administrative offices 17.8 Indoor Recreation Centers (Gymnasium) sq ft Ratio per Thousand Population Park District Children's play structure 11000 70000 15000 Sport courts, play structure, covered picnic shelter, art center 6.7 487 3097 2881 Indoor Rec Centers (physical conditioning) Sq Feet Ratio per Thousand Population Hidden Cove Park Park District 11000 34200 2400 Park District Ballfields & children's' play structure 487 1513 1240 Teen Center - sq feet Ratio per Thousand Population 3000 3000 8000 133 133 373 Senior Center - sq feet Ratio per Thousand Population 4800 4800 12000 212 212 570 Golf Courses - holes Ratio per Thousand Population 0 27 0 0.13 0.43 1.19 0.92 Golf Driving Ranges Ratio per Thousand Population 0 2 0 0.09 0.07 Table 5: Parks & Trails Inventory Park Site Owner Facilities Size (Acres) Resoitre (`wiserrrrinj, Meigs Park Park District None as yet 67.0 W. Port Madison Preserve Park District Trails, picnic shelters, beach access 13.8 Manzanita Park Park District Horse & pedestrian trails 120.0 The Grand Forest Park District Horse & pedestrian trails 240.0 Gazzam Lake Preserve (Close, Peters and Veterane) Park District Horse & pedestrian trails Beach Access 444.6 Battle Point Park, North Park District Fishing pond, trails, picnicking 45.3 Rockaway Beach Parcels Park District None as yet - undesignated 0.5 Hawley Cove Park (Eagle Harbor) Park District None as yet - undesignated 11.7 Ted Olson Park Park District Trails 17.0 A1lrletic i'rtrksff'!rr + r0iinris Battle Point Park, South Park District Sport courts, fields, play area, trails, horse arena, maintenance facility 45.0 Strawberry Hill Park Park District Sport courts, field sports, classrooms, skate park , picnicking, administrative offices 17.8 Aaron Tot Park Park District Children's play structure 0.3 Eagledale Park Park District Sport courts, play structure, covered picnic shelter, art center 6.7 Gideon Park Park District Trail and playground 2.5 Hidden Cove Park Park District Ballfields and tails 7.8 Rotary Park Park District Ballfields & children's' play structure 9.8 Sands Road Park School District Ballfields 10.0 Resouree Aclivio- PaAs : ' Camp Yeomalt Park District Multi -use bldg, trail, picnicking 3.0 Waterfront Park City Park Boat launch, picnicking, tennis courts, playground 8.1 T'Chookwop Park Park District Picnicking 0.3 Fay Bainbridge Park Park District Picnicking, camping, boat launch, volleyball, sandy beach 16.8 Fort Ward Park Park District Boat launch, picnicking, trails, beach access 137.0 Hidden Cove Park (Spargur) Park District Shoreline and boat access - to be designed 6.1 Pritchard Park Park District & City Shoreline access, WWII Japanese - American Memorial 21.9 Blakely Harbor Park Park District Picnicking, hand -carry boat access, shoreline 39.0 Recreation C'ewers Island Center Park I Park District Community hall, picnicking 2.5 10 Linear Park / Trail: Fairy Dell Trail Park Park District Trail and beach access 2.5 South End Trails Park District Trails, easements, trail implementation 4 linear miles Forest to Sky Trails Park District Trails, easements, trail implementation 10.7 Special Use Facilify B. I. Aquatic Center Park District (leased) Aquatic Center 1.5 Point White Dock Park District Dock, fishing, clamming _ 0.3 Other - City Open Space City None - Designated for Open Space / Ag 163.72 Total (Acres) 1,470.72 Transportation Facilities Roads Bike Lanes Sidewalks Trails Of the many types of capital facilities that are constructed, operated and maintained by the City, the most costly and most familiar to citizens are the transportation facilities. Where there are facility needs that involve SR305 or the ferries, the Washington State Department of Transportation assumes the costs. Kitsap Transit pays for facilities that support transit service. The transportation system outside of historic Winslow has suffered from "deferred maintenance." The Pavement Management System (PMS) studies periodically conducted for the City indicated the wearing surface of many of the roads to be at or near failure, especially the smaller suburban roads. Since many of the Island's roads were initially only scraped and then a thin layer of asphalt applied, the maintenance performed by the City is usually more extensive, and costly, than normal maintenance of "paved" roads. Many roads, having no substantial base before placing asphalt, need considerable base preparation. The PMS study indicated a need for $600,000 per year for 10 -12 years in the annual roads maintenance and repaving program to maintain the roads at the then current status. The City Council recently committed to providing $600,000 per year for the next 6 years to address annual roads maintenance, and is in the process of identifying additional road reconstruction project needs and associated funds. A complete inventory of the Island's transportation facilities is contained in the Island -wide Transportation System Study and a complete inventory of the Island's non - motorized transportation facilities is contained in the Non - Motorized Transportation Plan. A summary of those facilities follows: Table 6: Transportation Facilities Inventory Type of Facility Description Example Length FRC 1 * State Hi hway SR305 6.8 miles FRC 2 * Secondary Arterial Miller Road 35.2 1 miles FRC 3 * Collectors Oddfellows Road 42.3 miles FRC 4 * Residential Urban Wood Avenue 21.7 miles FRC 5 * Residential Suburban S ar ur Loop Road 38.3 miles FRC 6 * Unimproved City Roads (gravel) Walden Lane 10.2 miles Subtotal 154.4 miles Without SR305 & gravelroads 137.5 miles Bike lanes ** Shared roadway on paved shoulders High School Road 23.5 miles Sidewalks Paved walkway Madison Ave. 7.6 miles Trails pedestrian, bike, equestrian, etc. The Grand Forest 6.9 miles *FRC = Functional Road Classification; Source: Public Works Department, Pavement Management Program (Klohn Leonoff) ** With the exception of SR305, bike lanes on Bainbridge Island are three to five foot paved shoulders. Bike lanes are reported in lane miles. SR305 is included here. Water Domestic drinking water is supplied by the City of Bainbridge Island, Kitsap County P.U.D. No. 1, South Bainbridge Water Company, numerous smaller public water systems (2 or more hookups), and over 1,000 private single - dwelling wells. The levels of service in the Water Element for water systems on Bainbridge Island are the minimum design standards and performance specifications provided in the 1992 Kitsap County Coordinated Water System Plan. Fire flow requirements were adopted by Ordinance No. 98 -30 and Resolution No. 98 -34 and are tiered based on zoning and type of construction. Residences can satisfy deficiencies by installing individual sprinkler systems. Levels of service are as follows: Table 7: Water System Levels of Service Pressure 30 psi residual Pi 2e sizing 8" diameter min. (where fires stem is required) Storage "Sizing Guidelines for Public Water Systems" Quality Federal and State minimum standards Fire Flow Residential Zone R.04 & R.1 = 500 gpm orsprinkler Fire Flow Residential Other Zones = 1,000 g2rn or sprinkler Fire Flow Commercial & LM = 1,000 gpin or don't build The Bremerton - Kitsap County Health District records indicate approximately 170 water systems on the Island that have 2 or more households connected. The number of Group A & B systems are listed below and following is a summary of systems with more than 100 connections. 12 Table 8: Group A & B Water Systems IrGroup A systems (15 or more connections) 44 FG-roup B systems (under 15 connections) 124 Table 9: Waters Systems with over 100 Connections (2005/2006) Most existing water systems were established under state and local guidelines and generally provide high quality water at an adequate pressure and flow rate for residential use. However, because of the number of systems on the Island, it must be concluded that there are systems that may not be in compliance with Department of Health water quality requirements and may not meet minimum requirements of pressure and reliability. It is also concluded that most of the smaller systems have poor or nonexistent fire protection designed into their systems due to the cost of providing large diameter pipes and storage tanks. Winslow Water System The Winslow Water System is owned and operated by the City of Bainbridge Island under the direction and control of the Department of Public Works. It serves an area similar to the historic Winslow city limits plus Fletcher Bay and Rockaway Beach. The system gets all of its water from the eleven wells owned by the City as noted below. Water is pumped into the distribution system both directly from the well pumps and by booster pump stations. A detailed inventory is provided in the Winslow Water System Plan, which was accepted by the City Council in 2007. The next update of this plan was scheduled for January of 2013. However, the Department of Health approved an extension to this deadline in 2013. Table 10: Winslow Water System Well Inventory Name Cap acity Capacity Storage System # Connections (ERU) (MGD) Volumes (gal.) 400,000 Island Utility 140 455 0.43 PUD #1 1688 2,028 0.36 860,000 Meadowmeer (MWSA) 279 283 .45 200,000 South Bainbridge 1,395 1,415 0.90 562,000 Winslow (City) 2,184 4,727 1.00 2,800,000 Total 3,791 6,540 2.43 3,597,000 Most existing water systems were established under state and local guidelines and generally provide high quality water at an adequate pressure and flow rate for residential use. However, because of the number of systems on the Island, it must be concluded that there are systems that may not be in compliance with Department of Health water quality requirements and may not meet minimum requirements of pressure and reliability. It is also concluded that most of the smaller systems have poor or nonexistent fire protection designed into their systems due to the cost of providing large diameter pipes and storage tanks. Winslow Water System The Winslow Water System is owned and operated by the City of Bainbridge Island under the direction and control of the Department of Public Works. It serves an area similar to the historic Winslow city limits plus Fletcher Bay and Rockaway Beach. The system gets all of its water from the eleven wells owned by the City as noted below. Water is pumped into the distribution system both directly from the well pumps and by booster pump stations. A detailed inventory is provided in the Winslow Water System Plan, which was accepted by the City Council in 2007. The next update of this plan was scheduled for January of 2013. However, the Department of Health approved an extension to this deadline in 2013. Table 10: Winslow Water System Well Inventory Name Cap acity D- th Present Yield Head of Bay #1 50 g m 135 ft. 32 gpT Head of Bay #IA 150 m 145 ft. 135 ypm Head of Bay #2 215 m 50 ft. 184 gpm Head of Bay 43 100 m 50 ft. 270 m Head of Bay #4 138 gprn 150 ft. 115 m Head of Bay #5 96 gpin 160 ft. 111 m Head of Bay #6 110 1 _g m 70 1 ft. 91 gpm 13 Lower Weaver * 80 _.g m 135 ft. 47 gpin Fletcher Bay 688 m 1,050 ft. 500 gpm Sands Ave. 41 288 gpin 1,055 ft. 365 gpin Sands Ave. #2 600 gpin 1,055 ft. 400 g m Commodore Well 100 gpm 190 ft. 47 gpm Taylor Avenue 80 g m 600 ft. 56 m Total 2,615 g m 2,297 g m *Not a potable source - used for construction Under Washington law, water purveyors, including the City, need water rights in order to be assured that it can continue to provide water. The City has "primary" water rights for 2,054 acre - feet per years and "allocated instantaneous capacity" for 3,037 gpm (about 60% over the City's present capacity). According to the existing Winslow Water System plan, the system's capacity is adequate to serve the needs of the potential build -out population under existing zoning and build -out to the highest density possible (to R -28) in the Land Use Element. The available sources are adequate to serve a potential population of approximately 7,900 or approximately 4,000 units. The system currently serves a population of 3,500 and approximately 3,500 residential equivalent units. There are, however, upgrades necessary to provide adequate fire flow in areas, more efficiently use existing storage capacity, rehabilitate existing wells, and improve system reliability. Sanitary Sewage Disposal The City of Bainbridge Island provides for the collection, treatment, and disposal of effluent in the Winslow service area. The Kitsap County Sewer District #7 treatment plant north of Fort Ward Park serving customers within the District's service area in Fort Ward and the City's sewer service areas in the Emerald Heights, Point White, North Pleasant Beach, and Rockaway Beach neighborhoods and Blakely School. All other residents not within the service areas of the above districts rely upon on -site septic systems that require approval from the Bremerton - Kitsap County Health District. Levels of service for wastewater treatment systems are typically expressed as the number of gallons of flow per capita per day and the level of treatment provided by the treatment plant. The current and proposed level of service for the Winslow service area follow the Department of Ecology guidelines of 100 gallons per capita per day (flow) and secondary treatment. In areas not served by treatment plants, on -site septic systems must be built to Bremerton - Kitsap County Health District standards that consider combinations of lot size, soil type, infiltration capacity, depth to hardpan, and proximity to surface water among others. The Winslow sanitary sewer system consists of two separate parts: the collection system, and the treatment plant. 14 Table 11: Winslow Sewer Facility Inventory Collection system 15 miles gravity sewer (pipes 8 inches to 12 inches diameter) 12 miles 2ressure sewer (pipes 4 inches to 12 inches diameter) 16 pumping stations (300 to 2,300 gallons per minute) Treatment plant Secondary treatment facility located on Donald Place NE (3.9 million gallon per day and 2642 ppd BOD) The existing system will be able to accommodate projected population growth in the Winslow area through approximately 2018 if maintenance and periodic facility upgrades are performed timely. The sewer system plan was last updated in 1994 and the City began working on the update to the General Sewer Plan in July, 2013. The City's goal is to have the updated General Sewer Plan finalized by June, 2015; the updated plan will document the existing system and needs for new facilities and replacement or upgrading existing facilities during the coming decade. The system plan or a separate study should be done to assess infiltration and inflow (I /1) in the collection system so that an I/I reduction program can be undertaken. All pumping stations are now connected to a Supervisory Control /Data Acquisition (SCADA) system that is operated by the City's utility operations team. The SCADA system allows monitoring and operation of pumping equipment and response to alarms from a central station located at the Winslow Wastewater Treatment Plant (WWTP). Additionally, all of the City's sewer pumping stations are now equipped with emergency generators so that operations continue during power interruptions. The existing WWTP was designed for a population equivalent of 10,000 and began operation in 1978. The WWTP will have an excess "population equivalent" capacity (including commercial and multi - family custotners converted to a level population equivalent) of approximately 1600 for flow and 4260 for BOD at the conclusion of the current improvements. The WWTP was upgraded in 1994 at a cost of $2.5 million. An engineering assessment in 2003 identified a number of additional upgrades necessary to meet regulatory requirements for effluent disinfection, energy efficiency and for process reliability and redundancy. Some of the identified upgrades (replacing effluent pumps and controls, and conversion from chlorine -based to ultraviolet -based disinfection) were designed and constructed between 2004 and 2007. Engineering and construction documents for the remaining upgrades to the WWTP process, including enhanced odor control, was completed in 2007 and construction in early 2008. This work was completed in 2011 at a cost of approximately $13.9 million, including engineering and construction management. An engineering study of the WWTP outfall to Puget Sound was completed in 2008. Planning and decisions regarding future modification of the outfall and related decisions regarding additional WWTP process enhancements, including upgrading the WWTP process to produce Class A effluent and biosolids for discharge or re -use, are proposed future activities. Surface & Storm Water Manal4ement In the Winslow urban area and a few smaller areas, stormwater is managed by a combination of piped collectors, roadside ditches and natural stream channels. All other watersheds and sub - basins on the Island are drained by natural streams and roadside ditches only. The existing natural drainage system consists of wetlands, streams, springs, ditches, and culverts crossing 15 roadways and is labor intensive to maintain. Surface and storm water is managed by the City as a utility. A recent Surface and Stormwater Management Plan and ongoing system evaluation are used to identify capital projects. In addition, the City places priority on the improvement and restoration of natural stream channels, particularly undersized or perched culverts, for the improvement of fish passage and fish habitat. 16 III. FINANCIAL CAPACITY ANALYSIS/ SIX -YEAR CAPITAL IMPROVEMENT PLAN Provided below is the Capital Improvement Plan (CIP) for the City of Bainbridge Island. This CIP list shows the anticipated expense and timing of each project and contains a project description, if available, and the results of the Comprehensive Plan consistency review and level of service (LOS) deficiency analysis. The CIP lists for the special districts on Bainbridge Island are provided in the appendices attached to this document. 2014-2019 Capital Improvement Project Plan List Proposed Draft as of November 25, 2013 F— LL Q �J c/1 J I..L W nE `W 0 Q E .a m U O N llzr r" i O N +1 7 O L- la L T mqr cu a c v = Z o a 3 E M v v a •- E cr 0' = w Q oG J c ro CL CL E c U c m � f0a+Z CL 3 CL O U a C N u c m p 3 o Q O 3 �' u E CU � .0 U C u of a ZUl C C c p 3 u a ++ � -0 u m W O U M 0 C a H v> E a a a in O Z a u o4 c a O C C -ap O 2 c a +� °,p }' aci l7� z F z �-0 g�► cu �v CL (D `v^ " _ _ E a a a w _ p O c CL UO +; c p ai 4 aa) ai O t7 v_ O t cu a +� = o C L 4 O C C v p +� a aj L L s N O m lJ N a a a to - a _ u 3 42 0 a c cu a m m z c E p c c O o c Z v v X O O O v r, > � a Ou C C O p o v m v ° c a E w aic ai v v c ro� n E E a �' v aui aui a v i o m e a u a p p Z Z Z O m S a a n > a > c O f9 v v °- a •� a d T .� a E E m N ��-mo-0 O o'ao 0 CL z W_ a Q ,� 4 u (U to a +, a Q a� O ry �> N Q 0 c a l ro iv c p ;+_1 > � a m c o Z a t' y V' _ E aEi p o - � +, + O io 2 Ln CL O a t C N J d C G ei N M +' o g ° a L o V a W Z +1 7 O L- la L T mqr cu a c v = Z o a 3 E M v v a •- E cr 0' = w Q oG J Section One 2014 — 2019 Capital Improvement Project Plan List Transportation — Tax Supported C c M O 0. A d qrn� c t E rd 0� 9U O O m IL m � N 9 r a Q N U a G C � O O u o a a cy Cc X H } r r c c c N N 9 m m m U) (n �V) (n U) J) L? — c a) m p L ❑ a ED d a 2 N� c � � c C a) y O LL a) 0 0 Eo aa)i M O O1 C a) E O a E `o c 0 m C CL ❑ o. ° ° c a° CL ❑ a o 21 m n X m � 'x n a) m C O L a) N y 'O '> m O L CL M..2 yN 'G O� m C 'U 'r N O d x O D O y O d o a m C fC fa E w � J !a C EL O w W C N c0 •y V1 c c +y r L � m 0 a aa) 0Ei N 2 `' 0 CL CL CL o IEE a c `o `o O N N E c A LL ro• O m z zz ? 2wz 06 _ ce <O c2 v u� co n oo rnN .-. V rn w 7 N N N O O O O O y C y c c O 'O O LO y) U l N N N N N N N N N 8 C'I N N m lu CD m O N r N N N v o r o r r rrrr 2 z z c c c N N 9 m m m U) (n �V) (n U) J) L? — c a) m p L ❑ a ED d a 2 N� c � � c C a) y O LL a) 0 0 Eo aa)i M O O1 C a) E O a E `o c 0 m C CL ❑ o. ° ° c a° CL ❑ a o 21 m n X m � 'x n a) m C O L a) N y 'O '> m O L CL M..2 yN 'G O� m C 'U 'r N O d x O D O y O d o a m C fC fa E w � J !a C EL O w W C N c0 •y V1 c c +y r L � m 0 a aa) 0Ei N 2 `' 0 CL CL CL o IEE a c `o `o O N N E c A LL ro• O m z zz ? 2wz m m Vl m m lu CD m O N r a1 � o N v ° Z E c c E m ro z z z z z o m O E m E �Z O O O O QJ I c� cn d m U � U E m O 75 76 O Y ° c c ° — fn (A fA (A (n (n > v m o C N 'c d d d L1 d U m 0 E y w C 0 t Ti 3 U U U U d ° t3 a) d O c c c c c dp > m U Cq c Mn ca LL Y ,� Y a) $ a� a a� 0 d a) m N 't U > amo °0m a a a n d w O w a EO c au)aa B � a L c 3: m U) fn r- c Y Y U> O a1 U) F- ii a W J O c c c N N 9 m m m U) (n �V) (n U) J) L? — c a) m p L ❑ a ED d a 2 N� c � � c C a) y O LL a) 0 0 Eo aa)i M O O1 C a) E O a E `o c 0 m C CL ❑ o. ° ° c a° CL ❑ a o 21 m n X m � 'x n a) m C O L a) N y 'O '> m O L CL M..2 yN 'G O� m C 'U 'r N O d x O D O y O d o a m C fC fa E w � J !a C EL O w W C N c0 •y V1 c c +y r L � m 0 a aa) 0Ei N 2 `' 0 CL CL CL o IEE a c `o `o O N N E c A LL ro• O m z zz ? 2wz m m m m m o I I r E m I I I U � U E O O O O O N L C O) O LL H > > > > > m 2 fn LL U) � a U) fn F- F- 0 N 'G m 2 c z d c O 2 m y N y c c c v o n m n oo a�i $ O 0 02 O c N O L O c N O O c N O O a N O O c N O O c N O a� 'O 7 2 a' E 1% ° U E a E m E m E m Z c� Z m 2 6 Lo m Z p7 CD '° Z 0 2> j w CA a) �' 0. O 01 Q) O w O N tm a> N O O c 6 C O C v a a a 2O a n` a a a > o T m c a d a❑ U a m _ a n m a :3 m _ = m m y 3 N ° o° M ° Q p 41 m I C: O c 0 C O O C O y LL Scc r M c c c N N 9 m m m U) (n �V) (n U) J) L? — c a) m p L ❑ a ED d a 2 N� c � � c C a) y O LL a) 0 0 Eo aa)i M O O1 C a) E O a E `o c 0 m C CL ❑ o. ° ° c a° CL ❑ a o 21 m n X m � 'x n a) m C O L a) N y 'O '> m O L CL M..2 yN 'G O� m C 'U 'r N O d x O D O y O d o a m C fC fa E w � J !a C EL O w W C N c0 •y V1 c c +y r L � m 0 a aa) 0Ei N 2 `' 0 CL CL CL o IEE a c `o `o O N N E c A LL ro• O m z zz ? 2wz O d It O CL Q N C K F- r C O r 222 2222w �� E 'y L) c fl a� a > > C ccfl O fC } C C C C Q) r- N X X X X 3L Q Q .0 X X X X X CD Or 0 (D d r (L Q N U a) U O) a) C N N z C CL a 0 E E > >c`o co c o a) aV >, o ro 5 cl CL ui vi E O y ��-0 w C � + U c° 1°� () O a) 0 0 d o c E E� os o o o 'Y' at a.!= U c o °° ui C E E o 2 0 a � `n �(D�' 4) 43) inv)I E o QQC� m — T — ro > 3 = o Q) Y o .2 3 tt-- ro O F- Cn m w LL a) q1 ro Q Q Q Q m m m Q m o F- F- F- F- 4 = 0 I I I I a) Y U a) C Cl) T •C >, O 7 7 7 O O O N 5 vOi F- U O 'C .� C Y Co O f6 7 ro Li j City of Bainbridge Island Transportation CIP (2014 - 2019) Amounts in thousands v v; E o 15 1 Q. j ,a a M Qi c E o U c LL c Q U 2020- Project Location M °' w 2014 2015 2016 1 2017 12018 1 2019 1 2033 i _ TRANSPORT Ttb+ PROJECTS 6 -YEnr CIP` I i I Annual Roads Preservation , Y 600 612 624 637 649 662 11,677 Transportation Benefit District Y 250 Fort Ward Hill Reconstruction Bolero to top of hill q 856 Y Y 952 _.,.... _..... Madison Avenue Overlay HS to Winslow Way J . 4 434 Y 505 I Valley Reconstruction Sunrise to Falk Y Y 83 _ Mountaln View Reconstruction Manitou to End Y Y 86 Wing Point Way Reconstruction Ferncliff to Park Y Y Y Y 38 176 Knetchel Way Madison to Ericks.en Y Y 100 Wyatt Way Reconstruction Madison to Lovell Y Y Y Y 250 100 100 2,066 Winslow Way Reconstr. -Ph 2 Madison to Grow I Y Y Y Y Y TBD TBD Sports - Club /N- Brooklyn llntersection Imprv. . Y 180 813 — _- Tf��N51?fi3RT,a "f14�P� PR3E&S 2Ci- YERIi "Cli? Annual Road Pres. Arterials &Collectors ! j .8,400_ _. TBD Annual Road Pres. Local Access Y j 1,400 Annual Roadside Safety Upgrades Y Annual Local Access Rd Reconstr. , Y Y 1,400 Roadway Reconstruction Projects Country Club Road Past Toe Jam to Seawall TBD Manitou Beach Stabilization Falk to Skiff 1,505 1,632 Old Mill Reconstruction Blakely to Blakely Hill Wyatt Way Reconstruction Ericksen - Madison TBD Blakely Hill Road Reconstr Halls Hill to t. op of hill _ - - - i m — — TBD - ........ Country Club Rd Stabilization Shoreline frontage TBD Halls HIII Road Reconstr —_ Blakely to top of hill _ - -� TBD _ _ Manitou Beach Stablization Murden Cove - Falk TBD Intersection Improvement Projects HS Rd /Sportsman Club Intersection Imprv, Y _ TBD TOTALS ... , . 2,614 1,042 �,7 3 737 2,715 662 26,015 Amounts in thousands City of Bainbridge Island — Capital Project Summary 2014 Annual Roads Program DESCRIPTION The Annual Roads Preservation Program consists of a combination of 1) grinding & patching roadways and /or 2) chip sealing. Grinding & patching the roadways is a maintenance operation and chip sealing adds a coating of asphalt oil and fine crushed rock overthe existing pavementto preserve the street surface and to keep the roads in good drivable condition. LOCATION 2014 Proposed Roads List has not yet been determined. POSSIBILITIES _- BENEFIT Preservation and prolonged life of the roadway system. SCHEDULE Annual, preferabl during warm weather construction season. CATEGORY Preservation 1A M;GC PROJECTCOSTS (a.,000's) 20-1 f zos 2oz61 20-71 2018 201c) Desi n/P ermlttln 9 in -house in- house in- house in- house" In -house in -house g_ _ � -- - - -- - - ROW , Construction 6o.o 612 6241 6 649! ! 662 Sub -total $6001 $61z $6241 $637, $649 $662 FUND SOURCES (1,000's) � Grant mm ! 6z4. 637 — -6-4-9 - 662 Street Fund 600 612 - — n Sub -total $6o0 $612 $624 $637 $64 $662 i City of Bainbridge Island Capital Project Summary Fort Ward Hill Reconstruction & Shoulder Widening Phase Z (Sunny Hill to Bolero Drive) -- 17 �:77�� - - 6t.�yKr -� Ott i s {'' n s •'lam F 7 � ° t: I 3 DESCRIPTION Reconstruction of approximately 1,50o LF of roadway. Improvements consist of repair & paving of two -1o'travel lanes with 5' paved shoulders, approximately loo LF of guardrail, new rockeries, new storm drain systems and two new drainage culvert replacements. BENEFIT Preservation, safety enhancement, & non - motorized level of service. SCHEDULE Design/permitting phases are estimated to be completed by 20-12 year -end with construction to occur in summer of 2014. CATEGORY Preservation, 1A, M GC [PROJECT COSTS (1,000,5) j 2a1L 2015 2016) 20171 2018 201 -_.. Design/permitting_ o ROW _ o Construction 9651 !. I Sub -total s965 $01 $al $0 $0 _$O' FUND SOURCES (1,000's) _! I ' Street Fund 96 SSWM Fund -1B l Grant 856 1 Sub -total sg6s $o; $o $o $o so City of Bainbridge Island — Capital Project Summary Madison Avenue Overlay (High School Road to Winslow Way) DESCRIPTION I The project will provide for pavement restoration of Madison Avenue, approximately o.6 miles, from north of Winslow Way to High School Road. Pavement restoration work may include pavement repair excavation, asphalt for pavement repair (including patching, full width traffic lane restoration, and overlay), and pavement marking. BENEFIT Preservation SCHEDULE CATEGORY Construct in Summer 201 M, GC, Tier 1(Preservation), Priority A PROJECT COSTS (i,000's) 2014 21 Design /Permitting o ROW 9 0 Construction o Sub -total $5051 FUND SOURCES (1,000's) Street Fund 71 SSWM Fund o Grant 4341 Sub -total 2o16 20171 2o18 20191 $o $o $ol $o, $o $o $01- - — $o $o - $o i- - - City of Bainbridge Island — Capital Project Summary Valley Road Reconstruction Project (From Sunrise to Falk) DESCRIPTION Provides for roadway surfacing reconstruction and storm drainage improvements on Valley, and storm drainage improvements to Logg, and Gertie Johnson Roads. This work was identified in the 2012 Area Drainage Study performed by Brown Wheeler Engineering. Note that the majority of the cost is related to stormwater improvements. BENEFIT Preserves surfacing on Valley Road. Addresses stormwater run -off on Valley Road and addresses maintenance problems with the existing storm drainage system at the bottom of Logg Road that have led to overtopping of the conveyance system. Better accommodates fronting pr,opeqy owner stormwater drainage above Gertie Johnson Road which has a history of slides. SCHEDULE ---Design in winter / spring of 2014 and Construction in fall of 20:1 CATEGORY M, GC, Tier 1 (Preservation), Priority A PROJECTCOSTS (1,000's) Desicgn /permitting ROW Construction Sub -total - - -_ -- FUND SOURCES (i,000's) Street Fund SSWM Fund Grant Sub -total 2014! 20-15 2016 201 20181 201 59 0 144 J $203_1-- $O $ol $o $O $O i 8-311 I 120 _ _ — o� J $2031 $0 $01 $0 $o $o -1 - City of Bainbridge Island — Capital Project Summary Mountain View Road Reconstruction Project (From Manitou) 'T .IN DESCRIPTION Provides for roadway surfacing reconstruction and storm drainage improvements on Mountain View. Work includes upgrading the inlet condition at the outfall to address a capacity deficiency. This work was identified in the 2012 Area Drainage Study performed by Brown Wheeler Engineering. Note that a significant portion of the work is associated with stormwater improvements. BENEFIT Provides for surfacing repairs. Currently the roadway lacks conveyances for stormwater. The project provides for conveying storm water and improves the capacity of the existing outfall. Providing conveyances better accommodates fronting property owner stormwater drainage above Gertie Johnson Road and Rolling Bay Walk which has a history of slides. SCHEDULE Design in winter / sprin2 of 2014 and Construction in fall of 2014. CATEGORY NI /E, GC, Tier 1f Priority A PROJECTCOSTS (1,000,5) 1� 20142011 2016 2017 2018 201 Design /permitting 32 ROW o Construction 1.071 Sub -total $1391 01 01 „ °, _ __O FUND SOURCES {z,o[rm`s) -------- 1 Street Fund SSW_ M Fund 531 Grant o Sub -total $1 91- - - - °. ° .__ _.0: - -- 0 ° City of Bainbridge Island — Capital Project Summary Wing PointWayReconstruction (From FerndifF to Park) i• it h DESCRIPTION Reconstruct roadway surfacing and drainage. Provide sidewalk, on the downhill side, and shoulders, on the u hill side. Water and sewer utility rears maybe added. BENEFIT Preservation, safety enhancement, & non- motorized level of service. SCHEDULE The City received grant funding for the design phase in the summer of 2013. The City contracted with HDR. Design is starting in late 2013 and will continue with permitting, easement procurement in 2014. The City plans to submit for additional grant funding in 2014 for the construction phase. CATEGORY M /E, GC, Tier 1(Current Deficiency), Priority A. PROJECTCOSTS (i,000's) r 201 2o1 2o16 µ2o1 ; 2o18, 2019 Design /permitting 456 ROW o zoo Construction o 1 $1001 $1,614 $0 $01 $o Sub -total $456 FUND SOURCES (a.,000's) Street Fund 12 zoo 283 SSWM Fund I TBDI ? _ zo Water TBD Sewer 1S TBD 3031 Grant $456 $zoo $1,614 $o $o $0 Sub -total City of Bainbridge Island — Capital Project Summary Knetchel Way Surfacing and Drainage Repairs Special Project (From Madison to Ericksen) DESCRIPTION This local access roadway is in poor condition. Proposed work includes approximately 28o feet of curb and gutter infill and associated catch basins and tight line drainage improvements. Also included is the installation of anew catch basin and drainpipe at a flatter area. Surfacing repairs include extensive patching and thin asphalt overlay. An estimate has not been completed but the construction cost is thought to be on the order of $100K. Sidewalk inf ill maybe added for an additional $20K. The design would be completed in house. Thin asphalt overlays are relatively new to the local industry and this could be a pilot project for the City. Thin overlays maybe preferred to chip seals for low volume curb and gutter streets in urban zoned areas. BENEFIT Preservation SCHEDULE Desi n and Construction in one year. CATEGORY M /E, GC, Tier i(Current Deficiency), Priority A. PROJECT COSTS (i,000's) 2014 201 2o16 20171 2o18 201 Design/permitting— — _ _ -__ .0._ ROW o Construction 120 Sub -total $zzo FUND SOURCES (i,000,$) _ _ v 0 0 0 0 0 Street Fund Storm Drain Fund Water Sewer STP Grant Sub -total 100 20 i $zzo 0 0 0 01 0 z 0 NH 1.6 00 aW U) F Z �o �a a. 0 � N Cl) X 0 ~ C0 G z 0 z C C ro O d� w w w w w w ui z wwwwww w w oaf O a H �cpp E c °00 a 0 N Q f7 ypv 5 j > > j v v �t v LO to LO N CO v) a� Q Q Q Q Q N N N N N N N N N N Q rn �i } z IL Q N �? c a) c 0 Z E c c a o Ad c c c c c c ±? v c o E c ; 0 c v E ° v v v 'o 0 a E J CD a) C m ro ro ro ro ro y O O L a� n aC O c a 0. 0. n n n N v L CO E E� ooad Y E CL CD v v v v v o m v ro v a ° ° 0 > O > 0 a O > 0 > 0 E c ro 0. ��? � aa) 0 0 O o 0 0 d a t co L V) L U) t U) t U) L V) O Z a) (n L O L L ;� U) U) to V) Vi m O c w CL ,O U N oCL CL „y°, N N ,N �W� V m 0 0 w- 0 C L m 0 a� O N a) Cm "O �O n� w U) E2 O L O � U,g 5 A T a F U) s m ELM W(Dxa20U a . �,U 0 a . CC >+ O1 ° E CD T C C C .X n ITO fT0 o O v m Co mY C D Q 0 c c E c m m a9 o 2 9 000 c m m LL � 1i5Fn20z9a� H W �y U> cn to V) cn U) 10 U) en U) 0 0 U) 8 L g) a� o n .� •� a U) U) (n cn U) cn cn rn w 0 0 cn w w U) a Tu w w ° c C N ,V a)) U L) .271 aa)) LO G o 0 N p C Y+N •O N r a) �' ti y a) d a) N r N E t N; m�p N a a) a) 0 .� �O �t1�i a a 0 2` N ro t L t� E E N LO rn fD N ~ N a0 u! O) N a) C n N a C O -6 N a) O �1 N a) C. N 0 O 1 N 0 O N N O '6 N a) '> D N U O E f0 a) T s., Z` � ca 0 fa L ,�' ro O a) 0 0 O O O O O O a p_ •E T O m ro a y) o- C C J d IL 2a Ta 12 a- ma ma C. E E ° ago° =" 7 . a ro_ - 0. go 0) z 0 0 m •• 0° 0) w 0 0 m .� 0 o n a)- O 0 a ?, O a� O Y c3 ro ak rn LL U m m i- u a a� a a` 0) a a cn a a U) a cn a cn D o ° cn o ro L anZZ L Ww w ¢ 3 3 ,d W is 70 00 m 00 �o , 70 t0 00 00 ,n ; cO c C m �" Z �zZ i .X�+00�t0s�0r� N a w•L� ¢3 �C� ¢� cn U)U7U5C UUCJ U w x Z _O N� Li Op aW ui Z g 0 F- a D� N xN 0 O 2 Z Z C C O O a� wwwwwwwwwww a E .y U o v d 0 x x x x x x K x.x x x CL o � _ � a > o CA N E o � a T o 13 c a a 04 E 0 0 c 0 as a CL � 0 o a 0 (n U) O +� w.y. V C • _ [2 a a� a� w 0 0 ¢ F-CD EEEEEEEE 7 J G a) cc000 c rn°�o0CM0000o cu .9 0 E E E E E E E v c O a .0 J— LA a) V N Y Y Y Y (p ) j 0 u •E Q) V Q � >> V_ X 3 3 3 3 �� a w OY_ 0 Ttv gvv C] amc>cn(nF- cn(ncncntn oy 4) 0'a h b N cu ao o p c E= cc- a w0 Y O p CL u O C 0m °'0 E F- V1m >a � C � ,C i � a > > O O O U N � Lo 75 -0 O O O� O O_ a5 E (n =r- L 0 0 C_ U .+w.. LL M O C� Q Z:mU)c02UZ�� W W CD E cn N 8 fncncncovJCncnU)cncncn .2? .� N•-•? V F- F- F- F- F- F- F- f- F- F- F- w w0� of 2 xcr- w w wQ� 2 C V)U)wU)� w w O Li (~nc~cco(nnc~U) C X x N O a) .22 N N yam, n t°n a> c E E E E c0 O L N F— i Ll O O c9 CL CL Q (n c U a c Y c '- aD LO C U c a� 3 m aci toi cn cn 'D •cu Z O -gyp 3 tf >, aa> E 3r, � v v M- U L> m ca c 0 a) �o a)� g g EFn2 c ' pZZ w D 3 3 0000o U) 0 _ co , 1 N fnUUUUJULi WZ City of Bainbridge Island Non - Motorized Transportation CIP (2014 - 2019) Project Location m Q Q Q LL CC G E E t% 2074 2015. 2016 2017 2020- 2018 2019 ] 2033 NON- MOTORIZED PROJECTS - 6 YEAR CIP SR305 /Olympic Drive NM Design & ROW Construction Sound to Olympic Trail Phase 2 Winslow Way to Harbor Dr Winslow Way to HS Road a J 734 Y 363 Y 303 .' Y Y Y 90 644 420 1,450'_ Y Y Y 388 100 1,438 124 25 25 25 8 TBD TBD TBD J Wing Point Way Non Motorized * *SR305 Shoulder Improvements Connecting Paths Hyla Easement Sportsman Club Spine Trail Ferncliffto Park Vineyard - High School Road TBD Bucklin Hill Rd Blind Curve `HS to Sportsman pond u - 375 _ Lost Valley Carmella Lane Lost Valley (construct Appjy for Rec. Trails Grant 2014 Lost Valley (construct Cave to Sound to Olympics Construct _ TBD TBD Wallace Way to Madison Central Connecting Path Spine Central Connecting Path Spine Wardward School C40 - Spot Projects Wyatt Way Bike Lanes Eagle Harbor Phase 1 North of Island Rehabilitation Co. Rd along SR3051 Wardwell Koura TBD TBD Co. Rd along SR305 / Koura - Lovgren- missing path TBD Weaver - Finch (restripe) McDonald curve TBD TBD TBD TBD Finch to Sportsman Fletcher Bay to Lynwood Center blind curve near Island Cntr Hall C40 - Blakely Bucklin - Baker Hill Climbing Lane Y Top 5 Road Safety Projects.by NMTC _ ; - -- _ . -- , * *C40 Miller Road Tolo to Pederson Hill _ Y 50 * *C40 - Bucklin Phase 2 Blakely - Fletcher Bay Y Bucklin Pase 2 ROW Acquisition _ TBD Bucklin Pase 2 ROW Acquisition + Design — TBD Bucklin Pase 2 Design + Construct * *C40 - Eagle Harbor - Phase 2 (combine Wyatt - Pst Bucklin Head of Bay Y C40 - Eagle Harbor - Phase 1 (combine Pst Bucklin- Wyatt Head of Bay Y * *C40 - Fletcher Bay Roadl New Brooklyn to HS Rd Y 408 Ojj�¢r Non-Motorized Projects C40 - Lynwood Center (note changed yeah Bucklin - Pt. White Y Wyatt Way NM - Phase 1 Madison to Lovell Y 200 Wyatt NM - Phase 2 Ericksen - Madison Y I TBD Wyatt Sidewalk Extension E of Weaver - Weaver Y TBD �4. Sound to Olympic (STO) Trail - Phase 2+ Various TBD Sound to Olympics Under Pass STO to HS (Engineer + Construct) _ ? _ C40 - Blakely Bucklin - Baker Hill Separated Pth Y C40 - Valley N. Madison - Sunrise I Y Grow Ave NM Winslow Way - Wyatt Traffic Calming Y TBD Knetchel Way Ericksen - Madison Y TBD Lost Valley Trail - Phase 1 Carmella Lane Y Winslow Way Reconstr.- Phase 2 Madison to Grow _ Y 750 _Madison Avenue Sidewalks / Cross Walk Combine with Madison Reconstr. TOTALS . 1,741 3,033 TBD TBD TBD 882 TBD TBD TBD 700 505 _ — — TBD TBD TBD 2,395 580 775 75 1,125 Amounts In thousands City of Bainbridge Island — Capital Project Summary SR305 - Olympic Drive Non - Motorized Improvement Project Winslow Way to Harbor Drive DESCRIPTION Olympic Drive is a roadway with inadequate pedestrian and bicycle accommodations. This project provides improvements for pedestrian and cyclists along this heavily trafficked roadway. BENEFIT Non motorized level of service improvement, safety enhancement SCHEDULE Design in late 20-13 and early 2014. Construction in 2014. CATEGORY I Deficiencv 1B, E; SC PROJECTCOST_S (s000's) Design / Permittinq ROW Construction Sub-total FUND SOURCES (s000's) Street Fund Grant Sub -total 2014}1_ q0 2015 - 2o16 20171 2-oi 2019 - 644 - - - - -- -- $o $o $o i $o $734 $o $o- $o— $0 $o City of Bainbridge Island — Capital Pro'ect Summary Sound to Olympics Trail, Phase 2 Winslow Way to High School Road '7' : _.I �6_ f, I I. DESCRIPTION Design of Sound to Olympic trail and study of branch trails. Construction of separated pathway from Winslow Way to the existinq Ravine Creek non motorized bridge, BENEFIT Non motorized level of service improvement, safety enhancement SCHEDULE Design in 2014 and construction in 2015 CATEGORY E /N, SC, Tier3, Priority C PROJECT COSTS (z,000s) 2014 2015 2016 201 2018 201q Design /permitting 420 ROW — Construction 0 $o $0 Sub -total o�1 T FUND SOURCES (s,00es) Street Fund _ Grant # 363 1,254 Sub -total $420 $1,450 $0 $o $o $o City of Bainbridge Island — Capital Project Summary Wing PointWayReconstruction From FerndifF to Park) A - r +I .,; DESCRIPTION Reconstruct roadway surfacing and drainage. Provide sidewalk, on the downhill side, and shoulders, on the uphill side. Water and sewer utility repairs maybe added. BENEFIT Preservation, safety enhancement, & non - motorized level of service. SCHEDULE The City received grant funding for the design phase in the summer of 2013. The City contracted with HDR. Design is starting in late 2013 and will continue with permitting, easement procurement in 2014. The City plans to submit for additional grant funding in 2014 for the construction phase. CATEGORY M /E, GC, Tier 1(Current Deficiency), Priority A. PROJECTCOSTS (1,000'11 2014 20151 2os6 2017 20181 2019 Desiqn /permittinq 456 ROW 0 loo Construction o 153. Sub -total $4,6_ . slao $11614 $ol_ $o' $o FUND SOURCES Street Fund 123 ._ _ 100 — _ 283 SSWM Fund 5 TBD Water to TBD Sewer 15 TBD Grant 30.3 $100 $1,614 $o $o so Sub -total $456 City of Bainbridge Island Capital Project Summary SR305 Shoulder Improvement Project Vineyard to North H ',� ' DESCRIPTION This project addresses existing gap in shoulders on the East side of SR305 north of Vineyard Lane. Other work includes modification to an existing traffic island. - - - --W............. __ -- BENEFIT Non motorized connectivity, Safety enhancement. SCHEDULE Design and construct in 2014. CATEGORY Deficiency 1B, E /M; SC 1PROJECTCOSTS (z,000's) 201 201 2o16 2017 2018 201 Design /permitting 21 - ROW ° f - - - — - — - - - -.. _. Construction 10 Sub -total $1241 $o $o $o $-01 $o (FUND SOURCES (i,000's) IStreet Fund mm 1.241 0 Grant Sub -total $1241 $o $o $o $off $o i City of Bainbridge Island — Capital Project Summary Connecting Pathways Various locations) DESCRIPTION Annual funding to address trail opportunities such as easements and construction. Potential projects include Bucklin Hill trail near Hyla School, Sportsman's Club Spine Trail (near Sportsman's Club), Sportsman's Club Spine Trail (north of Sakai School), Lost Valley starting at Carmela and on City parcel, Cave connectorto STO trail, Woodward School (Sportsman's to Wardwell) and Central Connecting Path Spine Trail (Wardwell to Koura) _.� -.�. BENEFIT Safety and Non Motorized Transportation Connectivity: -- - - -- .. ............. - SCHEDULE As opportunities arise - ._.- _ ....... .. CATEGORY E, SC, Tierl Priority C PROJECT COSTS (s,000's) 2014, Zo15 _ 2016 2017 2o181 Zos. Design /permitting o 'ROW 0 I Construction 2S- Sub-total $25 o - 01 o' 01 o FUND SOURCES (s,000's) I Street Fund 25 'Storm Drain Fund o� STP Grant oI Sub -total $251 0 of o 0 0 City of Bainbridge Island — Capital Project Summary C40 - Annual Spot Projects (Various locations) 1 i = k t. r'T- J3,Crta'Y��• �tlt x t� � �� �. 'i� -�. - <�k .�,. —.. _,re� {. t 0 Is T r� f.l i,i ..�. �ch lj'7 � t;sy .� 1 _ -. ,!. ..• s 3 ,_ Yi Ft t d a•a r� } L r aS: t Ss i =F DESCRIPTION Add on to the Annual Roads Preservation Program to fund shoulder repairs and infill missing short segments. Potential projects include Wyatt (Weaver to Finch), Eagle Harbor (blind curve near McDonald), Finch (Wyatt to Sportsman's), and Fletcher Bay (blind curve near Island Center Hall), BENEFIT Safety and Non Motorized Transportation Connectivity. SCHEDULE Constructed annual l . CATEGORY E, SC, Tier3, Priority C PROJECT COSTS (i,000's) 2014 2015 2016 2017 2018 2019 Design/ permitting o - ROW 0 Construction 50 Sub -total $50 01 0 0 FUND SOURCES (s,000's) W _01 0 Street Fund so Storm Drain Fund 0 STP Grant o Sub -total $50 0 0 0 0 0 Section Three 2014 — 2019 Capital Improvement Project Plan list Facilities — Tax Supported C C M O FL Oof U ° y v v v v v u) )n u) (o n co co co 0) 0) rn M a 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 m m m m m m m m �" � � "' � O 0 A N N N N N N N N N N N N N N N N N � d F- ( CD Q N U " L C O U O V " O a) 0 0 1 r_ E > c o CL > " rn a E C (0 E (U C N C m O Mn aci Y 2) N `� E c W a) C T 0) C 0 > a) E O N a) a) a) N " 0) T C ro C N" ro N T V N U T U p) U E c d O " ro E 0 .te Ea E v 8' C �i v �) C cTi a) c " a) yN, OL ° o a) a) °�' ro w a) a a) 8 c u 0 T en 0 C a) w V-- C w w- 4-- C w C W C 'L-' 0 " f° ro ro o o o o o c o ro ro o o> v c W a.g N Y c s c m a . CO a � � 0 o m� a iv ro in o M- rn rn " a a c "� � M a) O'o MU'c N a" " w T w- tn "" V w" E Y— ++ D) 41 O Q 7 C O I— 0. e a m C E E E E E rn E T�0 q)) CCD rnC cc�',E2 "n e o'o J_ a 2" >> c ro > >> n m m" "E c o - c 3 o c 8 aao E nna0 E a Z a? y" a ,oa) N a V N p o ro Z m iv c co 6 is E m E o 0 0 m m' o o axi LL C ro 0 O -a .0 L L M L L L N L j L L a" 0 d L o M a) i< N N 7 v m w v N O O E W ;" V N U O C '" '� > u a aoi ani aai o y a) " a) Q) ro a) a) a) 7 ro 0 a N a) O ro ro ro a � N LL U aLL0.w�co�� °'> o v o a o .� a 1- Z O H M ��ro ro ro m ro ro ro c a a,a a n. as oo N�a O C O C C ro O O ro ro N N O ro ro ro O fC O` N ro ro C N N O ) O a U U U (S U 8 CS a a U a0U M0SL) U V z z z z z z z z z z z z z z z z z zzzzzzzz 8 gty w w w lu w w w w w w w w w w w w w wwwwwwww ro__ ci C7 C7 C7 C� (7 C� C7 C� C7 C� C� C� C7 C7 C7 C7 C7 C7 C7 (7 C� C7 C7 C� (7 n O C C CO ,U) V) ro N a) Q) a) a) a) a) C 0 C ;2 0) >0 .22 N c o w m m m E m E o y w c �' O cn ' ac) a) -B ti a s a s a.-) i; a ro Q) D� ro E M D ZD G ro () a) a> v w N a N N oy c c a.ac��a c�.n.a.a° aai a m m mro "0moOD �o� ° c U v Q O1 ro v v Q 0 0 rn rn 15 m o m m C.Q. �� m oww� an,LULUw� Ww �D� _�cg�yaUaa �•EE E E E E o) E E E a E E a a) rn roc E ro� °)�� ro o `o Y O 0) C N V) C U) N " '7 " L L E a) c c L N ++ +) m T T O >. >T >. E O' >. E ui > N a) ro CO C. ro a C (� 0 fn .SP a !n fn (n d LLJ U) 0 .� 0) d C " O '0 E > Ip 0 a E m T V U J v U U U ".0 U" J J u° a _m •a v o o .0 0 F' U o c `-M° > >U :3 C/) >> 0UU �(naE €lL�(n(n 033 d y (D 0 v a) )n ut °T) m � oo .S T rn 'E- rn 0) } ._ -< Q >- ro o a) E o 0 o ro 0 0 0 0 ro o 0 0 0 o o m m 0 U U a tD [If a W N N N a N N N LL a N LL N N NaLL LL- UODU)0 W z City of Bainbridge Island Facilities CIP (2014 - 2019) Q) M � v Q Q LL I Waterfront Park City Dock Impr. C City Park Design _ _ _ _ _moo Construction 1 166.( Road End Improvements 1 1 Island Wide _ 150 Pedestrian Bridge Reconstruction W Waterfront Park Trail 6 _ 1 6.o Emergency Generator Connection C City Hall z z HVAC System Equip. Upgrade C City Hall I HVAC System, Equip. Upgrade C I H Amounts in thousands I 1 1 2020 - 2016 2017 2018 zosg 1 2033 Il 81 42 _ 43 14 75 - 6 60 i TBD TBD TBD TBD TBD TBD TBD TBD 74 155_ TBD City of Bainbridge Island — Capital Project Summary Waterfront Park and City Dock Replacement Project DESCRIPTION This project provides for renovations and repairs to the City Dock and elements of the Waterfront Park. !BENEFIT Maintain utility of public infrastructure associated with the City parka nd the City dock. Ensure user safety is maintained. Enhance accessibility and utility for various user rou s, SCHEDULE Design beginning in 20-13; additional deli n and construction to continue in 2014. CATEGORY _. !PROJECTCOSTS ti,00r's }. 201 I 201 2o16l 2027 2018 2os Design /permitting ! 190 I ROW Construction 2,66o _ Sub -total $1,850 $0 $0 $01 $o $o FUND SOURCES (1,000'x) General Fund 1,85o I Grant i Sub -total $1,85oj 0 01 0 0i City of Bainbridge Island — Capital Project Summary City Road Ends Improvement Projects DESCRIPTION This project provides for infrastructure enhancement and other projects at various City road ends. _ - BENEFIT Expand and maintain utility of a variety of road end locations, some of which provide public access to waterfront. Ensure user safety is maintained. Enhance accessibility and utility for various user groups. SCHEDULE Design and construction in 2014, CATEGORY _ PROJECT COSTS 2015 2o16 2o1ZJ_ 2o18 , 20-1 Design /permitting I ROW Construction ' Sub -total $150 $o $o $ol $o, $o FUND SOURCES (i,000's) General Fund Grant Sub -total $150 $o $o $o $o $o City of Bainbridge Island — Capital Project Summary Pedestrian Bridge Reconstruction Waterfront Park Trail Shannon Drive to Harborview Drive DESCRIPTION This Waterfront Park trail pedestrian bridge project is basea on an assessment repon: or ine bridge prepared by KPFF Consulting Engineers. The bridge is over 40 years old and is in need of upgrades to preserve the structure. The project consists of preservation activities not covered under the pending emergency pile replacement project. The project will include deck replacement and painting. Because of the sensitive environmental location the work site will be contained from the environment during painting activities. BENEFIT Infrastructure preservation andpublic safety imprc�ver� rent. SCHEDULE Construct 203.4 CATEGORY M, GC, Tier 1, Priority A PROJECT COSTS (i,000,$) y 2014 2015 2o161 201 I 2018, 2019 Design /permitting I o IROW 0 ,Construction 6o Sub -total $60 _ $o $01 $01 $03 $o FUND SOURCES (1,000's) -_ General Fund 6o i o 4 0 Sub -total $6o $0 $ol. sol $o $o City of Bainbridge Island — Capital Project Summary KOPUR r- •- ••- .- . -_-,•° ^ice; ice^'.. ^�'��,•� {�� e i e Emergency Generator Connection Project City Hall 280 Madison Avenue DESCRIPTION The City Hall emergency generator is sized to provide limited power to critical systems during an electrical power outage. Critical systems served include the information technology computer infrastructure, emergency exit lights, and select building lighting. The emergency generator connection project will provide a receptacle and associated electrical equipment to allow the use of a mobile generatorto supply powerto these systems in case the main generator fails or is in the midst of maintenance dur, inq an unscheduled power outage. BENEFIT Emergency systems reliability and redundancv improvement. SCHEDULE CATEGORY Construct 20 Tier 2, Priority A PROJ ECT COSTS Design /permitting ROW Construction Sub -total 0's) 201 201 51 2016 20171 2o18 0 0 !FUND SOURCES (z,000's) General Fund Sub -total 20 -$O - - °l - $ol $_01- $o 0 0 - $13 $o $o $o $o $o r _ DESCRIPTION The City Hall emergency generator is sized to provide limited power to critical systems during an electrical power outage. Critical systems served include the information technology computer infrastructure, emergency exit lights, and select building lighting. The emergency generator connection project will provide a receptacle and associated electrical equipment to allow the use of a mobile generatorto supply powerto these systems in case the main generator fails or is in the midst of maintenance dur, inq an unscheduled power outage. BENEFIT Emergency systems reliability and redundancv improvement. SCHEDULE CATEGORY Construct 20 Tier 2, Priority A PROJ ECT COSTS Design /permitting ROW Construction Sub -total 0's) 201 201 51 2016 20171 2o18 0 0 !FUND SOURCES (z,000's) General Fund Sub -total 20 -$O - - °l - $ol $_01- $o 0 0 - $13 $o $o $o $o $o City of Bainbridge Island — Capital Project Summary HVAC System Equipment Upgrade City Hall 280 Madison Avenue DESCRIPTION BENEFIT SCHEDULE CATEGORY The City Hall HVAC system upgrade project is based on the recommendation of the city's current HVAC service provider, Air Management Systems Inc. The City Hall is served by 21 individual heat pumps. The heat pumps are currently 13 years old and have an estimated life expectancy of 12 — i5 years. The heat pump that serves the Information Technology room will be replaced in 2013. The City Hall HVAC system upgrade project will replace 4 heat pumps each year from 203.4 through 2o18. This project will insure systems reliability and avoid costly unscheduled failures. Systems reliability. Construct 203.4, 203.5, 2o16, -2017, 2o3.8 M, GC, Tier 2, Priority B PROJECT COSTS (i,000's) 2014 2015 2o161 20171 2018 2019= Design /,permitting o ROW _ o Construction 1 411 21 431 If It Sub -total $40 $411 $42 $43 $441 $a I FUND SOURCES (General Fund 40 41 42 ... _ 431 44 ii I o� _ - Sub -total i._ $401 __$_4_11_ .__ $42 _.$43 $44 of Section Four 2014 — 2019 Capital Improvement Project Plan List Fleet and Equipment — Tax and Utility Supported 0 W Z wa CL a o. 0 W � J_ a ~ H W Z LLJ LLJ. Q X H c C M O 0. ro . c a _m 8 42 C E E 0 U nFL v G � a } w o w Q N U L 3 0 0 a •c 0 v LL a w w w w w W w w w w w w w w w w w w w w w w w w iu w w w w a CJ d r 12 61 o 12 A A a� E E Yv L E E a, w Y •E ; Y E 5, p Y E t E o c o � s d a:2 v v a N m; YC .�- E pCj e N N j �O � E a a a a u o. a n a s CL � of o. � x ix O x x O V- x wa a: s •- Fo- a v v v v v v n �n (n u2 (o w m (o n n n n o0 0o ao ao 0o m rn n m m m w°�-• £ 0 0 0 0 0 0 0 p O p O O O O O O O O O 0 0 0 0 0 N N ON N N N N N m 3 N N N N N N N N N N N N N N N N N N N N N N N Q of U �yyF o ECL 0 al N C E: o a� 0 LD Z E 2 2 FC d o a $ E m ca m E E c E CM =g Y L la la .� C C a C :ti O 2 > v aci S h y m 0) aai (U d w� � m 2 E r d a r m m LE _a LE v .� E y .�� d w '� u V U U Lou- C .S Q U O' U C � O' U> U w L) N v m m W m W r� W m W w c o c C m. a c > of w p > .a > _vi > .o .� a > vi > oa > p� E w C C. 3 3 � - 2 3 v$ ' i ce -6S Q� g t� I 1 '6 � 3 c ate' in3 n 0- n u a m E m 9� U�vtoi `nvi ��� °' U,v_ � ~�? �U) �w.c ��> U o m y o` u c u c a s o �° o j p n c m 'v n c rn n u a o L° o m o o> c `o ?� E c U U a- a z H U a z (A a z ❑ in a z H Q: LL a z U> w a LL z LL N 0 � a «O m C m �SSy E CL 0 0a !n N 050"0 �" i0 N 7 v p U) N S L co (n (n 7 N a �O d W U 0 (0 co p (n U) p fn p_ U p N p ! 8 .N... 1 U op o v �% d U (� M — v> �+ a cn °�° a s v~i U) a n cn a (n w a° n a (n rq ~ zzz�Zz azzz �z2z ~zzz zzz wof a2z �1, g5 co w w w w w W W W w w w wW w F w w w F w w F c c rn cn (7 (7 U (9 U N U' C7 C9 (o 0 C7 (7 (n (D (7 C7 N V) C7 (7 C7 to U) � U O U U 0 E 2 - 0 n g u+i 2 v OO 3 m� m. °. a2 2 2 2 2 2 a 2 y w m o > y h a>> E o 0 O H a) (Oq N 01 {C5 T F- N O O n F O N �O_/q U 0) N > O .. s. Y >> '� v �% 9 Y V c V.D V o y v v U j E 3 7 a (� U L N N a ac4> a u v a> n > o.L m a> n v �> ° a 0> i naEi a s c m 7 , a a 5 m m c e m o W c o w o w U 'o W K 'o W E rn 'o C7 E a s o❑a mLL a. — aE ❑a—zy wa v �a E �, •a 5E ti a E E E a v_ v ._ w m ��Q �_ w mm qEq m W W ._ c `o `oNff U J `-' O) U U N U U U O L F� m m m m a Ew .mrt ig: F fn fn !n (n LL lL N = w CL o m } c �zz a�a z E E � � 00 W N EEEE� •t ve Y n U) SE Y Y •E ; A E 3 •E nw ; ,(� ,-'SC •lam � G CI .� Q1 Ol 'o s N � � O t L L L O VIA 0 0 0 o a� a �� a a L 4}`( 'n Nyy My w 1 ;! D y— ; > U U U U 4 m m ,� o O O O m A m o O N m m g x x x a o x W- x O w x O a CJ d r 12 61 o 12 A A a� E E Yv L E E a, w Y •E ; Y E 5, p Y E t E o c o � s d a:2 v v a N m; YC .�- E pCj e N N j �O � E a a a a u o. a n a s CL � of o. � x ix O x x O V- x wa a: s •- Fo- a v v v v v v n �n (n u2 (o w m (o n n n n o0 0o ao ao 0o m rn n m m m w°�-• £ 0 0 0 0 0 0 0 p O p O O O O O O O O O 0 0 0 0 0 N N ON N N N N N m 3 N N N N N N N N N N N N N N N N N N N N N N N Q of U �yyF o ECL 0 al N C E: o a� 0 LD Z E 2 2 FC d o a $ E m ca m E E c E CM =g Y L la la .� C C a C :ti O 2 > v aci S h y m 0) aai (U d w� � m 2 E r d a r m m LE _a LE v .� E y .�� d w '� u V U U Lou- C .S Q U O' U C � O' U> U w L) N v m m W m W r� W m W w c o c C m. a c > of w p > .a > _vi > .o .� a > vi > oa > p� E w C C. 3 3 � - 2 3 v$ ' i ce -6S Q� g t� I 1 '6 � 3 c ate' in3 n 0- n u a m E m 9� U�vtoi `nvi ��� °' U,v_ � ~�? �U) �w.c ��> U o m y o` u c u c a s o �° o j p n c m 'v n c rn n u a o L° o m o o> c `o ?� E c U U a- a z H U a z (A a z ❑ in a z H Q: LL a z U> w a LL z LL N 0 � a «O m C m �SSy E CL 0 0a !n N 050"0 �" i0 N 7 v p U) N S L co (n (n 7 N a �O d W U 0 (0 co p (n U) p fn p_ U p N p ! 8 .N... 1 U op o v �% d U (� M — v> �+ a cn °�° a s v~i U) a n cn a (n w a° n a (n rq ~ zzz�Zz azzz �z2z ~zzz zzz wof a2z �1, g5 co w w w w w W W W w w w wW w F w w w F w w F c c rn cn (7 (7 U (9 U N U' C7 C9 (o 0 C7 (7 (n (D (7 C7 N V) C7 (7 C7 to U) � U O U U 0 E 2 - 0 n g u+i 2 v OO 3 m� m. °. a2 2 2 2 2 2 a 2 y w m o > y h a>> E o 0 O H a) (Oq N 01 {C5 T F- N O O n F O N �O_/q U 0) N > O .. s. Y >> '� v �% 9 Y V c V.D V o y v v U j E 3 7 a (� U L N N a ac4> a u v a> n > o.L m a> n v �> ° a 0> i naEi a s c m 7 , a a 5 m m c e m o W c o w o w U 'o W K 'o W E rn 'o C7 E a s o❑a mLL a. — aE ❑a—zy wa v �a E �, •a 5E ti a E E E a v_ v ._ w m ��Q �_ w mm qEq m W W ._ c `o `oNff U J `-' O) U U N U U U O L F� m m m m a Ew .mrt ig: F fn fn !n (n LL lL N = w CL o m } c �zz a�a z City of Bainbridge Island FLEET and EQUIPMENT CIP (2014 - 2019) i-LCET F KkJjrzf- I D - 6 -Yf AR Crew Cab Truck with plow and tilt bed 3/4 ton Pickup Truck w /tank Crew Cab Truck with plow and tilt bed Police Vehicles {3} .._. - - — — Small Capital Equip <$1o,000 _ Financial System Replacement Roadside Mower — 444.4 Medium Duty Pickup Truck Police Vehicles (3) Small Capital Equip <$20,000 Sweeper Police Vehicles (3) Small Capital Equip <$10,000 Phone System Cab and Chassis Medium Duty Pickup Truck Police Vehicles (3) Small Capital Equip =$10,000 _ Roadside Mower chipper— _. _ Commercial Lawn Mower Police Vehicles (3) — Small Capital Equip <$10,000 Roller Compactor w Trailer Pup Trailer _ _ -- — Van Light Duty Pick Up T Police Vehicles (3) Emergency Generator Shoulder Gravel Conveyor _ - — Small Sander Attachment __. FLE'El' P#dOJECTS - xpa- YEAr� CIP Annual - Fleet Replacement Annual - Small Capital Equip <$1o,000 Annual - IT Equipment Capital Items TOTALS . �..,,. — - 65 65 Sol _ 200 96 41 - - - -- 14 143 10 . ' o; -.' °` o; �. ....... 50 —, -- 50 68 10 '10 10 -10 10 ,. 83 2,1 6 F3 _ 7`i I 10 to 10 10 20 - — 35 _ - i 2i 29 : - -- — ..... .... 7 Y 7 7 -7 _Q _ — 15 f a 7 0 -- . x RJ _ __ -- � . . . ... ........... . 4444 551,.z6 454 _ ........._...... � -- C]� OL aa� c _ �l En'v, aaxa- Project r 1l 207 u1. v1 2014 5 207117 -20171 2018 20191 -4033 i-LCET F KkJjrzf- I D - 6 -Yf AR Crew Cab Truck with plow and tilt bed 3/4 ton Pickup Truck w /tank Crew Cab Truck with plow and tilt bed Police Vehicles {3} .._. - - — — Small Capital Equip <$1o,000 _ Financial System Replacement Roadside Mower — 444.4 Medium Duty Pickup Truck Police Vehicles (3) Small Capital Equip <$20,000 Sweeper Police Vehicles (3) Small Capital Equip <$10,000 Phone System Cab and Chassis Medium Duty Pickup Truck Police Vehicles (3) Small Capital Equip =$10,000 _ Roadside Mower chipper— _. _ Commercial Lawn Mower Police Vehicles (3) — Small Capital Equip <$10,000 Roller Compactor w Trailer Pup Trailer _ _ -- — Van Light Duty Pick Up T Police Vehicles (3) Emergency Generator Shoulder Gravel Conveyor _ - — Small Sander Attachment __. FLE'El' P#dOJECTS - xpa- YEAr� CIP Annual - Fleet Replacement Annual - Small Capital Equip <$1o,000 Annual - IT Equipment Capital Items TOTALS . �..,,. — - 65 65 Sol _ 200 96 41 - - - -- 14 143 10 . ' o; -.' °` o; �. ....... 50 —, -- 50 68 10 '10 10 -10 10 ,. 83 2,1 6 F3 _ 7`i I 10 to 10 10 20 - — 35 _ - i 2i 29 : - -- — ..... .... 7 Y 7 7 -7 _Q _ — 15 f a 7 0 -- . x RJ _ __ -- � . . . ... ........... . 4444 551,.z6 454 _ _ 176 _ 1 4 35 58 41 35 _ ?56 6 X51 50 _ I� _ -- TBD 700 417 428 14050 —49 Amounts in thousands Section Five 2014 — 2019 Capital Improvement Project Plan List Water Utility G J_ H W LW W W Iz LZ�1 lZi� LZ�1. CL 0 ` f0 0 f0 NNE c c c C c c c 0 0 0 0 0 0 n a n c. 0. n n N o n E d d d a�E a re n a a s ro N lC �V N aEi a�Ei T T i T i > p m m N C C C C C CC° E E E E E E c c c c c c °c m d d d a) E y a 0 _ 0 , C LC L s N (�tn�i'tnt�rn v v d m o V Zr o F o 0 0 $' o o E m �io c E N V7 �O h o0 u'1 a7 h h O g m 0 0 0 0 0 0 N N N N N N o O O O O O O O N N N N N N N N O a IEL } N 0 O ` Q1 r C O '� w } 9 N d r d 0 d N U O O O O O O A L m c n 0 a) c 0n v c c m o 2D 2 2 2 2 2 3 3 � co r c yy yy yy yy 02 O O Tw m N (a n Ol N . G O O_ a a n 0- d =3 L _0 N w O a a1 a ^ d 2 .2 2 d d n CL - N 0 N Z o E E E E E E a�i CD a) 3: d a N a) � O N > n c 0 - 2 O 4 > > > > > mo w v m L cL m o CL d 0_ G G O. N N w 6 N o p d E (L CL CL d m m N T F H Z Z W of K N W (0 rn a) C C � x0 `O D a) 2 O 272 .2 C m M a a y a) N N N O O C C U. •X jp al a) 0 O O E E E E E E c C C () a) m m m m m m 0 0 0 0 0 2 c .4' N E _ a a a a a a 2 s q o m n �> c c c c c c 0 0 0 0 0 0 [2 Ti 0 U 0 c 2 O/ N '0 0 m 0 n ,c o 0 E E Z 2 2 Z Z an dy aD d aD C7 a o U m °- c X 0 0 y In a2i -_ a- CL (L a- CY ao `° a) 4N V Z 0 c. 'o _ CO V 4 Ql w w U V ¢ ¢ ¢ ¢ ¢ ¢ E) a ¢> y t y (D aa) O } 0 0 N j� C c m_ C Z Z d m 0 0 0 0 N N N N N N W LL City of Bainbridge Island Water CIP (2014 - 2019) Mir .IL P'rdject Location (2 ) ` 2014 2015 , 2016 2017 1 2018 12019 2020 2033 iillli,:ii PR09 I'S,76) YUAR 'C (0`111 Annual Preservation Program 1 Emergency Power Generator iHead of the Bay Wing Point Way Taylor Avenue Well _ .._...- — .— _ _ ......... _ _. Sands Well . #2 ....., _ —..__ High School Reservoir -- - -- - -- -- Fletcher Bay Well 4dV.' Wyatt High Zone Main Madison - Grow — - — -- - _ ........ TOTALS.,... ........... .......................... .................. _. - — - 144 105 10 - ®_ 147 „ TBD 25 541 148 TBD 157 2,170 ........ 151 154 311 2 26.6 — T 140 TBD _ _. - .:..:.'i 259 .2,170 157 713 459 2,55 7 154 Amounts in thousands City of Bainbridge Island — Capital Project Summary Water System Annual Preservation Program Water System Wide ......_.... DESCRIPTION This project addresses water system wide, water system preservation projects. Specific projects are still to be determined. Typical projects will include pipe replacement, water valve replacement/repairs, water meter replacement /repairs, pressure reducing station repairs, etc, BENEFIT Improved water system reliability and increased system life. SCHEDULE Identify project needs and design and construct in 2014. CATEGORY Deficiency 1B, M, SC PROJECTCOSTS (�,ouo's� '_ 2014 2015 2o16 20171 2o18' 2011 Design /permitting 14. 15 _ .15 �5 _. 15. __. 16 ROW 0 0 0 0 of o Construction 1301 1321 1331 :L36 31 141 $148 $1511 $154-1 $157. Sub -total $144 $1471 FUND SOURCES I I i , Water Fund 144 147 148' 151 1541 157 Grant oI o of o o' 0 Sub -total 1 $1441 $147' $148 1 $151 $154, $157 City of Bainbridge Island — Capital Project Summary Emergency Power Generator Installation Head of the Bay Well Field DESCRIPTION This project will install emergency power generators at the Head of the Bay well field. -- .................. BENEFIT Increased system reliability during power outages. SCHEDULE Design and construct one generator in 2014. CATEGORY Deficier�c :LB,E SSC _ PROJECT COSTS (a,000' Desgn� permitting ROW Construction Sub -total FUND SOURCES ci 000's Water Fund Grant Su b -total 2011 2015 10 0 i j $0 105 0 01 - -101 $o I_ 2o3.61 20171 2018' 201 i . $o $0 $01 _ $0 i i $0 $o $ol $o City of Bainbridge Island — Capital Project Summary Wing PointWayReconstruction (From FernclifF to Park) DESCRIPTION Reconstruct roadway surfacing and drainage. Provide sidewalk, on the downhill side, and 2oi6i shoulders, on the uphill side. Water and sewer utility repairs maybe added. BENEFIT Preservation, safety enhancement, & non - motorized level of service. SCHEDULE The City received grant funding for the design phase in the summer of 2013. The City contracted with HDR. Design is starting in late 2013 and will continue with permitting, easement 100 _ _75 procurement in 2014. The City plans to submit for additional grant funding in 2014 for the -- construction phase. . M /E, GC, Tier a.(Current Deficiency), Priority A. CATEGORY $a ^ $0 $0 i { { F DESCRIPTION Reconstruct roadway surfacing and drainage. Provide sidewalk, on the downhill side, and 2oi6i shoulders, on the uphill side. Water and sewer utility repairs maybe added. BENEFIT Preservation, safety enhancement, & non - motorized level of service. SCHEDULE The City received grant funding for the design phase in the summer of 2013. The City contracted with HDR. Design is starting in late 2013 and will continue with permitting, easement 100 _ _75 procurement in 2014. The City plans to submit for additional grant funding in 2014 for the -- construction phase. . M /E, GC, Tier a.(Current Deficiency), Priority A. CATEGORY PROJECT COSTS (s,000's) 201 20 - IS 2oi6i 201Z 2028 201c) -- . ..... .......... Design /permitting 456 I ROW 0- µ01 100 _ _75 -- Construction Sub -total $456r 1 $soot $1,614 $a ^ $0 $0 FUND SOURCES Street Fun_ d 123 100 283 SSWM Fund 5 TBD Water so TBD Sewer 1 TB D Grant 3031. 2331J _ $soo si,63.4' $o $o $o Sub -total $456 Section Six 2014 — 2019 Capital Improvement Project Plan List Sewer Utility J_ D w W W U) C C ep O x ro z z z z z z z ❑ ca z z z d u7 u7 u7 u7 u7 u� u7 u7 u7 u7 ° c m m C C C C C C O O O O O O a > > CL a L L L L L L d d d d aa� E w� E a$ a a�Ei m a�Ei v ° N ma- N N N N N � W N N N N N N E C �� 9 m N y _O 0 0 0 0 0 0 �' E E E E 2 co N d O N 71 C Lam+ D CL (L rn E E O C, 0 0 0 0 0 0 0 0 o N N N N N N N N N T O d a ¢ E N r O C 1O O D a 0. N N N N En N N N L .c L L L C a�°� mmmmmm m-- E E E E E E E m> E m C C_ C_ C d o 0 0 T n°� C _C _C r a n n _n _n _n Al. _ n c d `) d O a 0 r- a n a a a a a o �o C C C C C C O C '5 u E m a) E E� E E E E t t5 v R a 3 m m pE� p 0 0 0 0 0 ,2`o o m o.0 3 am m m N zv C 0 C C C C C C C C C L o m O N pJ a 'C m m m m m m ° m o E aN 2i, 211 Z'Z'Zl 41 c a ._ ._ ._ mccc m m m v v o•- .-> = > 5 > > > 5 E > ;a •°- c cr3 cry a E C7 (D U C7 C7 U` LL C7 5 w N ZI n T '0 m �- m o c� E CL .D -6 0 (n m _n CD N U d O O C O .m+ O O C (n L C s m O d , m o a m m c o o o (= ° ❑❑❑o❑❑ m LAC `n M E 8 (D JO m cc co F- ~ W 3 z J U) CL U `7 y c d N N N N d O N m 3 3 3 3 3 3 3 3 3 N 3 m m o c c LL (n 0 (n co (n (n (n (n U) O• m N N � O O E E E E E E N 2 2 m m E E c n 2 w m m m rn m m 0 0 0 0 0 2 g s m E •c° 5 ` aci aci m aanan.aa N rom a >> > 0 C c C C C C j O O 0 0 0 O mmmromm m p> 9 m 0 IL d Q SEE 2 z Z 2 Z 2 g c R> m' 'Z `0 w m w N N N E 4 ma c 0 d v d 2 2 d � c Z 0 w w? aNi c� aaaaaa m -�' a�cmm sa- 'e Cj m 0 w w is cl, D v Q Q Q Q Q Q o in re n t m a> z m o d v (o w m c c E - z IL } 0 0 0 0 0 0 m w N N N N N N LT S J d. CL Lu Z City of Bainbridge Island Sewer CIP (2014 - 2019) Protect I Location and/or Phase SEVER PROJECTS - 6 -YFAR CIP. Annual Preservation Program Eagle Harbor Sewer Beach Mains Eagle Harbor Design/ ROW _ Construction Northtown Woods & Portable Generator Plugs Lynwood Center Wing Point Way Sewer Design / ROW Construction SEWER �ROjECTS.- 2:0 -YEAR CIP Pump Station Upgrade - Various Madison - Grow Pump Station Upgrade - Village WWTP Upgrade - Various 8�r.�j i 2020 2015 2016 2017 , 2018 i 2019 2033 p. I 146 14971 152 155 158 161 ! 2,240 3,985 i 325 4,045 25 y.j 15 TBD - _ TBD —_ TOTALS .......... ..................... >......... .x i,. 4,556 149. 152 155 158 ! 161 Amounts in thousands City of Bainbridge Island — Capital Project Summary Annual Sanitary Sewer System Rehabilitation Program Sewer System Wide DESCRIPTION BENEFIT This project addresses sanitary sewer system wide system preservation projects. Specific projects are still to be determined. Typical projects will include pipe repair/replacement, in flow/infiltration elimination, manhole repair, etc. Improved system reliability and life span; increased capacity resulting from I &I elimination. SCHEDULE Design and construct in 2014 CATEGORY Deficiency 113, Eft SC PROJECTCOSTS (3,c�oo's1 201 2015 2o161 I 2018^ 201 Desiqn /permitting s6 3.5! -- - 15 16 16 16 _.._ ROW Construction 1301 134 137, ?, 242v. i 1 Sub -total $.w/06i $149 $152 $15, $158 $161 IIFUND SOURCES (i,000 °s) k Sewer Fund 1461 1491 152 15;i 158'_ 161 Grant I Sub - total $146 $14g w152 $155; $1.58 $161 City of Bainbridge Island — Capital Project Summary Eagle Harbor Beach Mains Replacement Project SR 305 & Wing Point Lift Stations to WWTP WWTP to Wing Point Effluent Outfall DESCRIPTION ' BENEFIT SCHEDULE CATEGORY J This project provides for replacement of the sewer force mains on the Eagle Harbor Beach from the SR 305 and Wing Point Lift Stations to the WWTP and from the WWTP to the Wing Point eff luent outfaIi line. These existing ductile iron force mains are over 40 years old and have failed a number of times in the past few years spilling raw sewage into Eagle Harbor. The project will replace the existing ductile iron lines with high density polyethylene (HDPE) plastic force mains designed for highly corrosive environments. System reliability and environmental imravement. Desi In and Ri ht of Way 203-31201.4 and construct in 2514 Deficiency 3.13, E/N; SC PROJECT COSTS (i,000's) I 2014 201 I Design /permitting T 275 ROW - - - Construction —so 4,0451 Sub -total $4,3701_ $o FUND SOURCES (a,aav's) I Sewer Fund 385_ PWTF Loan 3,985 0 Sub -total $4,370 $o 2o16 20171 20181 2 e $o $o $ol $ol $o so! $ol $0 City of Bainbridge Island — Capital Project Summary Lift Station Generator Plugs North Town Woods and Lynwood Center 0;.1 n"I . I R M1,4 np !) DESCRIPTION This project provides installation of emergency generator plugs at the City's North Town Woods and Lynwood Center sanitary sewer lift stations. These new plugs will allow direct plug in of the City's portable emergency generators at these two lift stations in case of a power outage. Installation of these plugs at these two facilities will mean that all city lift stations using portable generators for their emergency power source will have the same standard generator plug in capability. BENEFIT Safety and system reliability SCHEDULE Design and construct in 2014 CATEGORY Deficiency 2B, M; SC PROJECTCOSTS (z,000 -s) 2014 203.q 2o16 2017i zo18 2019 Design /permitting 2 ROW 0 Construction 2� $25 $ol $o! $o $o $o Sub -total IFUND SOURCES (i,000's) I Sewer Fund 25 _ 'Grant 0 0 $25 1 $01 $o $o $o _ $o Sub -total City of Bainbridge Island — Capital Project Summary Wing PointWayReconstruction (From Ferncliff to Park) i DESCRIPTION Reconstruct roadway surfacing and drainage. Provide sidewalk, on the downhill side, and shoulders, on the uphill side. Water and sewer utility repairs maybe added, BENEFIT Preservation, safety enhancement, & non - motorized level of service. SCHEDULE The City received grant funding for the design phase in the summer of 2013. The City contracted with HDR. Design is starting in late 2013 and will continue with permitting, easement procurement in 2014. The City plans to submit for additional grant funding in 2014 for the construction phase. CATEGORY M/E, GC, Tier 1(Current Deficiency), Priority A. PROJECTCOSTS (z,000's)' �' 2014 20151 2o16i 2017 2o18 2019 - - - - -- Design /permittinq 45 56 ROW — o — - -soo� 75 Construction 0 1539 $o! $o Sub -total $456 $cool $1,614 $ol FUND SOURCES Street Fund 12.; 100 283' - - SSWM Fund 5 TBDI Water 10 TBDI Sewer 15 TBD Grant 303 1 1 $soo $1,614 $0I $o: $o Sub -total $456 Section Seven 2014 — 2019 Capital Improvement Project Plan List Stormwater Utility a J H W F- O I" N E 'w O 0 c 1 1= N } pl n N 22 ri 2f2 22Om 2- i°3 22 i i 22 22 2 i f2 C C C tt ot rot 0 di t_ L O •G c c c C C { c c C c C c c 0 g o 0 0„ �¢ o oss gg Q o ojg� m y y -6 47 '$ c tf t3 y L 'tS 'Ti 43 $ 2 m �2L_= .91 8o0$�O�ocgcie°�v 00 0 0 $ UV t°>v by cici Z ea $ ' Q ' 0 oe -d -6 a -a E oe 0 g C c c C , O O ❑O O O 000ty ❑006 ❑ U r O O 0 0000000000 0 0 0 0 0000 000 000 (� dryNd od d¢d N N N N N N N N N N N N N N N N N N N N N N N N N N N N 0 0 O O O O 00 O �b�" O N N N N N N N N N N }yyyyyyoyr 0 }0} y y yy} o }yyy }> }yy m al 0 d cc � `N > W Q o GI 3 0 IV d Ol H 2 N° B 0 N N N VI N a 'E E Sys �NN 0. n 8. a n C C C 42 Vi V! VI g>j r , tii Toi 4 t7S a+ U ° 0 E c t t O) 3 ; c 2 or v 2 2 y� o 1S b C ,O i%i N Y Vl L Vl N 10 Cp E k 4- 2 N g �0. 22° `83 g c Q N o aL°L c i v E a- $ w w $ $ v 8 8LL Y� v 'E E v m a m mon E2mv d v ac ,��c m a� m 8 m w m d> w w m0 2 'o E m N 3 o a d E ,E 28 a� 8c oo 8L Scv m �� �a m w J c f0 0) N N l0 10 �• J C C ?i "' ° pp C L C C? C C ° C p�7 C ❑ c L t C ppc f0 ❑ U 0 z fn fn U U ICJ U U U U U U iL' U {- U H U U LL LL U U 0: U f- o m m is U c o >�c wa U uim E o 'ov —❑ 'C LL O« O Y 10 C co U) N c c c d E 0011 p w c O m❑ F- v m m 0 $ 0 U) it n'nF >� i i = F mF n U) N U) m co y co U) (7 w N co N fn (n (U y 0 w N N N N co 0 uJ N V) U) (n fn UW) F- V1 N U) uJ V) N m f0 fq U) fq m to O O O tV�E�jj( W 41 v m m a. .� q 4• ro f F- N 01 J O Wr 9� m !0 Q 3 gQ Y 3 ,XI v 3 .2— a ° m O "✓� ,a U ) w ` w av��1 ° ; �°C w �a S m i y a_m d 5ro `c c c c me f° Urn =Q U U do [K k* m .� .ct ;r+ • dL Q = m d` m .r Y u q"z! Sy vt 414nr co r m a? .m m y 9E yl $ L o m ii 1 r 9 S' 2 3 S? 1:= iv R1 5 iv n _0101 w. a `am E a aEi 0 O O w 8 � Z S� c N Y/i N r 'a C O1 'a � Z N O 01 � yl 01 O O O IO O 10° T ME x� ro d v c ° a O 16 O N n `m w� _.5.9 0 �I 0x1 N ooa . m v N > > O Q E E C O O m m 5 E w a3 �zz iwz City of Bainbridge Island Storm water CIP (2014 - 2019) N o;ect CL Q F+ v Q ro C LL n` V 2014 2015 2016 2017 2018 20191 2020- 2033 s -rq iMWATER PROJEL S - 6 -VEAW r „l 2014 Annual Stormwater Preservation --- Hidden Cove Estates (2014) 2015 - 2019 Annual Stormwater Preservation Manual Road (2015) Other Projects TBD Fort Ward Hill Reconstruction Dripping Water Creek Lynwood Center Outfall „ T Valley (with Reconstruction project) Wardwell (with Reconstruction project) NE Mountain View Yeomalt Area ICnetchel Way - —� Wing Point Way (with Reconstruction /ISM project },,. Blakely Falls Creek Waterfront Park Outfall Eagle Harbor Drive 5tUW'U'UrA'f-fR`Fk6TrCT5 - 20 -YFAR C #P, � d Annual Stormwater Preservation - Projects TBD Wardwell High School Road /Fletcher Bay Pleasant Beach Road Hall's Hill Blakely Avenue Country Club Road Deep Culvert Preservation Assessment Winslow Way East Outfall Madison Street Outfall Port Orchard Passage TMDL Related Projects TOTALS.. ... 100 13 200 173 231 120 _281 280 285 29.1 297 _ _.. V V V V 60 60 V V — 13 60 r 60 20 5 -_ -- TBD ISO 170 150 - 5,239 TBD TBD TBD TBD TBD TBD TBD i 862 — 601 3 { 280 TBD _TBD -- TBD 5,239 _. � 435 291 297 Amounts in thousands City of Bainbridge Island — Capital Proj*ect Summary Fort Ward Hill Reconstruction & Shoulder Widening Phase 2 (Sunny Hill to Bolero Drive) r1_4411 rl _TT sk _11 Aa tvj A U __J & . . ............ . DESCRIPTION Reconstruction of approximately 1,5oo LF of roadway. Improvements consist of repair & paving of two:1o'travel lanes with 5' paved shoulders, approximately 70o LF of guardrail, new rockeries, new storm drain systems and two new drainage culvert replacements. BENEFIT Preservation, safety enhancement, & non-motorized level of service, SCHEDULE Design/permitting phases are estimated to be completed by 2012 year-end with construction to occur in summer Of 2014. CATEGORY _I Preservation, 3.A, M GC PROJECT COSTS (:L,000's) 2014 20151 2016i 2o17._.. 2o18l 201c) d Design/permitting 0 ROW 0 Construction 6 — Sub-total sg65 $o $o. $o! $0 FUND SOURCES (:L,000'S) Street Fund SSWM Fund 13 856 ,Grant Sub-total $965 $01 $O, $0 $0 $0 City of Bainbridge Island — Capital Project Summary Dripping Water Creek Fish Passage Culvert Project (Sunrise north of pay) '-Is2Q 90 d 6rSrw G1M SVlzAa" !-. f 1 f FT_ DESCRIPTION Replacement of a failing culvert with anew fish passage culvert. The design was completed in 2013. Construction has been delayed to 2014 due to higher than anticipated construction costs as better estimate information was developed in design and a funding shortfall in 2013. BENEFIT Addresses a priority 1 repair, Replaces a failing culvert and addresses fish passage. SCHEDULE Construction in summer of 2014. CATEGORY I M /E, GC, Tleri, Priority A PROJECT COSTS (1,00a "si i 20141 201 2o16l 2017 2o3.81 2019 Design /permitting 01 ROW 0 - Construction j 200 Sub -total I $2001 $o $o $0 $o $o FUND SOURCES ti, ❑oo sj Street Fund 0 SSWM Fund zoo Grant o S�Sub-total $200 $o $ol $o $o $o — City of Bainbridge Island — Capital Project Summary Lynwood Center Outfall Improvement Project Point White Drive near Lynwood Center) DESCRIPTION BENEFIT SCHEDULE CATEGORY Provides for roadway drainage improvements, upgrading of closed conveyances, and a gate valve at the shoreline outfall to improve water quality. 75% of the project ($173K) is funded by the DOE Statewide Stormwater Grant Program. The project will reduce standing water on Point White Drive and address odor and maintenance problems with the outfall and flat conveyance _ system. _ - ....... Construction in summer of 2014. M /E, GC, Tier 3, Priorit C PROJECT COSTS (1,000,5) 2014 2015. 2o16 W 201-7 2o18, zos Designlpermitting� o - ROW 0 Construction 231 Sub -total $231 $OF, $01 $o., -- $o — _ so FUND SOURCES Street Fund o SSWM Fund 58 _ ___ DOE Grant 1 Sub- total $231 $o $o $o $o $o City of Bainbridge Island Capital Project Summary Valley Road Reconstruction Project (From Sunrise to Falk) DESCRIPTION Provides for roadway surfacing reconstruction and storm drainage improvements on Valley, and storm drainage improvements to Logg, and Gertie Johnson Roads. This work was identified in the 2012 Area Drainage Study performed by Brown Wheeler Engineering. Note that the majority of the cost is related to stormwater improvements. BENEFIT Preserves surfacing on Valley Road. Addresses stormwater run -off on Valley Road and addresses maintenance problems with the existing storm drainage system at the bottom of Logg Road that have led to overtopping of the conveyance system, Better accommodates fronting rp operty owner stormwater drainage above Gertie Johnson Road which has a history of slides. SCHEDULE Design in winter / spring of 20-14 and Construction in fall of 2014. CATEGORY M, GC, Tier 1(Preservation), Priority A PROJECTCOSTS (1,000's) 1 2014. 2o16 2017! 2018 2019 1 Design /permitting ROW Construction Sub -total FUND SOURCES g9 o 1 $203J .. - $o� $o $0� $0 $0 Street Fund SSWM Fund Grant Sub -total 8� 120 o $20 i $0 $0 $o $o� $o City of Bainbridge Island — Capital Project Summary Wardwell Road Reconstruction Project (From Short of Sportsman's Club to Triple Crown) DESCRIPTION Provides for roadway surfacing reconstruction and storm drainage improvements. The City has received a DOE grant for the design of storm water quality improvements and a fish passage culvert at Woodward Creek. BENEFIT Provides for surfacing repairs. -. Currently the roadway lacks conveyances. The project provides for the construction of the conveyance system for the roadway to reduce ponding and improve water quality. Currently the Woodward Creek culvert over-tops during storm events and does not provide for fish passage. The Grant allows the City to comprehensively address road repair and stormwater drainage at a reduced cost for the City. SCHEDULE Desi n in 2014. Candidate for DOE grant funding in zoaS. CATEGORY M /E, GC, Tier a,, Priority A. PROJECT COSTS (1,000's) Desiqn /permittinq ROW Construction Sub -total FUND SOURCES (z,000,$) Street Fund SSWM Fund DOE Grant Sub-total 2014 2015 20161 2017 2o18 201 6o -- ��— - i- s60l *i * $0 $0L cco o o s6o $o $01 $o City of Bainbridge Island — Capital Project Summary Mountain View Road Reconstruction Project (From Manitou) DESCRIPTION BENEFIT SCHEDULE CATEGORY Provides for roadway surfacing reconstruction and storm drainage improvements on Mountain View. Work includes upgrading the inlet condition at the outfall to address a capacity deficiency. This work was identified in the 2012 Area Drainage Study performed by Brown Wheeler Engineering. Note that a significant portion of the work is associated with stormw_ater improvements. _ Provides for surfacing repairs. Currently the roadway lacks conveyances for storm water. The project provides for conveying storm water and improves the capacity of the existing outfall. Providing conveyances better accommodates fronting property owner stormwater drainage above Gertie Johnson Road and Rolling Bay Walk which has a history of slides. Design in winter/ spring of 203.4 and Construction in fall of 20 4. M /E. GC, Tier :1, Priority A PROJECTCOSTS (i,000's) 201 201 20i6 2017 2o-18l 201 Design /permitting 32 E ROW — ° Construction 107 Sub -total -$139 $o $o $.o $0. $o FUND SOURCES Street Fund 86 SSWM Fund3 Grant o _ Sub -total $139 $ofi $o $o $o $o I __ - City of Bainbridge Island — Capital Proj*ect Summary Yeomalt Area Drainage Improvements Project (Area bordered by Cherry, Yeomalt Drive, Madrona, and Wing Point Way) ._ -__ - - -- - - -- _. --- 1 -1. .......... ... -. DESCRIPTION Provides for storm drainage improvements in the Yeomalt Area. The City has received a DOE grant for the design of storm water quality improvements and fish passage culvert at Ravine Creek. This work was identified in the 2013 Area Drainage Study performed by Browne Wheeler Engineering BENEFIT Much of the Wing Point area above Yeomalt Point was developed before regulations required conveyance systems. Currently there are drainage problems in many areas and or existing conveyances are inadequate. The grant allows the City to begin to comprehensively address roadway drainage in the Yeomalt area. This work will be coordinated with the current Wing _Point Way Reconstruction project which will provide for some of the needed improvements. SCHEDULE Design in 2014. Possible candidate for grant funding in 2015. CATEGORY FIN, GC, Tier 1, Priority A. PROJECT COSTS (a,00v's� __2014- 2015i 2o-i6 I 202 Design /permitting 6o' ROW Construction o Sub -total $6o * * $0 FUND SOURCES (a.,000's) Street Fund SSWM Fund iDOE Grant Sub -total 0: o *I 6o $6o * * $o zo18J 201.9 $0, $0 $01 $o City of Bainbridge Island — Capital Project Summary Knetchel Way Surfacing and Drainage Repairs Special Project (From Madison to Ericksen) DESCRIPTION This local access roadway is in poor condition. Proposed work includes approximately 28o feet of curb and gutter infill and associated catch basins and tight line drainage improvements. Also included is the installation of anew catch basin and drainpipe at a flatter area. Surfacing repairs include extensive patching and thin asphalt overlay. An estimate has not been completed but the construction cost is thought to be on the order of $1ooK. Sidewalk inf ill maybe added for an additional $2oK. The design would be completed in house. Thin asphalt overlays are relatively new to the local industry and this could be a pilot project for the City. Thin overlays maybe referred to chip seals for low volume curb and gutter streets in urban zoned areas. BENEFIT Preservation _ SCHEDULE Design and Construction in one year. CATEGORY MI E, GC, Tier i(Current Deficiency), Priority A. PROJECTCOSTS (1,000'5) F 201 2015 2o16 2o18 201 Design /permitting o .2017 ROW o Construction 120 Sub -total $120ir of o 01 o' 0 I i ,FUND SOURCES (1,000'1) IStreet Fund 3.001 _ (Storm Drain Fund 20 Water I Sewer STP Grant Sub -total $120 _ 0 0 0 01 0 City of Bainbridge Island — Capital Project Summary Wing PointWayReconstruction (From Ferndiff to Park) ;. iV7ll i tl I p ��l J l3. f DESCRIPTION Reconstruct roadway surfacing and drainage. Provide sidewalk, on the downhill side, and shoulders, on the uphill side. Water and sewer utility repairs maybe added. BENEFIT Preservation, safety enhancement, & non - motorized level of service, SCHEDULE The City received grant funding for the design phase in the summer of 203.3. The City contracted with HDR. Design is starting in late 203.3 and will continue with permitting, easement procurement in 203.4. The City plans to submit for additional grant funding in 203.4 for the construction phase. CATEGORY M /E, GC, Tieri(Current Deficient) Priorit A. PROJECTCOSTS (i,000's) Desjgn /permitting_ ROW — Construction Sub -total FUND SOURCES Street Fund SSWM Fund Water Sewer Grant Sub -total 2024 2015 2o16, 201ZI 2o18 20 o - 100 _75 1 0 1 X4 6 - $3.001 $1,6141 $01 $01 $0 12 . 110P. 283 5 TBD I I 10 TBD, f 15 TBD J - - - o .I 1-331 R $456 $100 $3.,614. $0 $0: